Timelines for swath of Victorian construction projects blow out

Timelines for swath of Victorian construction projects blow out

On the road network, the duplication of the Western Highway between Ballarat and Stawell still has no firm completion date despite being slated for 2021. The government's Big Build website says planning for the final section is still under way.
Another project renewing sections of the Great Ocean Road, forecast to be completed this year, is expected to be four to six months behind schedule after already being pushed back from as far back as 2020.
The Big Housing Build, a 2020 state government commitment to build 12,000 social and affordable homes over four years, is now forecast to be completed in 2028.
The government says the $6.3 billion project will now deliver 13,300 social and affordable homes, with work on 10,100 complete or under way.
A government spokesperson said the auditor-general's report was a 'snapshot in time' and information was provided 12 months ago. Other delays outlined in the report are no longer accurate and have not been included in this article.
Loading
'Since then, works have progressed, with Victorians reaping the benefits from these vital major projects across the state,' the spokesperson said.
Opposition major projects spokesman Evan Mulholland said the government's management of projects had become a 'slow-motion disaster'.
'Victorians pay the price with added costs and delayed projects because we have a government that rewards union thuggery instead of demanding accountability,' Mulholland said.
Improvements to Victoria's male prison system capacity, first forecast for 2023, are also delayed and unlikely to stay within budget because of black mould infestations affecting hundreds of new beds at Barwon Prison in Lara and the Metropolitan Remand Centre in Ravenhall.
The Department of Justice and Community safety is currently negotiating with the contractors of the prison project and argues the works were not completed to standard.
Infrastructure Australia's market capacity report, published in December 2024, said investment in transport projects was falling as billions of dollars more in funding flowed to energy and housing projects.
Chief executive Adam Copp said at the time that the nation's infrastructure ambitions were being challenged by skills shortages, stagnant productivity growth and the rising costs of materials.
'Construction materials on average cost around 30 per cent more than they did three years ago, and with ongoing skills shortages we simply don't have the people power we need to get the job done on time – our analysis shows 7 per cent of the pipeline, or $15 billion of planned construction work, has been hampered by project delays,' Copp said in the report.
Loading
Copp said projects would also shift into regional areas and northern Australia, which would bring other challenges in attracting workers and supplying materials.
Roads Australia chief executive Ehssan Veiszadeh has previously warned of the impact of delays, particularly those linked to union action.
The peak body's members reported that repeated construction delays and poorer working environments added 30 per cent to the total costs of projects.
'On major public infrastructure worksites, workplace safety has not only been undermined – it has been weaponised,' Veiszadeh said.
'Worksites have been shut down for spurious reasons, sometimes costing up to $5 million a day. Often industrial action has targeted critical works such as concrete pours, which can have a cost impact of tens of millions of dollars.'
This masthead's Building Bad investigation has detailed allegations of serious misconduct across government sites over the past year, including allegations gangland-linked figures were receiving large payments from companies on publicly funded projects looking to gain favour with figures within the CFMEU.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Deafening silence is government's shameful habit when it comes to taxpayers' money
Deafening silence is government's shameful habit when it comes to taxpayers' money

The Age

time14 hours ago

  • The Age

Deafening silence is government's shameful habit when it comes to taxpayers' money

The state government has a problem. It does not know how or when to speak to people. It seems unable, either through incompetence, ignorance, arrogance or just plain lack of will, to communicate to Victorians about things that will profoundly affect them. Memo premier and ministers, photo ops in high vis at construction sites don't cut it. The latest example of Victorians being left in the dark is the Outer Metropolitan Ring. The Age revealed this week that the OMR, one of the largest transport projects in the state's history, is slowly grinding its way into reality. The plan is for a 100-kilometre rail and road corridor to be carved out in Melbourne's outer north and west. A public acquisition overlay was placed on the corridor 15 years ago. Some might argue this was later than it should have been, but still this was an act of thinking about the future. The state has spent $350 million compensating landowners along the route for taking their property. This is a logical progression from the land reservation if the government plans to proceed with the project. But does it? We know that in 2021-22, the state and federal governments jointly put together $20 million in a preliminary business case. We don't know what it found. A freedom-of-information request by The Age was rejected on the grounds of cabinet confidentiality. This is unacceptable. We can accept confidentiality is necessary on matters such as security. The Outer Metropolitan Ring is a transport project. Victorians should know what is being discussed concerning their money, especially as now at least $350 million has been spent. Acting Premier Jaclyn Symes said this week that the project was 'not a proposal that we're actively considering' but 'preserving land for a future decision is an appropriate course of action'. This walks past The Age 's revelation that the government's own planners warned that the first component of the OMR was needed by 2031 to help address stifling congestion and the growing population in Melbourne's north and west. Then there is the associated freight rail line. This is a crucial part of the project, giving freight trains exclusive use of a 73-kilometre link from Werribee to Beveridge, thus removing them from the suburban rail network.

Taskforce promises action after anti-Semitic attacks
Taskforce promises action after anti-Semitic attacks

Perth Now

time08-07-2025

  • Perth Now

Taskforce promises action after anti-Semitic attacks

An anti-hate taskforce has met for the first time in the wake of a spate of incidents involving Jewish institutions in a major capital city. The taskforce, set up by the Victorian government, heard from a number of stakeholders, including police, Premier Jacinta Allan revealed on Wednesday. It listened to members of the Jewish community, including Zionist Federation of Australia president Jeremy Leibler, all of whom shared their views on how the state can tackle anti-Semitism. It also heard from Victoria Police Chief Commissioner Mike Bush on the force's readiness to act on the criminal components of the Anti-Vilification and Social Cohesion Act. Members were also told about the work of the government's Local Escalation and Help group, set up to facilitate communication between community leaders and the government. "We also discussed the importance of education in combatting anti-Semitism," Ms Allan said in a statement. "We agreed if there were further action we needed to take to keep Victorians safe, we will not hesitate to take it." Ms Allan said the government would introduce to parliament as soon as possible new laws aimed at "stamping out extreme, dangerous and radical public demonstrations." The taskforce will meet again in the coming weeks. The meeting came after worshippers were forced to flee the East Melbourne Synagogue after it was firebombed on the same night Israeli restaurant Miznon in the CBD was targeted by pro-Palestine protesters. Sydney man Angelo Loras, 34, has been charged over Friday night's synagogue firebombing. But Palestinian Australians have accused leaders of political silence, suspicion, hostility or surveillance when it comes to their plight and say they are met with protest crackdowns and threatened with repressive laws. "There have been no task forces, no public statements of care for Palestinians as they watch their loved ones massacred by the genocidal state of Israel, or are targeted by anti-Palestinian racism here in Australia," Australian Palestine Advocacy Network president Nasser Mashni said on Tuesday. Mr Mashni demanded political leaders stop criminalising Palestinian resistance, grief and political expression and engage in meaningful consultation and inclusion in decisions that affect their lives and rights. "The longer political leaders ignore and avoid us, the more obvious their double standards become," he said. Miznon's owners have spoken of the "profound impact" of the incident on Friday. The demonstration outside the Hardware Lane restaurant ended with protesters smashing a glass door, up-ending tables and throwing chairs. About 20 protesters converged on the restaurant, some chanting "death to the IDF" in reference to the Israel Defence Forces. Police on Tuesday charged a 50-year-old Richmond man, a 48-year-old Footscray woman and a 28-year-old Essendon woman with assault, affray, riotous behaviour and criminal damage after another person was arrested and then released for hindering police that night. The restaurant said the actions of a few had caused much distress to customers, patrons and staff in neighbouring restaurants. "We respect everyone's right to their own nationality and religion. We ask for the same," the owners said in an Instagram post. Whistleblowers, Activists and Communities Alliance have claimed responsibility for the protest. Other offenders on Saturday spray-painted cars with anti-Semitic "inferences" then set them alight in the city's northeast, while a fourth incident involved offensive images spray-painted on pillars and walls near a Holocaust museum in Elsternwick.

‘At what cost?': Victorian opposition dismisses poll showing support for Suburban Rail Loop warning the project is a ‘debt bomb'
‘At what cost?': Victorian opposition dismisses poll showing support for Suburban Rail Loop warning the project is a ‘debt bomb'

Sky News AU

time08-07-2025

  • Sky News AU

‘At what cost?': Victorian opposition dismisses poll showing support for Suburban Rail Loop warning the project is a ‘debt bomb'

The Victorian opposition has dismissed polling showing a majority of Victorians support a major Allan government infrastructure project, describing it as a 'debt bomb'. Newspoll results released on Tuesday show a massive 78 per cent of Victorians are fairly worried or very worried about the state's skyrocketing debt levels – which are set to hit $194 billion by 2028-29. However the poll also found 59 per cent of Victorians backed the controversial multi-stage Suburban Rail Loop project, the first stage of which is set to cost more than $34 billion. Opposition Leader Brad Battin dismissed the findings on Tuesday afternoon, telling reporters the question lacked key context. 'It depends on what question you ask. If I said to people, would you like to see a rail loop that goes all the way around Melbourne, they'd say yes. But if I said to you, it's at the cost of the next generations ever getting infrastructure, they'd say no,' Mr Battin said. The comment was echoed by shadow major projects minister Evan Mulholland, who said everyone liked a train, "but they don't like a debt bomb". "A debt bomb is what the Suburban Rail Loop is,' Mr Mulholland added. 'It's Victorians, particularly in the eastern suburbs, but everywhere that will be paying for the suburban rail loop for generations.' Mr Mulholland said the Victorian Liberals and Nationals wanted more new rail, but priority should be given to electrifying rail in outer suburban growth areas. 'It's people in the growth areas, places like Donnybrook and Wallen in my electorate, and Wyndham Vale and Melton that desperately need electrified rail,' he said. 'And we know the government sitting on a secret report which shows that these communities, within five years, are going to be facing crushed conditions where V-Line trains are going to have to skip stations because the government hasn't planned the infrastructure where it is urgent. 'We want electrified rail where it's needed for all Victorians, because you've got people living in third-world conditions in our growth areas. Our fellow Victorians that are suffering, that do not have public transport access where it's needed.' Mr Battin said that in just four years Victoria would be spending $1.2 million every hour in interest on the debt. 'That's more than $10 billion each and every year,' he said. 'That's nearly twice what we spend on Victoria Police during a crime crisis. It's just under what we spend in health during a health crisis. It's more than we spend on education here in Victoria. How can the government justify putting so much money into one project?' The Allan government is yet to outline how it will fund the SRL East - the first of three stages on the project, which will see trains run between Cheltenham and Box Hill. The Victorian government has committed just $11.8 billion towards the project with the Albanese government committing just $2.2 billion, leaving an almost $20 billion black hole – with the Allan government claiming a third of the funding will come from value capture. The multi-stage orbital train line was estimated to cost $50 billion when it was proposed by then-Premier Daniel Andrews ahead of the 2018 state election. However costs have since doubled, with a 2024 report by the Parliamentary Budget Office estimating it will cost $96.4 billion to build the SRL East and SRL North sections of the project. SRL East, which is already being constructed, will see trains running from Cheltenham to Box Hill, with stops in Clayton, Monash, Glen Waverley and Burwood – thereby connecting the Frankston, Pakenham/Cranbourne, Glen Waverley and Lilydale/Belgrade train lines. SRL North will then see this extended from Box Hill to Melbourne Airport, with stops in Doncaster, Heidelberg, Bundoora, Reservoir, Fawkner, and Broadmeadows – connecting the Lilydale/Belgrade line with the Hurstbridge, Mernda, Upfield and Craigieburn lines. The line will then connect to the long-awaited Melbourne airport rail link, which will run from Sunshine to the Airport via Keilor East, with a final SRL West section connecting Werribee to Sunshine.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store