Pachpaoli Flyover demolition halted as NHAI waits for railways' permission

Pachpaoli Flyover demolition halted as NHAI waits for railways' permission

Time of India15-05-2025
1
2
Nagpur: The ongoing demolition work of the decades-old Pachpaoli flyover, which will be replaced by a new, longer one, has hit a roadblock. The National Highway Authority of India (NHAI), which is implementing the project, is awaiting permission from the railways to demolish the flyover over the two railway lines.
The flyover demolition was supposed to be completed this month but is likely to stretch for the next one to two months.
The NHAI is currently implementing the Rs998
Indora to Dighori project
, under which two flyovers will be built. The first flyover would start just ahead of Kamal Square and would pass through congested squares like Golibar Square, Lal Imli Square, Agrasen Square, Gandhi Gate, and Ashok Square before landing ahead of Reshimbagh Square.
For this, the decades-old 1.5-km-long Pachpaoli flyover is being demolished. The second 2.2 km long flyover would start before the Bhande Plot Square and would land ahead of Dighori Square.
The NHAI started the demolition work last month and was supposed to complete it within a month. However, their plan has hit a snag. "We have so far demolished the flyover till the railway crossing. But to demolish it over the railway crossing, we need the train movement to stop.
For this, we have written to the railways, and they have asked us for a plan, which we have submitted. Until the railways give us permission, the demolition work will be halted.
We are not demolishing the flyover from Golibar Chowk side as we need a route for the heavy vehicles to go on the flyover for the demolition work," said a senior NHAI official.
While the NHAI awaits permission from the railways, they have started the piling work on the already demolished side for installing piers of the new flyover.
Meanwhile, tons of debris continue to lie on the roadside, and NHAI is systematically disposing it of. The NHAI hopes to complete the work of the Kamal Chowk to Reshimbagh flyover by December this year, even as their deadline is June next year. However, one hiccup after another continues to stall the work.
Meanwhile, citizens in the area are hoping that the new flyover is built at the earliest, as it will cut travel time from North Nagpur to South Nagpur drastically. As part of the project, two RUBs will also be built at two level crossings in the Pachpaoli area, but this will start after the completion of the flyover.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

NHAI yet to take charge of South Delhi's Mandi Road
NHAI yet to take charge of South Delhi's Mandi Road

Time of India

time11 hours ago

  • Time of India

NHAI yet to take charge of South Delhi's Mandi Road

Advt Advt Three months after Delhi government's plan to transfer Mandi Road to the National Highways Authority of India, there is still no clarity on the status of the handover. Meanwhile frustration is growing among residents and motorists, who are now urging authorities to expedite the process in light of the deteriorating traffic Road, one of south Delhi's most heavily congested stretches, is a critical alternative route connecting Mehrauli-Gurgaon Road with Faridabad-Gurgaon Road. The corridor winds through rural settlements, upscale farmhouses and compact commercial clusters. But it is inconsistent in its width and infrastructure, making travel both inconvenient and happens during rains, by afternoon on Saturday, the road was inundated in knee-deep water. "I stood there one afternoon for nearly 20 minutes, just taking in the scene - people wading through the accumulated water, traffic at a standstill," said Juhi, a local resident. "It made me question where we were living. Even picking up children from school has become a challenge."While the proposed right of way for the road is 30 metres, the current width fluctuates sharply between just 8m and 18m. This, combined with the absence of lane markings, street lighting, pedestrian pathways and traffic signals renders the route dangerous and inefficient. The most critical point of congestion is at the entry from MG Road, where potholes, broken surfaces and bottlenecks cause regular traffic snarls. Emergency vehicles, school buses, and daily commuters often find themselves stuck there for long road-widening project, which requires the acquisition of 16.9 hectares of land, was first conceptualised in 2012. It was formally approved by road engineering authority Unified Traffic and Transportation Infrastructure (Planning & Engineering) Centre (UTTIPEC) in March 2023. Despite this clearance, no physical work commenced on proposed handover to NHAI comprises two segments: the Mehrauli-Gurgaon Road to the Urban Extension Road-II (UER-II) and UER-II to Faridabad-Gurgaon Road. Together, these segments form a 7.7km stretch under the broader Mandi Road corridor. According to the latest updates, despite two official reminders to NHAI, no physical handover has taken place, according to Tandon, general secretary, Federation of South Delhi Farm Houses RWAs, which represents over 1,200 farmhouses and over 25 RWAs in the Chhatarpur belt, said, "We had a glimmer of hope first in 2012, then in 2023, and finally, earlier this year when surveys were conducted. But even after three months, there's been no action on the ground. These bureaucratic delays crush the hopes of all residents." He added, "The road is far too narrow for the traffic it bears - easily 10 times more than its capacity. Add water tankers, school vans, buses and the occasional tractor from farmhouses, and chaos is inevitable."Other city roads scheduled for transfer to NHAI have seen at least some administrative progress, such as issue of internal orders, even if physical transfer was still pending. Two stretches of NH10 (Rohtak Road) - Peeragarhi to Tikri Border (13.2km) and Peeragarhi to Zakhira (6.8km) - received NHAI's internal clearance and round 8km of NH148A (MG Road) has also been given internal clearance, although physical handover of both roads is awaited. Internal approvals for the 7.5km between Ali Village and Ring Road on NH2 (Mathura Road) have also been Mandi Road, officials claimed, "The work is already under process and every formality will be completed soon."

Bihar Elections: 80% Work Done, Asia's Longest River Bridge On Kosi May Be Completed By Year-End
Bihar Elections: 80% Work Done, Asia's Longest River Bridge On Kosi May Be Completed By Year-End

News18

time17 hours ago

  • News18

Bihar Elections: 80% Work Done, Asia's Longest River Bridge On Kosi May Be Completed By Year-End

Last Updated: The bridge is expected to drastically cut the distance between Supaul and Madhubani—from over 100 km to just 30 km—and improve connectivity to Patna from flood-prone regions The Kosi River—known as both the lifeline and the sorrow of Bihar—is poised to become home to Asia's longest river road bridge soon. The over 13-km structure between Madhubani and Supaul has crossed 80 per cent completion as of July, and is likely to be completed by year-end, News18 has learnt. The two-lane bridge between Bheja and Bakaur is being constructed under the Bharatmala Pariyojana by the National Highways Authority of India (NHAI). Of the total 13.3 km length, at least 10.2 km is the main bridge comprising 170 spans. Each span length is about 60m. The NHAI has termed the 'engineering marvel' Asia's Longest River Bridge. The foundation stone of the bridge was laid by Bihar Chief Minister Nitish Kumar in 2014. Of the 171 well foundations and substructures planned, over 165 have been completed as of July. As the name suggests, well foundations are the deep foundations used for bridge construction in rivers and other water bodies. Substructure is the supporting components below the deck level, primarily consisting of piers and abutments. Segments, which are assembled to form the bridge deck, have also seen significant progress, with 2,660 of 3,400 completed. 'With construction advancing at pace, we expect the bridge to be completed and ready for use by the end of this year," they said, seeking anonymity. The Kosi River is one of India's most unpredictable and flood-prone rivers. Originating in Tibet and flowing through Nepal before entering Bihar, it carries enormous sediment load from the Himalayas, causing it to frequently change course and flood large swathes of land. Despite the devastation it brings during monsoons, the Kosi is also a lifeline for North Bihar—supporting agriculture, fishing, and daily life for millions. Its dual character as both nurturer and destroyer has shaped the socio-economic landscape of the region for centuries. Last year, in March, a portion of the under-construction bridge collapsed, killing one and injuring nine others. The bridge is expected to drastically cut the distance between Supaul and Madhubani—from over 100 km to just 30 km—and improve connectivity to Patna from flood-prone regions. The project's completion could be a key highlight ahead of Bihar's assembly elections, with the current government's term ending in November. view comments Disclaimer: Comments reflect users' views, not News18's. Please keep discussions respectful and constructive. Abusive, defamatory, or illegal comments will be removed. News18 may disable any comment at its discretion. By posting, you agree to our Terms of Use and Privacy Policy.

How W-beam fencing along Mumbai-Gandhinagar route brought down cattle collisions with Vande Bharat by 81% in 3 years
How W-beam fencing along Mumbai-Gandhinagar route brought down cattle collisions with Vande Bharat by 81% in 3 years

Indian Express

time6 days ago

  • Indian Express

How W-beam fencing along Mumbai-Gandhinagar route brought down cattle collisions with Vande Bharat by 81% in 3 years

Three years after incidents of the Mumbai Central-Gandhinagar Capital Vande Bharat Express suffering damaged nose and delayed runs due to collision with cattle herds raised safety concerns in high-speed train operations, the Western Railway — in a first-of-its-kind initiative of the Indian Railways — installed W-beam fencing along the 565-kilometre length of the tracks of the Vande Bharat route, bringing down the incidents of Cattle Run Overs (CRO) by 81%. Soon after its launch in September 2022, repeated incidents of collision of the Mumbai-Gandhinagar Vande Bharat, with images of the train's Fiber Reinforced Polymer (FRP) nose cone damaged surfacing, posed grave risk to the train operating at high speed. Besides, they threatened the lives of cattle grazing along the tracks. To counter this, the Western Railway installed the W-beam fencing — a crash barrier widely used by the National Highway Authority of India (NHAI) — along the stretch from Mumbai to Gandhinagar as well as an additional 300 kilometers from Vadodara Junction to Nagda on the Rajdhani Express route. From 538 reported cases of CRO between Virar and Ahmedabad in 2022-23 to 101 cases in 2024-25, and 12 until July 23 in the current financial year, the Western Railway has been able to achieve a significant reduction with continuous fencing on the Vande Bharat route. According to records of the Western Railways, the figure of 12 cattle that died between April 1 and July 23 this year is also lower than the 27 that died in the corresponding period last year. Of these, the maximum cattle deaths have been recorded in the sections from Virar to Surat and from Vadodara Junction to Geratpur, owing to the fact that these sections are located outside the urban sector and surrounded by villages where cattle rearing is a common profession. In 2022-23, out of the 538 incidents of cattle deaths, 302 were reported between Virar and Surat while 140 were reported between Vadodara and Geratpur. The number significantly reduced to 48 CROs between Virar and Surat and 37 cases between Vadodara and Geratpur in 2024-25. Officials said that the elevated railway tracks between Surat and Vadodara have meant a lower number of CROs — from 72 in 2022-23 to nine in 2024-25 — as compared to the other sections. The 565 kilometres of W-beam fencing installed along the route is also the longest 'thorough fenced section' of the Indian Railways. Chief Public Relations Officer, Western Railway, Vineet Abhishek, told The Indian Express, 'In the initial months, when Vande Bharat had started, there were incidents of cattle run-overs, which were very unfortunate. Western Railway, under the guidance of the Railway Board, took up this initiative in a mission mode to figure out a solution to bring down these cases. It (the collisions) not only adversely affects train operation but also raises concern for the safety of our train passengers…' Following the incidents reported during the early run of the Mumbai-Gandhinagar Vande Bharat — the second to be launched in the country — the Railway Protection Force (RPF) had identified vulnerable locations and carried out awareness and sensitisation campaigns at all the locations. In 2022, RPF conducted 1,023 awareness campaigns at vulnerable locations along with meetings with the sarpanches of all villages in the vicinity of railway tracks. The railways also identified that dumping of garbage along the railway tracks by the people also attracted the cattle in the area. Railway officials said that while conventional locomotives are fitted with cattle guards to prevent the animals from slipping under the train, the new designs of Vande Bharat are designed for an aesthetic look and the nose does not feature rail guards although the engines are robust and protected beneath the FRP layer. According to officials, the W-beam fencing was chosen after much deliberation, considering that it was the most popular crash-barrier on highways to absorb the impact of high-speed cars. The W-beam has been installed in a staggered manner to ensure that cattle do not stray onto the railway track and, at the same time, the path for villagers is not blocked throughout the tracks. The staggered installation also allows movement of railway goods across the tracks when needed. 'It was also equally important to bring down loss of animal life and resources for villagers residing near our railway tracks. Multiple solutions were explored and finally, the W-beam fence was installed in the entire section of the Vande Bharat route and Rajdhani route of the Western Railway. As a result, the number of CROs have come down drastically. It is almost negligible as compared to FY 2022-23,' Abhishek said. Vivek Kumar Gupta, General Manager, Western Railway, said, 'Train-animal collisions pose significant risks, including derailment. However, recent initiatives have led to a drastic reduction in cattle run-over rates, allowing drivers to operate trains with increased confidence and safety. Moreover, cattle have livestock value for the villagers. This initiative to fence the entire route has not only benefited the Railways, but also these villagers and their livestock. As a result, the initiative is being widely appreciated by all.'

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store