Ferguson Marine: Firm 'mitigating risks' affecting Glen Rosa delivery
And Graeme Thomson, the new chief executive of Ferguson Marine was unable to be clear on when the ferry would finally arrive for user by state-owed ferry operator CalMac although he said he remained "confident" of meeting the latest of what he called targets.
He told MPs: "We have a target date of quarter 2 of 26 and I'm sticking with that. What I mean is we're working to schedule and still have risks that we have to manage.
"So while that schedule is getting worked, I'm very conscious that we will need to mitigate the risks that will affect that schedule any further.
"So although we'll keep driving the programme to be as early in quarter two, we have risks that may manifest despite the effort to mitigate them, and that has potential to move that delivery out to later in quarter 2."
He also said he was committed to "refine" the delivery window by the end of this year and the costs "based on the success we have in mitigating the risks that we perceive at the moment that aren't yet sentenced and mitigated".
Last year wellbeing economy secretary Màiri McAllan said nationalised Ferguson Marine considered the latest delays and costs forecasts - which had Glen Rosa ready to use in September - was the "final position" after the firing of chief executive David Tydeman.
David Tydeman (Image: Ferguson Marine) Glen Rosa and its sister ship Glen Sannox were both due to be online within first seven months of 2018, to serve Arran.
In the midst of the delays and soaring costs, Ferguson Marine, under the control of tycoon Jim McColl, fell into administration and was nationalised at the end of 2019 with state-owned ferry and port-owning agency Caledonian Maritime Assets Ltd and the yard's management blaming each other.
Mr Thomson, appearing before the UK Parliament Scottish Affairs Committee repeated an "unreserved apology to the island communities".
Read more from Martin Williams:
He said: "It must be acutely frustrating for them to hear this and hear it again in May, given that we had said previously, September 25.
"I'm confident in what we've done. We are confident we'll make it for quarter two of 2026, but we do need to mitigate some risk before we can actually narrow that down."
A ferry user group official said that there was concern that the "goalposts appear to be being repositioned on delivery once again".
"Nobody wants anything but to for Ferguson Marine to finally deliver on the last of the ferries," he said. "But what are these risks that could affect scheduling.
"Most of us would want to see Glen Rosa after all the years of delay finally ready for the summer of next year, but if April is the earliest that it can be delivered, then it will, of course, miss the start of that and there are already signs that the timings are being pushed back and back, which has to affect CalMac planning."
Graeme Thomson (Image: Ferguson Marine) Ferguson Marine said Mr Thomson had spent his first weeks studying the delivery plans, working with finance and project management teams to challenge the assumptions on key milestones, critical paths, resource hours and costs to ensure the assessments are robust and well-informed with an appropriate level of risk attached.
In February, Ferguson Marine interim chief executive John Petticrew admitted to MSPs there was a risk of further delays to Glen Rosa and there were fears then of a six-month hold up.
He expected a full update on a "bottom-up exercise" on Glen Rosa with a view to provide a new schedule including updated costs by the end of February - but it and any amended costs and delay information did not emerge until now.
Glen Sannox finally entered service in January, some seven years behind schedule.
But in March, the Inverclyde shipyard was dealt a major blow after losing out to a Polish yard on a contract to build seven CalMac electric ferries, raising concerns over its future viability.
However, Deputy First Minister Kate Forbes said if the first phase of the small vessel replacement programme - responsible for building ferries capable of servicing short routes on the west coast of Scotland - had been awarded directly to Ferguson Marine, without any competition, it would have introduced 'substantial risk' and the prospect of court action.
Four days earlier, Mr Petticrew had resigned as chief executive for "personal reasons".
He initially took on the chief executive's role for six months after the firm's board dismissed his predecessor a year ago, but had agreed to stay on until Easter.
Ferguson Marine declined to explain what the "risks" were.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


STV News
2 hours ago
- STV News
Delivery of Glen Rosa marks ‘key milestone' as it enters dry dock
The second of Ferguson Marine's over-budget and delayed ferries has reached a 'key milestone', the shipyard has said. The MV Glen Rosa has now been moved to dry dock at Dales Marine Services in Greenock. The dry dock will allow the state-owned yard to carry out essential maintenance, repairs and inspections to the vessel. PA Media Works planned include rudder and stabiliser inspections, welding work to the bow clam doors and painting repairs. The Glen Rosa, which will serve the Arran route, is expected to remain in dry dock until August when it will return to Ferguson Marine's shipyard in Port Glasgow. The publicly owned Caledonian Maritime Assets Ltd (CMAL) is expected to be handed the ferry in the second quarter of next year following several delays. The ship, along with the now-delivered Glen Sannox, was meant to be delivered in 2018 and will now cost an estimated £460 million – up from the original price tag of £97 million for the two vessels. Graeme Thomson, chief executive of Ferguson Marine, said: 'Entering dry dock is a significant event in the build lifecycle of a new vessel and we are pleased we have reached this key milestone. 'I'm delighted to be able to demonstrate the progress that has been made and want to restate our commitment to delivering MV Glen Rosa, which we are currently confident will happen to schedule.' Kevin Hobbs, chief executive of CMAL, said: 'This is an important milestone, and we welcome this further step towards vessel completion and delivery.' Kevin Paterson, chief executive at Dales Marine Services, said: 'We are proud to play a role in the ongoing development of the MV Glen Rosa. 'Our team of experienced engineers at the Greenock dry dock will work closely with Ferguson Marine to ensure that the maintenance and repair work is completed to the highest standard. 'It is a pleasure to contribute to the journey of a vessel that will play a vital role in Scotland's ferry network.' Get all the latest news from around the country Follow STV News Scan the QR code on your mobile device for all the latest news from around the country


Scotsman
2 hours ago
- Scotsman
Delivery of ferry fiasco vessel Glen Rosa marks ‘key milestone' as it enters dry dock
The MV Glen Rosa, second of Ferguson Marine's over-budget and delayed ferries, arriving at dry dock at Dales Marine Services in Greenock. The second of Ferguson Marine's over-budget and delayed ferries has reached a 'key milestone', the shipyard has said. Sign up for the latest news and analysis about Scottish transport Sign up Thank you for signing up! Did you know with a Digital Subscription to The Scotsman, you can get unlimited access to the website including our premium content, as well as benefiting from fewer ads, loyalty rewards and much more. Learn More Sorry, there seem to be some issues. Please try again later. Submitting... The MV Glen Rosa has now been moved to dry dock at Dales Marine Services in Greenock. The dry dock will allow the state-owned yard to carry out essential maintenance, repairs and inspections to the vessel. Advertisement Hide Ad Advertisement Hide Ad Works planned include rudder and stabiliser inspections, welding work to the bow clam doors and painting repairs. The Glen Rosa, which will serve the Arran route, is expected to remain in dry dock until August when it will return to Ferguson Marine's shipyard in Port Glasgow. The publicly owned Caledonian Maritime Assets Ltd (CMAL) is expected to be handed the ferry in the second quarter of next year following several delays. The ship, along with the now-delivered Glen Sannox, was meant to be delivered in 2018 and will now cost an estimated £460 million – up from the original price tag of £97 million for the two vessels. Advertisement Hide Ad Advertisement Hide Ad Graeme Thomson, chief executive of Ferguson Marine, said: 'Entering dry dock is a significant event in the build lifecycle of a new vessel and we are pleased we have reached this key milestone. 'I'm delighted to be able to demonstrate the progress that has been made and want to restate our commitment to delivering MV Glen Rosa, which we are currently confident will happen to schedule.' Kevin Hobbs, chief executive of CMAL, said: 'This is an important milestone, and we welcome this further step towards vessel completion and delivery.' Kevin Paterson, chief executive at Dales Marine Services, said: 'We are proud to play a role in the ongoing development of the MV Glen Rosa. Advertisement Hide Ad Advertisement Hide Ad 'Our team of experienced engineers at the Greenock dry dock will work closely with Ferguson Marine to ensure that the maintenance and repair work is completed to the highest standard. 'It is a pleasure to contribute to the journey of a vessel that will play a vital role in Scotland's ferry network.' Last week, the new boss of Ferguson Marine has said the business will 'struggle' in the future if it is overlooked for a deal to replace an aging ferry. With the MV Lord of the Isles having sailed for the first time in 1989, the Scottish Government – throughoperator CalMac and procurement body Cmal – is looking for a replacement. Advertisement Hide Ad Advertisement Hide Ad The tendering process has not yet opened but Ferguson – which is also owned directly by the Scottish Government – is expected to bid for the contract. Appearing before the Scottish Affairs Committee at Westminster on Wednesday, Ferguson chief executive Graeme Thomson pushed for a direct award of the deal to the yard. 'I do support a direct award for the Lord of the Isles replacement,' he said. 'I am not aware of what might be any challenges or blockers to that, but I know the Scottish Government are considering how that would be sentenced.'

The National
3 hours ago
- The National
MV Glen Rosa marks ‘key milestone' as it enters Greenock dry dock
The MV Glen Rosa has now been moved to dry dock at Dales Marine Services in Greenock. The dry dock will allow the state-owned yard to carry out essential maintenance, repairs and inspections to the vessel. Works planned include rudder and stabiliser inspections, welding work to the bow clam doors and painting repairs. READ MORE: Scottish ice rink set to close due to 'spiralling energy costs' The Glen Rosa, which will serve the Arran route, is expected to remain in dry dock until August when it will return to [[Ferguson Marine]]'s shipyard in Port Glasgow. The publicly owned Caledonian Maritime Assets Ltd (CMAL) is expected to be handed the ferry in the second quarter of next year following several delays. The ship, along with the now-delivered Glen Sannox (below), was meant to be delivered in 2018 and will now cost an estimated £460 million – up from the original price tag of £97 million for the two vessels. Graeme Thomson, chief executive of Ferguson Marine, said: 'Entering dry dock is a significant event in the build lifecycle of a new vessel and we are pleased we have reached this key milestone. 'I'm delighted to be able to demonstrate the progress that has been made and want to restate our commitment to delivering MV Glen Rosa, which we are currently confident will happen to schedule.' READ MORE: Three men arrested under Terrorism Act after national Palestine demo in Edinburgh Kevin Hobbs, chief executive of CMAL, said: 'This is an important milestone, and we welcome this further step towards vessel completion and delivery.' Kevin Paterson, chief executive at Dales Marine Services, added: 'We are proud to play a role in the ongoing development of the MV Glen Rosa. 'Our team of experienced engineers at the Greenock dry dock will work closely with Ferguson Marine to ensure that the maintenance and repair work is completed to the highest standard. 'It is a pleasure to contribute to the journey of a vessel that will play a vital role in Scotland's ferry network.'