Construction of Mohmand Dam to be completed by 2027-28

Construction of Mohmand Dam to be completed by 2027-28

LAHORE: WAPDA achieved yet another landmark on Mohmand Dam Project, as construction work has commenced on the Main Dam. Prior to achieving this landmark, several pre-requisites such as river diversion, up and downstream starter (coffer) dams, dam plinth and excavation of left and right abutments and dam foundations were completed. Mohmand Dam is scheduled for completion in 2027-28.
Federal Minister for Water Resources Mian Muhammad Mueen Wattoo visited Mohmand Dam Project to mark the occasion. Chairman WAPDA Engr Lt Gen Sajjad Ghani (retd) also accompanied him. The GM/PD Mohmand Dam along with his team and Project Managers of the Consultants and the Contractors were also present on the occasion.
The Federal Minister had a detailed visit of the key sites and observed construction activities going on there. These sites included Diversion System, Power Intake Tunnel, Main Dam, Spillway and Power House.
During on-the-sites briefings, the Federal Minister was apprised by the Project Team that construction work is continuing on 14 different sites. The Federal Minister was also briefed about the site-wise progress on the Project.
The Federal Minister expressed satisfaction over the progress on the Project. He said that the Federal Government is fully cognizant of the increasing needs of water and affordable electricity in the country, that is why, WAPDA and Ministry of Water Resources have been making all out efforts for completion of the under construction mega projects. Mohmand Dam, being amongst these projects, will help fulfilling requirements of water and low-cost electricity in Pakistan. He hoped that WAPDA would complete Mohmand Dam and other projects as per their timelines. The Ministry of Water Resources will provide full support for the purpose, the Minister added.
Mohmand Dam Project being constructed across River Swat, in Tribal District Mohmand of Khyber Pakhtunkhwa Province. The 213-meter Mohmand Dam is the 5th highest concrete faced-rock fill dam (CFRD) in the world. It has a gross water storage capacity of 1.29 MAF sufficient to irrigate 18,233 acres of new land in Mohmand and Charsadda, besides supplementing irrigation supplies to 160,000 acres of existing land. With installed power capacity of 800 MW, the Project will provide 2.86 billion units of green, clean and affordable hydel electricity to the National Grid annually. It will not only help save Peshawar, Charsadda and Nowshera from flooding but also provide 300 million gallons water per day to Peshawar for drinking purpose.
Copyright Business Recorder, 2025
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

World Bank MENAAP official meets Wapda chief
World Bank MENAAP official meets Wapda chief

Business Recorder

time38 minutes ago

  • Business Recorder

World Bank MENAAP official meets Wapda chief

LAHORE: World Bank Practice Manager for Middle East, North Africa, Afghanistan and Pakistan (MENAAP) Husam Mohamed Beides, accompanied by Senior Energy Specialist Gunjan Gautam, Friday called on Chairman Wapda Naveed Asghar Chaudhry and discussed with him the matters relating to World Bank-funded Tarbela 5th Extension and Dasu Hydropower Projects. Member Water Syed Ali Akhtar Shah, GM/PD Dasu HPP Amir Shafiq-ur-Rehman and GM/PD Tarbela 5th Extension Umair Mannan also attended the meeting. It is pertinent to mention that World Bank is providing financial support worth US$1517 million and US$390 million for under-construction Stage-I of Dasu and Tarbela 5th Extension respectively. The World Bank's Practice Manager was given a rundown of the physical progress achieved so far, ongoing construction works, and schedule for completion of key activities on both projects. He was also apprised of the financial progress and monetary requirements for completion of Dasu and Tarbela 5th Extension Hydropower Projects. Speaking on the occasion, Chairman Wapda appreciated the World Bank's contribution for harnessing low-cost, clean and green energy in Pakistan through Wapda projects. He said that Wapda takes pride in being the partner in progress with the World Bank, as the biggest development portfolio of the World Bank in Pakistan relates to Wapda projects. The Chairman expressed the hope that the World Bank-Wapda partnership will further extend in the days to come. Thanking Wapda for arranging the briefing about progress of Dasu and Tarbela 5th Extension Hydropower Projects, World Bank's Practice Manager lauded the efforts made by Wapda for improving the ratio of environment-friendly electricity in the National Grid and mitigating adverse impact of climate change. He said that the World Bank and Wapda will continue exploring avenues for mutual cooperation for hydro development in Pakistan. Copyright Business Recorder, 2025

Govt focus on reservoirs minimal despite water woes
Govt focus on reservoirs minimal despite water woes

Business Recorder

time2 hours ago

  • Business Recorder

Govt focus on reservoirs minimal despite water woes

ISLAMABAD: Despite the devastating impact of climate change on Pakistan's infrastructure, massive water losses worth billions of dollars and ongoing inter-provincial disputes over water distribution, the government's focus on developing water reservoirs remains minimal. 'The government is working on water reservoirs, but not with the urgency this task demands. We have neither built major reservoirs in the past 40 years nor improved our water usage methods,' said a government official, speaking on condition of anonymity. Pakistan consistently ranked among the top 10 most vulnerable countries to climate change - largely due to the strain on the Indus River system which has been exacerbated by the unilateral withdrawal from the Indus Water Treaty by India in the aftermath of the Pahalgam terror attack and India's insistence that Pakistan is responsible without providing any proof. Water flow in rivers increasing Over 80% of the country's arable land is irrigated by Indus waters. Rising temperatures and recurring heatwaves are expected to intensify water scarcity and worsen drought conditions. According to the Public Sector Development Programme (PSDP) for 2025–26, the government allocated Rs 20 billion for the Dasu Hydropower Project (Stage-I), Rs 3.4 billion for the 1,410 MW Tarbela 5th Extension Hydropower Project, and Rs 500 million for the 54 MW Attabad Lake Hydropower Project. Additionally, funds have been set aside for the refurbishment and upgradation of Mangla Power Station to enhance its capacity from 1,000 MW to 1,310 MW. Rupees 25 billion has been earmarked for the Diamer-Bhasha Dam (including the Tangir Hydropower Project), while Rs 7.78 billion is allocated for land acquisition and resettlement (2nd revised) under the same project. The Mohmand Dam Project (800 MW) has received a substantial allocation of Rs 35.72 billion. The federal government is currently exploring financing options for the $10 billion Diamer-Bhasha Hydropower Project—$8 billion for the dam and $2 billion for the transmission line. Development partners have shown reluctance to commit the required funds. The project, which has an installed capacity of 4,500 MW and a gross storage of 8.1 MAF, is expected to generate 18.1 billion units of electricity annually, plus an additional 2.5 billion units for downstream projects. It is seen as crucial for enhancing energy security, reducing carbon emissions, and addressing water shortages. Last month, Prime Minister Shehbaz Sharif chaired a high-level meeting where he directed authorities to remove all obstacles hindering the timely completion of the $15 billion Diamer-Bhasha Dam, calling it vital for Pakistan's energy and agricultural security. Officials involved in water infrastructure stress the need for diverting additional financial resources toward reservoir development beyond current commitments. The Water and Power Development Authority (WAPDA), responsible for building and managing dams, estimates that new projects could make an additional 10 million acre-feet (MAF) of water available within 4–5 years. 'With new dams, water availability could rise from the current 13 MAF to 23 MAF per annum,' the former Wapda chairman told a parliamentary panel in January. However, the main challenge remains financing, especially for key reservoirs like Diamer-Bhasha. Pakistan currently has access to 135 MAF of surface water, of which 102 MAF is used for agriculture. Nearly 94% of this water goes to agriculture alone. Experts argue this percentage must be reduced—China, for example, brought it down from over 90% to 60%. Efficient irrigation methods, largely under provincial jurisdiction, have yet to be implemented. While the World Bank has funded efforts such as concrete canal delivery systems, actual progress on the ground remains limited. Command area development activities are underway but remain unsatisfactory. Currently, around 450 million acres of land are irrigated with canal water, which typically faces a 25% supply shortfall. To close this gap, Pakistan needs 15–16 MAF of new storage capacity. However, the Diamer-Bhasha Dam, with a 6.4 MAF capacity, will not be operational until 2029 or 2030—by which time demand could increase to 14–15 MAF. Even then, the DBD would only reduce the shortage from a projected 35% to around 25%. Pakistan is now bearing the consequences of its prolonged inaction on water storage infrastructure. To address financing gaps, the government has approached the Arab Consortium—including the Saudi Fund, Kuwait Fund, OPEC Fund, and the Islamic Development Bank (IsDB)—for support. These institutions previously supported the Mohmand Dam, and securitization of existing assets like the Ghazi Barotha Dam is now being explored to fund DBD. 'IsDB, SFD, and the ADB have been approached to help bridge the $3.5 billion funding gap for DBDP. However, no multilateral development bank has yet stepped up as an anchor financier,' said an official source. 'If Wapda is to secure funding, there are two main options: either the government provides a sovereign guarantee — which is unlikely — or Wapda issues a bond based on its balance sheet. But that's not feasible either, given its Rs 214 billion in receivables from the power sector,' said the source. This receivable is part of the broader issue of circular debt, which undermines Wapda's creditworthiness. Lenders are expected to scrutinize Wapda's repayment capacity before committing funds. The government is also exploring loans secured against operational projects or offering attractive returns to entice investors. Nine out of Pakistan's ten largest cities lie within 50 kilometers of the Indus River. The continued degradation of the Indus Basin presents a looming economic, social, ecological, and demographic threat to the country's development and stability. Copyright Business Recorder, 2025

K-IV delays
K-IV delays

Express Tribune

time6 hours ago

  • Express Tribune

K-IV delays

Listen to article Karachi has been desperately water-stressed for longer than many of its citizens have been alive, but after almost a decade of work on a solution that millions had pinned their hopes on, the project is still several years behind schedule. The Greater Karachi Bulk Water Supply Scheme (K-IV) was designed to alleviate Karachi's chronic water crisis by delivering 650 million gallons per day (MGD) from Keenjhar Lake, but the project's first phase, which was supposed to deliver 260 MGD, is still only at 63% completion, with its 2026 deadline hanging by a thread. Incidentally, the first phase was kicked off by the Sindh government in 2016 and was supposed to be completed by 2019; but in 2018, with only 20% of work done, the project was shelved. In 2021, the federal government reallocated the project to Wapda, where it underwent a redesign that resulted in a new completion date of the end of 2025 and a cost estimate increase from Rs26 billion to Rs125 billion. The cost has now risen by another Rs30 billion, according to reports, while completion is almost sure to miss the new 2026 deadline. This is because the 2025-26 federal budget allocated a mere Rs3.2 billion against Wapda's requested Rs40 billion — a 92% shortfall. The Sindh government, which is still involved in the project, has allocated a paltry Rs100 million. Wapda warns that without "uninterrupted funds", the 2026 target is unattainable. Meanwhile, Karachi's water deficit now stands at 550 MGD, meaning that the entire K-IV project would barely cover the shortfall. And even if the K-IV project itself is only slightly delayed, the Sindh government's work on the water supply network has barely started. That work is scheduled for completion in 2029, which is another deadline that is certain to be missed because of a lack of funding. Other supporting infrastructure work is also well behind schedule. It is becoming a foregone conclusion that by the time anyone receives a drop of water through the K-IV project, the city will be even more water-stressed than it is today.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store