
Power generation stabilises after falling for two years
Pakistan's power generation reached 127,159 gigawatt-hours (GWh) in financial year 2024-25, remaining almost unchanged as compared with previous year's production of 127,059 GWh, according to a report released on Monday.
The stability in power generation came following a decline over the past two years. Year FY25 could be divided into two parts – in the first nine months (July-March), power generation fell 2% to 90,147 GWh while in the fourth quarter (April-June), the generation increased 7% to 37,012 GWh. The recovery in the latter part of the year helped offset the earlier decline, said Topline Research in its report.
The uptick in 4QFY25 was led by the diversion of captive power plants to the national grid after the government imposed an off-grid levy on captive power users, effective from February 2025. Furthermore, the government also announced a reduction in the overall unit cost in the April-June quarter after using savings that stemmed from tariff negotiations with the independent power producers (IPPs) and the reallocation of petroleum development levy (PDL).
In the first three quarters, the report mentioned, the electricity generation declined as bulk buyers largely relied on their own captive power production by using furnace oil, gas and other fuel sources.
Hydel electricity contributed the most to total production, having a 31.44% share in FY25 compared to 31.38% in FY24. It was followed by re-gasified liquefied natural gas (RLNG)-based power production, which accounted for 17.48% of total production against 18.70% a year earlier.
Local coal-fired plants contributed 12.23% in FY25 vs 12.51% in FY24 while imported coal-run plants had a 7.13% share compared to 3.40% in FY24. Nuclear, gas, wind and furnace oil-based generation contributed 17.66%, 8.82%, 3.02% and 0.41%, respectively.
Three new hydroelectric power additions to the system include SK Hydropower Station, initially commissioned at 221?megawatts, with total planned capacity of 884?MW; Pehur Hydel Power Plant, having capacity of 18?MW; and Marala Hydropower Plant, with a capacity of 7.64?MW. Additionally, the Lakhra Power Plant (Genco-IV), a 150MW coal-fired facility, has also been added.
In FY25, the average generation cost edged down 2% to Rs8.6 per kilowatt-hour (kWh) compared to Rs8.8 per kWh in FY24. In June alone, the fuel cost dipped 9% year-on-year (YoY) but was up 1% month-on-month to Rs7.9 per unit.
"It is interesting to note that around 46% of power generation came from RLNG, coal and gas with average fuel cost of Rs16.5 per unit in FY25," Topline commented.
Separately, the cost of imported coal-based generation declined 28% YoY to Rs16.7 per kWh due to a 5% drop in international coal prices. Similarly, the RLNG cost decreased 1% on the back of a decline in international crude oil prices by 12% to $70 per barrel in FY25.
"We expect 5-8% growth in electricity consumption in FY26 due to gradual and continuous transition of captives to the national grid and imposition of PDL on furnace oil. Furthermore, gradual economic recovery amidst easing interest rates will also help increase power generation," the report added.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Business Recorder
8 hours ago
- Business Recorder
Forced curtailments, low demand drag down Pakistan's oil & gas output in FY25
Oil and gas production in Pakistan declined significantly by 12% and 7% year-on-year (YoY), respectively, in FY25, as output from key fields remained under pressure due to forced curtailments and lower gas demand. 'The contraction in hydrocarbon output comes amid forced curtailments at Nashpa, TAL and other blocks due to lower gas demand,' said Arif Habib Limited (AHL), in its report released on Thursday. As per the report, major oil fields such as Nashpa, Makori East, Pasakhi, Adhi, Taj, Mardenkhel, Maramzai, Rajian, and Umar experienced a drop in production during FY25. AHL E&P Universe Oil Production (BOPD) FY25 FY24 YoY OGDC 30,961 33,027 -6% PPL 10,221 11,325 -10% POL 4,444 4,727 -6% MARI 1,271 1,193 7% Gas Production (MMCFD) OGDC 652 715 -9% PPL 480 532 -10% POL 53 62 -14% MARI 818 799 2% In terms of gas production, key fields including Mari, Qadirpur, Sui, Sharf, Kandhkot, Naimat West, and Sutiari Deep registered a decline. On a quarterly basis, oil and gas production in Pakistan decreased by 15% and 10% YoY, respectively, in 4QFY25. Pakistan Petroleum Limited commissions new exploratory well in Sujawal Speaking to Business Recorder, Iqbal Jawaid, Senior Investment Analyst at AHL, said that the decline in hydrocarbon production this fiscal year 'was primarily due to weak gas demand from the consumers'. 'The problem is that RLNG gas is available in the system, and as per our agreement with Qatar, the government is bound to purchase it. So, what is within the government's control? Domestic gas production… hence, local production was curtailed in FY25,' he said. The analyst was of the view that due to gas curtailment oil production was also curtailed, as both are extracted together. Commenting on the economic impact, Jawaid noted that with lower oil production in Pakistan, our reliance on imported crude further increases. 'The only way out of all this is renegotiating the RLNG deal in March 2026,' he said. The senior analyst explained that under the original agreement signed in 2016, the terms can be renegotiated after 10 years. 'At that point, the government can seek a reduction in RLNG rates and volumes. If this happens, domestic gas and oil volumes are likely to increase, and gas prices — influenced by the lower RLNG rate — will also decline,' he said. Meanwhile, as per the report, a total of 23 exploratory wells and 30 appraisal/development wells were spudded during FY25, against a target of 27 exploratory wells and 40 appraisal/development wells. 'The exploration efforts of Pakistani E&P companies in the listed space yielded 21 discoveries during FY25, with a cumulative discovery size of approximately ~3,187 bopd of condensate and ~303 mmcfd of gas,' AHL said.


Business Recorder
16 hours ago
- Business Recorder
Minister visits K-IV project to review progress
LAHORE: Federal Minister for Water Resources Mian Muhammad Mueen Wattoo visited Greater Karachi Bulk Water Supply Scheme (K-IV Project) and reviewed the ongoing development works on the project. The federal minister visited in detail various key work fronts, which included intake structure and pumping stations being constructed at Keenjhar lake, water conveyance system consisting of pressurized pipeline from Keenjhar to Karachi as well as water reservoirs and filtration plants in suburbs of Karachi. During the visit, the federal minister was briefed by the project team about the site-wise progress achieved so far, remaining works and timelines for their completion. It was briefed that construction work on all components of the project is in progress at a satisfactory pace. Overall physical progress stands at 63 percent, while a sum of Rs 86.4 billion has so far been spent on construction of the project. Phase-I is planned to be completed in 2026, provided the required funds are made accordingly. Speaking on the occasion, the federal minister expressed satisfaction over the pace of work and reiterated the federal government's full support for the project. K-IV is a vital scheme for supplementing water supplies to Karachi to meet water requirements for the urban use. 'We are committed to ensuring completion of K-IV at the earliest as it is one of the priority projects of the Ministry of Water Resources,' he added. The minister emphasized the need for enhanced coordination among all stakeholders to remove bottlenecks for smooth implementation of the project. He also directed the consultants and the contractors to adhere to the quality standards stipulated for the project. The K-IV project is a critical infrastructure initiative aimed at addressing Karachi's acute water shortage by providing an additional 650 million gallons per day (MGD) water to Karachi from Keenjhar lake. The project is planned to be completed in two phases. At present, WAPDA is constructing Phase-I of to supply 260 MGD water to Karachi. Phase-II, when implemented, will also augment another 390 MGD water to the system for Karachi. Phase-I is being implemented through eight contract packages awarded to different local and international contractors. Copyright Business Recorder, 2025


Business Recorder
18 hours ago
- Business Recorder
Has Rs1.71/unit electricity relief vanished?
It was widely expected that the government would continue the Rs1.71 per unit electricity subsidy component—backed by the IMF staff-level agreement, which explicitly cited plans to fund the relief via additional Petroleum Levy collections. Yet, to the surprise of many, the subsidy appears to have quietly disappeared—if not formally withdrawn, then at least absent from the electricity bills issued for July 2025. Recall that the only component explicitly extended into FY26 was the Rs182 billion relief—equivalent to Rs1.71 per unit—for all non-lifeline consumers, financed through the enhanced Petroleum Levy. The government, in its communication with the IMF, had committed to maintaining this limited relief until June 30, 2026. Significant ambiguity now surrounds the fate of this relief and its continuity into FY26. The matter came up during Nepra's recent tariff hearing, but the Ministry of Energy's remarks did little to resolve the uncertainty. In its response, the Ministry noted that the 'average applicable consumer tariff in July 2025 would be lower by around seven rupees compared to July 2024.' While ostensibly reassuring, the phrasing raises more questions than it answers. No assumptions were disclosed, nor was it clarified whether the comparison referred to gross billing or adjustments embedded within the base tariff trajectory. With the Rs1.71 per unit subsidy now seemingly off the table, the month-on-month increase in tariffs for non-lifeline protected consumers—who account for the bulk of domestic electricity consumption—exceeds 30 percent. Previously, under the assumption of subsidy continuity, first and second protected slabs were projected to rise by 11 and 9 percent, respectively. They now stand to increase by 35 and 26 percent, respectively. Among non-protected slabs, effective tariffs for the first three categories are slated to rise by 12, 9, and 8 percent month-on-month. This development implies that effective tariffs in July may be materially higher than assumed—at odds with both prior policy signalling and the inflation projections built on that premise. Whether this reflects a temporary lapse awaiting formal notification, an oversight in tariff design, or a quiet policy reversal is yet to be clarified. What is clear, however, is that this shift—if sustained—has real implications that one hopes the Pakistan Bureau of Statistics (PBS) appropriately incorporates any change in effective tariffs into its CPI computation, lest the official inflation trajectory miss a key price signal affecting millions.