
Recovering PPIB's annual fee: Nepra approves 1.1 paisa per kWh tariff hike
This adjustment permits the annual PPIB fee to be treated as a pass-through cost, similar to other recoverable charges by the Central Power Purchasing Agency-Guarantee (CPPA-G) and the Nepra itself.
The Nepra held a suo motu public hearing on February 13, 2025, to seek input from PPIB and stakeholders. As per Nepra's rules, any fee levied on power generation or capacity is typically passed on to consumers.
Power tariff hike: govt reaches 'understanding' with IMF
In its determination issued Monday, Nepra acknowledged that PPIB has significant budgetary needs, including plans to develop infrastructure such as a dedicated office building. While these may be valid from an operational perspective, Nepra emphasised that any cost passed on to end-consumers must be carefully justified and balanced against electricity affordability.
'The Authority recognises PPIB's institutional requirements but also must ensure that costs allowed as pass-through items do not place an unjustified burden on consumers,' the determination stated. 'Only demonstrably necessary, efficient and proportionate expenses should be permitted under the Nepra Act.'
Nepra noted that while it scrutinises and approves the budgets of other licensees such as the Market and System Operators, it does not currently have the authority to vet PPIB's budgetary requirements. This lack of oversight, the Authority observed, reinforces the need for the PPIB fee to be rationalised and denominated in rupee terms to minimise exchange rate risks and unnecessary financial pressure on consumers.
From PPIB's perspective, the annual fee is necessary to ensure institutional financial sustainability and falls within its legal mandate. However, Nepra acknowledged that many Independent Power Producers (IPPs) view this fee as an added financial burden not originally factored into their tariff structures or Power Purchase Agreements (PPAs), especially since the PPIB Fee Rules were introduced in 2018.
Nepra noted that the CPPA-G has treated the fee as a pass-through in most cases. However, for projects under the 2015 Power Policy, this treatment depends on the 'change in law' provisions within their contractual frameworks, requiring both Nepra's determination and a government notification.
'In view of the legal framework, historical practice, and the need to maintain regulatory consistency, the Authority has allowed the PPIB annual fee as a pass-through, subject to compliance with the relevant provisions of PPAs/ EPAs and Nepra's tariff regime,' the decision stated.
PPIB earlier informed Nepra that while some IPPs have paid the annual fee without objection, others have raised concerns before forums including the Minister for Energy and the secretary Power Division. These IPPs argued that the original $300/MW fee was excessive and requested a downward revision.
In response, the PPIB Board reduced the annual fee to $250/MW through the 'PPIB Board (Fees and Charges) (Amendment) Rules 2021,' which were officially notified on June 15, 2022, following Board approval in August 2021.
Commenting on the decision of Nepra, Barrister Asghar Khan, a power sector legal expert, stated that the PPIB fee allowed by the Nepra as a pass-through is not permissible under the Nepra Act, Rules and Regulations. 'When PPIB fee is not part of the capital expenditure (CAPEX), operational expenditure (OPEX), Quarterly Tariff Adjustments (QTAs) or Fuel Price Adjustment (FCA), of the IPPs, then how in a slipshod manner, it to be treated as part of the tariff by the Nepra Authority,' he added.
According to him, the Nepra Authority does not have the competence and jurisdiction to admit and allow such charges, fees and taxes as part of the tariff when (i) PPIB is not a licensee of the Nepra and (ii) such fees, charges and fees are not levied as part of the generation, transmission and distribution business of the power entities. Needless to mention that such fees and taxes have been allowed in exercise of suo motu powers exercised by the Nepra Authority which powers are not vested in the courts of law let alone the Nepra Authority.
He stated that the Nepra Authority does not have the power and competence to convert fees and charges into tariff or terms and conditions of the tariff. The PPIB Fee levied under Section 5 (2) (i) of the PPIB Act 2012 prescribes that it shall receive fees and charges for processing applications and deposit and disburse or utilise the same, if required. Such fees and charges are never meant to be part of the tariff to be charged to the consumers of the electricity. Further, such fees and charges constitute part of the PPIB Fund under Section 14 of the PPIB Act 2012 and are not to be treated as a pass-through in the tariff.
He said furthermore, the PPIB fee is not part of the security package agreements or any power policy then how Nepra Authority has allowed such PPIB fee as part of the tariff and an additional burden on the consumers of electricity.
The PPIB is a public entity as such entity is defined under the Public Finance Management Act, 2019, and without any views of the Finance Division on the policy, guidelines, rules or regulations framed for the PPIB Fund constituted under the PPIB Act, 2012, Nepra has allowed these charges and fee as part of the tariff which in essence means that monies from the Public Accounts are withdrawn to be collected and disbursed to the PPIB fund which is violation of the constitutional provisions, Nepra Act, 1997, PPIB Act, 2012, and PFMA 2019, he said.
He was of the view that the Nepra Authority without any financial analysis has allowed the entire fees levied by the PPIB in a blanket manner. The scope of such fee is unlimited spanning from 1994 Power Policy, 2002 Power Policy, 2015 Power Policy, RE Policy 2006, ARE Policy 2019 and others. 'The Nepra Authority's Order is bad in law as it does not define the scope, quantum, causation; etc., of such fee in relation to the electric power services and is a taxation without the approval of Parliament under Article 77 of the Constitution of Pakistan which clearly directs and mandates that 'No tax shall be levied for the purposes of the Federation except by or by or under the authority of Act of [Majlis-e-Shoora (Parliament)],' he concluded.
Copyright Business Recorder, 2025
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Business Recorder
2 days ago
- Business Recorder
EPQL seeks PD's support for early gas supply from Badar field
ISLAMABAD: The Engro Powergen Qadirpur Limited (EPQL) has approached the Power Division for support in expediting the signing of a Supplementary Agreement (SA) to utilise low-BTU indigenous gas from the Badar-1 gas field. In a letter to the Power Division, EPQL CEO Adeel Qamar stated that the company operates a 225-MW power plant running primarily on permeate gas from the Qadirpur gas field under a Power Purchase Agreement (PPA) signed with the Central Power Purchasing Agency Guarantee Limited (CPPA-G) on October 26, 2007. Since the commencement of commercial operations in March 2010, the plant has maintained a high position in the Economic Merit Order (EMO) and supplied 18.9 billion units of electricity to the national grid with high gas-based utilisation. Engro Powergen plant: PD and CPPA-G at odds over gas pricing mechanism The EPQL claims that its operations have delivered substantial benefits to electricity consumers and the Government of Pakistan, including: (i) Rs 89 billion in savings through procurement of low-cost electricity;(ii) $1.6 billion in foreign exchange savings by using indigenous gas; and (iii) Rs 96 billion in revenue for fuel suppliers (SNGPL and OGDCL) from the sale of permeate gas that was previously being flared. 'These benefits were only possible due to the extensive cooperation and support from the Government of Pakistan and its departments, including PPIB, CPPA-G, and NTDC,' said Qamar. To address the declining gas supply from Qadirpur and to enhance the plant's utilization, EPQL, in collaboration with stakeholders such as PPIB and CPPA-G, explored alternative fuel sources. As a result, NEPRA, in its determination dated February 20, 2024, approved the use of low-BTU gas from the Badar-1 field as an additional fuel source for the EPQL's operations. Following NEPRA's approval, the EPQL entered into an agreement with Petroleum Exploration Limited (PEL) on August 5, 2024, for the supply of 8–13 mmscfd of low-BTU gas from Badar-1. Subsequently, the EPQL submitted a draft Supplementary Agreement to the PPA for CPPA-G's review on August 26, 2024, after detailed consultations. However, the company says the matter remains unresolved. 'We note with deep concern that, despite a lapse of 10 months, the matter is still pending with CPPA-G, delaying the opportunity for EPQL to generate additional electricity using low-BTU gas from Badar-1,' Qamar stated. EPQL says the infrastructure for gas supply from Badar-1 is fully operational, and off-take can begin immediately upon receiving the necessary approvals. The transaction is structured on a Take-and-Pay basis, meaning gas will only be used if it qualifies under the Economic Dispatch Merit Order. The company estimates that had the approval been granted by October 2024, it could have generated an additional 122 million units of electricity, resulting in:Rs 787 million in potential savings for power consumers, and$9 million in foreign exchange savings. 'We have consistently followed up with CPPA-G and responded promptly to all queries, but the approval remains pending. Given that we are currently in the peak summer season and relying on high-cost imported fuels for electricity generation, it is imperative to finalize the Supplementary Agreement without further delay,' Qamar added. The EPQL has urged the Power Division to facilitate the earliest possible approval to unlock the economic and operational benefits associated with the project. Copyright Business Recorder, 2025


Express Tribune
4 days ago
- Express Tribune
Engro Powergen seeks early gas supply from Badar field
Listen to article Engro Powergen Qadirpur Limited (EPQL) has urged the federal government to expedite the long-pending approval of a supplemental agreement that will allow it to utilise low BTU gas from the Badar-1 field. In a letter sent to Power Division Secretary Dr Muhammad Fakhre Alam Irfan, EPQL Chief Executive Officer Adeel Qamar highlighted that despite completing all technical and procedural formalities, including infrastructure readiness and regulatory approvals, the supplemental agreement remains pending, which was submitted to the Central Power Purchasing Agency-Guarantee (CPPA-G) in August 2024. EPQL, which operates a 225-megawatt power plant primarily on permeate gas from the Qadirpur gas field, entered into an agreement with Petroleum Exploration Limited (PEL) on August 5, 2024 for the supply of 8-13 million cubic feet per day (mmcfd) of low BTU gas from Badar-1. It came after the National Electric Power Regulatory Authority (Nepra) formally approved the use of Badar-1 gas through a determination issued on February 20, 2024. However, the EPQL's proposal to amend its power purchase agreement (PPA) with CPPA-G to incorporate the use of this indigenous gas has yet to be approved. The company has cautioned that continuous delay not only undermines the use of cheaper domestic energy resources but also forces reliance on expensive imported fuels amid peak summer demand. In the letter, the company noted that if approval had been granted by October 2024, EPQL could have generated an additional 122 million units of electricity using the low BTU gas, resulting in estimated savings of Rs787 million for power consumers and $9 million in foreign exchange. 'Infrastructure is ready and we can begin immediate offtake. Moreover, the transaction is based on a take-and-pay model, meaning gas will only be utilised when it is competitive under the economic dispatch merit order,' the CEO said in the letter. Since commencing operations in March 2010, EPQL has contributed approximately 18.9 billion units of electricity to the national grid, saving the country an estimated Rs89 billion and $1.6 billion in foreign exchange by using indigenous permeate gas. The company emphasised that this track record of cost-effective generation underlines the urgent need to begin Badar-1 gas supply. While acknowledging past cooperation from government entities, EPQL expressed dismay over the current lack of progress and called on the Power Division to facilitate early approval of the supplemental agreement. Given the summer energy crisis, the company said that the delay was becoming increasingly costly and counterproductive to the national energy security goals.


Express Tribune
4 days ago
- Express Tribune
Rs4 tariff relief likely for KE customers
Listen to article Electricity consumers will get a power tariff relief of Rs4.0349 per kWh in the bill for the month of July, according to the decision taken by the National Electric Power Regulatory Authority (Nepra) on Wednesday on a petition moved by the K-Electric (KE). The KE's petition pertained to provisional monthly Fuel Charges Adjustment (FCA) for the month of April 2025, indicating a relief of Rs4.0349 per kWh to be passed on to customers in the metropolis in their monthly bills for July 2025. Fuel charge adjustments are incurred by utilities due to global variations in fuel prices used to generate electricity, and the changes in generation mix. These costs are reflected in the customer bills following Nepra's scrutiny and approval. Customers also benefit from negative FCA in their bills when global fuel prices decrease. Rates charged to customer bills are determined by Nepra and notified by the federal government. As per Nepra decision, the FCA shall be applicable to all the consumer categories except lifeline consumers, domestic protected consumers, electric vehicle charges stations (EVCS), and prepaid electricity consumers of all categories who opted for prepaid tariff. Nepra has provisionally retained an amount of Rs800 million in respect of adjustments on account of partial load, open cycle and degradation curves along with start-up cost pursuant to NEPRA's decision regarding generation tariff for the control period July 2023 onwards from the FCA for April 2025 to be adjusted against the pending claims of KE to ensure that consumers are not burdened at later stage.