Business Forum ready to fight extortion claims
Image: File
THE Philippi Business Forum has distanced itself from the City's claims that it was responsible for derailing the MyCiTi construction project along Govan Mbeki Road in Philippi through extortion.
The City recently confirmed having secured an interim interdict against alleged extortionists after officials and the contractor's staff received death threats and were verbally intimidated.
The Philippi Business Forum and Crossroads Business Forum were cited as respondents in the application. The City said both failed to present their answering affidavits to the Western Cape High Court concerning why the order should not be made permanent.
'Self-proclaimed 'activists' within the Philippi Business Forum, Crossroads Business Forum and other affiliated entities had engaged in intimidation, threats, and blatant misinformation campaigns in their shameless efforts to dictate how and to whom employment opportunities are awarded.
'There are lawful and transparent processes available to local businesses and residents from the affected wards to apply for the available opportunities that form part of this construction project.
'Those who have been involved in the intimidation, death threats, and other disruptive tactics are well aware of these processes as they have been briefed at numerous public information days and during other engagements. There is only one way to benefit from the available opportunities at any City project and that is by following the legal and transparent route. This route ensures equal access to all. We will not deviate from it,' said Urban Mobility mayco member Rob Quintas.
He said the interdict does not prevent anyone from participating in the project.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Next
Stay
Close ✕
'It only stops those who are trying to hijack it through threats, violence and sabotage. The City continues to encourage all eligible businesses to submit their profiles via the clearly marked boxes at the Subcouncil Offices.'
Philippi Business Forum member Lonwabo Matshisi denied the allegations.
'It is not true. They (contractors) want to do the work on their own and take the money given by the municipality. They did the same thing during the last project. Everywhere they go, they accuse the SMMEs. We are just looking for an opportunity to grow. We never did what they're claiming. They just took pictures of our cars and formed a story, saying we were involved in extortion.
"That's false. Our cars were stopped and searched for guns. There were no guns. We've never stopped any project, we just want them to come and meet with us. We've sent several emails and tried calling them. We asked them (the main contractor) to come and sit with us, to make a presentation. They never came. Meanwhile, we've followed every step we're supposed to take,' Matshisi said.
He said they had just recently found out the City received an interdict against them.
'They just made accusations. On Tuesday, we hired an advocate. We never did what they're claiming. They (the contractor) are working on-site. They promised our community jobs but delivered nothing. That's why the community is also upset,' Matshisi said.
Attempts to contact the Crossroads Business Forum were unsuccessful.
The Building Industry Bargaining Council (BIBC) said the country's construction sector was being 'systematically undermined' by criminal syndicates. The impact has been severe, including forced stoppages and heightened security requirements which have led to significant project delays and cost overruns.
'These criminal networks are not simply disruptive, they're deeply embedded in some areas and operate with increasing sophistication,' said Danie Hattingh, spokesperson for business at the BIBC.
The council explained that the 'construction mafia' initially emerged around 2015, 'often misrepresented as attempts at economic transformation. Exploiting clauses in procurement policy, particularly the requirement that 30% of public contracts benefit local communities, these groups claimed to represent local interests'.
According to the BIBC, contractors, workers, and even government officials have reported intimidation, assaults, and in some cases, killings. Armed gangs have stormed construction sites demanding a cut of the project (usually 30%, under the false interpretation of local empowerment policies).
'What began as calls for inclusion quickly devolved into extortion and violence. We have seen armed site invasions, demands for 'protection fees,' sabotage of equipment, and even threats to life. These are not empowerment activists. These are criminal syndicates exploiting legitimate policies for personal gain,' Hattingh said.
'The construction mafia exploits every gap. They scare and threaten without facing any punishment or consequences, manipulate the tender process, and operate freely due to legal delays and poor coordination between stakeholders.'
Cape Times
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Citizen
a day ago
- The Citizen
New electricity tariff structure explained for Ekurhuleni residents
The electricity tariff structure is regulated by the National Energy Regulator of South Africa (NERSA), requiring municipalities to review tariffs annually and conduct a Cost of Supply (CoS) study every five years. 'The latest tariff adjustments are in line with these requirements and reflect the findings of Ekurhuleni's most recent CoS study,' said CoE spokesperson Zweli Dlamini. Two main tariff options for residents For residential customers, the City offers two main tariff structures: 1. Tariff A: Inclined Block Tariff (IBT) This is split into two categories: Category A1 (Approved Indigent and Deemed Indigent Households): Best suited for low-consumption households. Customers receive 50kWh of free basic electricity (FBE) per month . No basic monthly charge applies. Category A2 (Non-Indigent, Low Consumption Customers): Does not include free basic electricity. A basic monthly charge will apply for the 2025/26 financial year: Single-phase supply: R109.78 per month Three-phase supply: R203.89 per month The City explained that this basic charge assists in recovering the costs of distributing electricity, maintaining infrastructure, and ensuring ongoing repairs. 2. Tariff B: Residential This option is suitable for medium to high consumption households and has been in place since 2018. It also includes a monthly basic charge: Single-phase supply: R109.78 per month Three-phase supply: R203.89 per month Residents encouraged to apply for indigent support Customers can choose the tariff option that best suits their consumption patterns but are required to remain on the selected tariff for a minimum of 12 months before switching. The City urged qualifying residents to apply for the indigent social package to benefit from subsidies and free basic electricity under Category A1. Keeping increases reasonable while ensuring reliability 'In setting tariffs for the new financial year, the City considered all factors within its control and aimed to keep increases reasonable and affordable while ensuring a continued and reliable electricity supply to residents.' 'We remain committed to transparency, regulatory compliance, and serving the best interests of our community,' said Dlamini. For further details on the City's electricity tariffs, residents are encouraged to visit the City of Ekurhuleni's official website or contact their nearest customer care centre.


Daily Maverick
3 days ago
- Daily Maverick
Extortionists ‘hell-bent' on derailing MyCiTi bus project, says City of Cape Town
But Crossroads and Philippi business forums deny the city's allegations of intimidation and say they are being sidelined. Extortionists are 'hell-bent on derailing' the MyCiTi bus project along Govan Mbeki Road in Philippi, says the City of Cape Town. The project was launched in 2022. This week, the city welcomed a decision by the Western Cape High Court to extend an interim interdict obtained last month against the Philippi Business Forum and Crossroads Business Forum and two of their members. The interdict against intimidating and threatening officials and workers or entering the site without permission is effective until 21 April 2026, when the matter will be argued in court. The city said contractors had received death threats. According to the city, the forums failed to present their answering affidavits as to why the order should not be made permanent. Mayoral Committee Member for Urban Mobility Rob Quintas said: 'Self-proclaimed 'activists' within the Philippi Business Forum, Crossroads Business Forum and other affiliated entities have engaged in intimidation, threats and blatant misinformation campaigns in their shameless efforts to dictate how and to whom employment opportunities are awarded. 'There are lawful and transparent processes available to local businesses and residents from the affected wards to apply for the available opportunities that form part of this construction project.' In its statement the city said: 'The interdict does not prevent anyone from participating in the project. It only stops those who are trying to hijack it through threats, violence and sabotage. The city continues to encourage all eligible businesses to submit their profiles via the clearly marked boxes at the subcouncil offices.' Attorney Ashley Leeuw, for the business forums, told GroundUp that the city labelling his clients extortionist (in the media release) was 'damning to their reputation'. 'It is very unfair to our clients,' Leeuw said. 'Due to insufficient time we could not oppose an interim interdict but we filed a motion to oppose,' he said. 'There is no final court interdict against my clients.' He said the interim order had been granted to allow work to continue at the site. 'The allegations set out in the city's court application are denied as false,' he said. He said his clients have no intention of going to the site. 'It is all lies they're spreading that we have intimidated workers at the site,' Thanduxolo Xokoza, Philippi Business Forum secretary, told GroundUp. 'This started last year when the subcouncil invited us to an information service on how we will participate and benefit from the project and that was the last time the city had a meeting with us.' He said small businesses in Philippi had gone to the site on 15 May to seek answers from the community liaison officers. Xokoza said their approach had been peaceful. On 28 May, the businesses had again gone to stop construction until their demands were met. 'The project was halted last week until our businesses are given an opportunity,' said Xokoza. 'We also have companies that are able to do some work at the construction of the project. The community also joined in because they also want to be part of the project. 'We are business people and have a right to be part of the project,' he said. Crossroads Business Forum member Nokuzola Mpimpi said: 'We were surprised to see the work continuing last month and this prompted businesses to rally and go to confront the main contractor at the site.'

IOL News
3 days ago
- IOL News
City invests R2. 7 million in Bellville United Soccer Club amid security concerns
Vandalism hampers Bellville United Soccer Club. Image: Supplied Two weeks after management of the Bellville United Soccer Club approached the media following a spate of vandalism and theft, the City said it has invested more than R2.7 million into the sports facility and others in the community. Earlier, club management said they pleaded for more than 10 years for flood lights for the facility and for repairs to be done to damaged infrastructure caused by criminals. They also called for improved security measures at the club situated at the sportsground in Peter Barlow Street. Following their complaint, the facility has seen additional break-in which left their electrical infrastructure damaged. The City's Recreation and Parks Department said they were aware of the spate of burglaries. 'These incidents prompt the department to involve the City's Environmental Health Department to assess the facility's safety and ensure compliance with health standards. 'Following this latest incident, the City deployed internal maintenance teams to stabilise the facility, delivered 10 ceiling boards and plumbing materials to the soccer clubhouse to assist with repair work, bricked up an access window and requested additional safety assessments. "Routine maintenance support continues to be provided within the limits of available resources' As an interim measure, the City installed practice lights on the soccer fields at a cost of R235 000, enabling shared access to evening matches, and pumped over R2 million into infrastructure of the various sports facilities. 'During the 2024/25 financial year, the City undertook repairs totaling R1.27 million across the darts, pigeon and rugby clubhouses. At the time of planning these repairs, the soccer clubhouse was assessed to be in relatively acceptable condition, based on previous electrical, plumbing and general building upgrades that had already been completed. 'However, subsequent incidents of vandalism and theft, particularly in May 2025, have since caused further damage. 'While two 24-hour security officers are currently deployed on-site, additional security resource requests have been submitted based on facility size and risk assessments. These are reviewed annually as part of the City's planning and budget allocation processes. 'As with all community facilities, routine maintenance and upgrade requests are considered each year. For the 2024/25 financial year, a total of R2.75 million in repairs and maintenance requests were submitted for the Bellville South Sport Grounds, including items relating to the soccer clubhouse.'