
Traffic restricted on Vantage Bridge throughout June
As most cross-state travelers already know, one lane in each direction on the bridge is closed most of the time during construction season as it undergoes a major, multi-year overhaul. Information from the Washington Department of Transportation indicated that both lanes of the bridge in each direction would be open throughout June.
Megan Lott, communications manager for the WSDOT south central region, said there was some misunderstanding though, and the bridge will be closed on weekdays in June.
"Our mistake," Lott said.
All four lanes of the bridge will be open Memorial Day weekend and during the week after, from May 23 through June 1. After that, traffic will be restricted to one lane in each direction Monday through Friday throughout the month of June. All lanes will be open on weekends.
Two lanes will be open in each direction over the July 4 weekend, July 3 through 8. But after July 8 the construction schedule shifts, Lott said, and one lane in each direction will be closed through the end of the construction season in November. The exception will be Labor Day weekend, Aug. 28 through Sept. 2, when both lanes will be open in each direction.
The Vantage Bridge was one of the first projects to start in the spring, along with an extensive paving project on 2.2 miles of Westshore Drive. To date, construction crews have removed the old roadbed, rebuilt it, poured gutters and added a base layer for sidewalks. The sidewalks are being poured now.
"There are no delays; the project is on schedule," said interim Grant County Engineer Dave Bren.
The contractor has 70 working days to finish, Bren said, with a completion date of mid-July.
Fewer DOT road projects are scheduled in Grant and Adams counties in 2025 than was the case in 2024, but there are some planned later in the summer.
Sebastian Moraga, communications consultant for the DOT north central region, said two sections of Interstate 90 are scheduled for repaving, with the start date right in the middle of summer. That means the project might not be finished in one construction season — some sections may have to wait until 2026.
"It is not scheduled to start until mid-July at the earliest," Moraga wrote in response to an email from the Columbia Basin Herald.
Paving is scheduled for the Vantage Bridge to George, then from Dodson Road to Mae Valley. Crews will be shaving down the original surface and repaving, fixing cracks, adding signage and lane markings. Drivers on I-90 may experience delays while the crews are working. There might be some short-term ramp closures, so getting on and off I-90 in the project area might mean taking an alternate route.
A project to improve a section of Schoonover Road about eight miles west of Ritzville is scheduled to start in June.
A new roundabout is scheduled for State Route 26 and its intersection with South First Avenue in Othello. Moraga said construction is scheduled to begin in early August, lasting two to three months.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
a day ago
- Yahoo
Interstate Bridge crash briefly blocks southbound traffic Friday morning
PORTLAND, Ore. (KOIN) — The southbound side of the Interstate Bridge was blocked for around an hour Friday morning after a crash. According to the Washington Department of Transportation, the crash happened near milepost 0 and blocked all southbound lanes just after 9:45 a.m. Close Thanks for signing up! Watch for us in your inbox. Subscribe Now At around 10:20 a.m. WSDOT said there was a two-mile backup reaching all the way to Exit 2 at 39th Street. Shortly before 11 a.m., the lanes began reopening as the crash was cleared. Officials warn drivers to expect delays and to be patient as traffic moves slowly through the area. Copyright 2025 Nexstar Media, Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed. Solve the daily Crossword
Yahoo
2 days ago
- Yahoo
Expect delays: Everett traffic will be jammed by 14-week paving project
The Washington State Department of Transportation (WSDOT) just announced a prodigious paving project on I-5, starting Saturday, July 19. Work is scheduled mostly evenings and overnight hours, but commuters may see occasional daytime work. No matter how you slice it, commuting through Everett is going to get rough at times during this 14-week project. 'Saturday evening in Everett, the contractors are going to start shutting down up to four left lanes to begin the grinding part of this repavement project,' WSDOT spokesperson Della Kostelnik Juarez said. 'The lanes are going to start shutting down at 7 p.m. (and) reopen at 9 a.m. on Sunday, close again at 7 p.m. Sunday and reopen by 5 a.m. Monday, there will be no work on Monday (evening).' The work starts on southbound I-5 between 41st Street and 100th Street Southeast, near the Everett Mall. Once contractors complete work in the southbound lanes, they will repave the same section in the northbound lanes of I-5. The schedule throughout the 14-week project includes closures: From 7 p.m. Saturday, July 19 to 9 a.m. Sunday, July 20. From 7 p.m. Sunday, July 20 to 5 a.m. Monday, July 21. From 7 p.m. to 5 a.m. nightly Tuesday, July 22 to Friday morning, July 25. WSDOT will inform us if there are any changes. The Broadway HOV on-ramp to southbound I-5 will also close during the roadwork, but the general purpose on-ramp from Broadway will remain open. Some of this work needs dry weather and may need to be rescheduled. The Everett pavement project will repave 4 miles on I-5 This pavement repair project will repave approximately 4 miles of southbound I-5 in Everett and is expected to finish later this fall. Motorcyclists should watch for grooved, uneven pavement and use extreme caution. 'We really encourage people to look at our travel page and look at our travel map to see what is going to be open and closed,' Juarez added. Solve the daily Crossword

NBC Sports
2 days ago
- NBC Sports
Winners, losers from NASCAR Cup race at Dover won by Denny Hamlin in overtime
A look at the winners and losers from Dover. WINNERS Denny Hamlin — Fends off the field on a pair of overtime restarts despite being on older tires to win his fourth race of the season. No driver has won more Cup races this season. Dustin Long, Chase Briscoe — His runner-up result gave Joe Gibbs Racing a 1-2 finish. Briscoe has scored back-to-back runner-up results the past two weekends. Sunday's finish was his eighth top-five finish in 21 races this season. Briscoe had 13 top-five finishes in 144 Cup starts before this season. Alex Bowman — His third-place finish is his third top-five result in the last six races. He moved from 12th in the points to ninth after Sunday's result. Chase Elliott — His sixth-place finish, along with William Byron's crash in overtime, put Elliott into the points lead with five races left in the regular season. Elliott also led 238 of the 407 laps and won a stage Sunday. That is his first stage win of the season. Bubba Wallace — His seventh-place finish snapped a five-race streak of results outside the top 10. Wallace also scored his best Dover finish in 11 Dover starts. Wallace remains on the playoff cutline but expanded his lead on Ryan Preece from three points to 16. Ty Gibbs — His fifth-place finish marks his seventh consecutive top-15 finish. Gibbs has gone from 27th in points to 16th in that stretch. He also advances to the finals of the In-Season Challenge and will race for $1 million next week at Indianapolis. Ty Dillon — He finished 20th, scoring his fourth consecutive top-20 finish to advance to the finals of the In-Season Challenge. He'll race Ty Gibbs for $1 million next week at Indianapolis. LOSERS William Byron — He was collected in a crash in overtime and finished 31st. Byron also lost the points lead. Byron had led the points since the Coca-Cola 600 on Memorial Day weekend. Christopher Bell — While he won a stage and led 67 laps, his most laps led in a race since his Phoenix victory in March, Bell spun twice and lost a chance to win Sunday because of those incidents, particularly his spin in overtime. He finished 18th instead of possibly scoring his fourth victory of the year. Carson Hocevar — His 35th-place finish due to a mechanical issue is his third consecutive finish outside the top 30. It's also the fifth time in the last seven races he's placed 29th or worse.