Uganda: The end of the runway? Kabalega airport fabled finish line
Uganda's Kabalega International Airport (KIA) has featured in several budget and State of the Nation addresses, but it has remained at 95 percent completion, and the government now says that the facility will begin operations within the next financial year.
While presenting the budget for the 2025/26 financial year, Finance Minister Matia Kasaija reported that the 'operationalisation of Kabalega International Airport' is one of the 'priority interventions' but did not provide more details.
Mr Kasaija echoed President Yoweri Museveni's statement during the State of the Nation Address on June 5 that the airport is near completion, as part of the requisite infrastructure that the Ugandan government has invested in to support commercial oil production.
But the project has been stuck 'at 95 percent completion' for over two years, lacking an air traffic control tower and other infrastructure, partly due to modifications in the design for a mobile air traffic control tower, which was dropped midway.
The switch to a fixed tower required a redesign of this aspect, which sent the project contractor back to the drawing board, causing delays, according to Amos Muriisa, the contractor's spokesperson.
In the next financial year, the government has allocated Ush6.92 trillion ($1.91 billion) for integrated transport infrastructure, namely roads, bridges, railways, water transport, and air transport, to undertake interventions that include completion of the airport.
Two years ago, the contractor, SBC Uganda Ltd, a joint venture of Israeli-British firms, Shikun and Binui International-SBI, and Colas Ltd, sought to avoid delays and proposed handing over the project to the government, with a plan for the airport's air traffic control to be handled by Entebbe International Airport.
Construction of Uganda's second international airport began in April 2018 and was expected to be completed in 48 months as part of the support infrastructure for oil and gas in the Lake Albert region.
Its completion was planned to coincide with the surge in oil and gas logistics, as oil companies were preparing to ship in heavy equipment ahead of launching field development works at the upstream oil and gas projects Tilenga and Kingfisher, as well as midstream operations of the East African Crude Oil Pipeline (Eacop).
But, as the airport fell behind the timelines, the oil majors shipped all equipment, including four drilling rigs and pipes, by road from Mombasa to the drilling sites in the Albertine Graben.
China National Offshore Oil Corporation launched well spudding at its Kingfisher oilfield on January 24, 2023, while TotalEnergies began drilling six months later at two of the three drilling sites of the Tilenga project.
Funded to the tune of €264 million ($309 million) through loans from the UK Export Finance and Standard Chartered Bank, officials also blame the airport's slow progress on funding shortfalls, as the government delayed disbursing additional funds for the project.
Mr Muriisa said that Covid-19 restrictions disrupted the pace of construction, as the contractor was compelled to halve the workforce, per Ministry of Health directives.
The airport was intended to support Uganda's oil and gas upstream and midstream operations by facilitating the transportation of heavy equipment to the oil-rich Lake Albert region, but it is now far behind the oilfield developments it was expected to service.
Industry executives argue that Kabalega remains a critical project for the sector.
The airport has a 3.5km runway, 45-metre shoulders, a cargo terminal, and an apron that can hold four large Antonov-sized aircraft simultaneously, but the critical air traffic control tower remains the missing link.
Other infrastructure to support commercial oil production includes 700 kilometres of tarmac roads that have been constructed in the Albertine region, and the export pipeline, currently at 58 percent.
© Copyright 2022 Nation Media Group. All Rights Reserved. Provided by SyndiGate Media Inc. (Syndigate.info).
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

Zawya
an hour ago
- Zawya
Statement by the Ministry of Foreign Affairs (MFA) of Ukraine on the Peace Agreement Between the Democratic Republic of the Congo and the Republic of Rwanda
We welcome the signing of the peace agreement between the Democratic Republic of the Congo and the Republic of Rwanda. This important achievement for Africa and international security has been made possible thanks to the decisive role of the United States and personally President Donald Trump, as well as a number of countries and international organizations. In particular, we commend the constructive efforts of the Presidents of Angola and Kenya, the African Union, the East African Community, the Southern African Development Community, and the United Nations. The State of Qatar has made a significant contribution to advancing the peace settlement, especially by ensuring complementarity and coherence among various mediation initiatives. Ukraine highly values the effective mediation by the United States. We congratulate U.S. Secretary of State Marco Rubio and American diplomacy on this achievement. The active involvement of the American side in the negotiation process played a decisive role in reaching and signing the peace agreement. We hope for the responsible efforts of both parties in implementing the peace agreement and in ensuring lasting peace and security in the Great Lakes region. This will create favourable conditions for strengthening the economic potential and social stability of the states in the region, improving their investment attractiveness, and deepening economic ties with other countries. Ukraine reaffirms its commitment to comprehensively intensify mutually beneficial cooperation with the countries of the region, including a readiness to contribute meaningfully to achieving their socio-economic development goals. We are confident that the United States can play a similarly decisive role in achieving a just peace and ending Russia's war of aggression against Ukraine. This peace agreement demonstrates that it is possible to stop the killing and restore peace even under challenging circumstances, when the international community acts resolutely and the parties participate in the peace process in good faith. We emphasize that the foundation of the peaceful settlement between the Democratic Republic of the Congo and the Republic of Rwanda is based on the fundamental principles of the UN Charter, including the mutual obligation of states to respect each other's territorial integrity and sovereignty within internationally recognized borders, to refrain from the threat or use of force, to avoid interference in internal affairs, and to facilitate the return of refugees and internally displaced persons. It is precisely these universally recognized principles of international law that underpin Ukraine's proposals for ending the war in Europe and restoring a comprehensive, just, and sustainable peace for Ukraine. Distributed by APO Group on behalf of Ministry of Foreign Affairs of Ukraine.

Zawya
an hour ago
- Zawya
Seychelles: Courtesy Call by Ambassador Jardine and Rear Admiral Mattis on Minister Radegonde
On Friday, 27 June 2025, H.E. Henry Jardine, United States Ambassador to Seychelles, and Rear Admiral Michael Mattis, Director of Strategic Effects at U.S. Naval Forces Europe-Africa (NAVEUR-NAVAF), paid a courtesy call on Mr. Sylvestre Radegonde, Minister for Foreign Affairs and Tourism, at Maison Quéau de Quinssy. The meeting focused primarily on enhancing maritime and defence cooperation, particularly through the ongoing initiatives of NAVEUR–NAVAF. Discussions covered the challenges faced in patrolling Seychelles' Exclusive Economic Zone (EEZ) and the potential for leveraging drone technology to assist in maritime surveillance efforts. Minister Radegonde commended NAVEUR–NAVAF for its leadership in promoting maritime security in the region and for its continued support in building the capacity of the Seychelles Defence Forces through joint exercises. Notably, he highlighted the successful 2025 edition of Cutlass Express, which was conducted earlier this year under the leadership of U.S. Africa Command (AFRICOM). Minister Radegonde also expressed his appreciation for the United States' participation in this year's National Day Parade, underlining the strength of the bilateral relationship. Distributed by APO Group on behalf of Ministry of Foreign Affairs and Tourism, Republic of Seychelles.


Gulf Business
5 hours ago
- Gulf Business
New $205m agreement to boost UAE-GCC power grid interconnection
Image courtesy: WAM/ For illustrative purposes Abu Dhabi Fund for Development (ADFD) has signed a Dhs752m ($205m) financing agreement with the Gulf Cooperation Council Interconnection Authority (GCCIA) to support the expansion of the GCC power grid interconnection with the UAE's national electricity network, state news agency WAM reported. The agreement, signed at The infrastructure project forms part of broader efforts to enhance regional energy resilience and enable wider economic and developmental integration, aligning with the UAE Energy Strategy 2050. The strategy aims to create an energy system that is both sustainable and economically efficient. Initiative will increase electricity transmission capacity between UAE and GCC Designed as a strategic grid upgrade, the initiative will significantly increase electricity transmission capacity between the UAE and the GCC network. Technical and economic feasibility studies have supported its design, in line with the GCCIA's vision for a durable, regionally connected power infrastructure. The project includes the construction of a 400kV double-circuit overhead transmission line spanning 96 kilometres, connecting the Al Silaa substation in the UAE with the Salwa substation in Saudi Arabia. It also entails the expansion of three substations — Gonan, Al Silaa, and Salwa — and the installation of advanced 400kV switchgears, circuit breakers, and reactors, along with modern protection and control systems to enhance grid efficiency and reliability. 'This project reflects ADFD's commitment to financing high-impact infrastructure that supports the UAE's development priorities,' said Mohammed Saif Al Suwaidi, director-general of ADFD. 'Power grid interconnection is a strategic enabler of energy security and a foundation for accelerating the transition to He added that the project would 'increase the efficiency of the power grid, improve emergency preparedness, strengthen connectivity with regional partners, and promote the integration of renewable energy,' supporting the GCC's sustainability and emissions reduction goals. Engineer Ahmed Ali Al Ebrahim, CEO of the GCCIA. called the initiative the first phase of a broader collaboration with ADFD during the current grid expansion and noted parallel efforts to interconnect with Kuwait, Oman, and southern Iraq, representing a total investment exceeding $1bn. 'By leveraging increased transmission capacity, we aim to activate a unified Gulf electricity market to facilitate cross-border power trade,' Al Ebrahim said. 'This could create economic opportunities projected to exceed $20bn over the next 15 years.'