No end to water woes as K-IV hits another snag
The water crisis has been plaguing most areas of Karachi for years. The city, which is supplied 650 million gallons of water per day from two sources, the Indus River and the Hub Dam, has a daily requirement of 1200 million gallons. Yet even after the passage of nearly two decades, the shortage of 550 million gallons could not be addressed.
Launched in 2016 under the supervision of the Sindh government and the Karachi Water and Sewerage Corporation (KWSC), the K-IV project set out to supply 260 million gallons per day of water to Karachi. In 2021, the federal government took over the project, handing it over to the Water and Power Development Agency (WAPDA). Under the new plan, its cost reached Rs126 billion, and construction was to be completed by December 2025.
According to WAPDA's General Manager South and the Project Director of K-IV Aamir Mughal, thus far 55 per cent of the work on K-IV has been completed however, due to power supply issues and other reasons, the project's completion has been delayed to June 2026, with its cost likely to be increased by 20 per cent due to the high cost of materials," said Mughal.
As per sources of the Express Tribune at WAPDA, even if this important project is completed in time, the citizens will not benefit from the additional supply of water since the three other projects associated with the K-IV are still stuck in limbo. While one project is under construction and will be completed in two years, work on the other two has not even started.
The most important of these is the Augmentation Plan, which involves the construction of an underground pipeline of K-IV from Keenjhar Lake to the Kathore area of Karachi, after which a system of bulk lines for the inner city, spanning about 100 kilometres, will be established. This project will be completed in two years.
The second project, the construction of a power station, involves a 132 KV transmission line that will be installed from the Jhampir Grid Station to the K-IV pumping complex near Keenjhar Lake, enabling the pumping complex to supply 50 MW of electricity. The construction work on the project will start soon and will be completed by December 2025.
Likewise, the Kalri Baghar (KB) Feeder Lining Project, involves the cleaning and expansion of a 38-mile long canal that supplies water to the Keenjhar Lake. This will remove any obstructions in the flow of 260 million gallons per day from the Indus River to Keenjhar Lake. This project too will be completed in two years.
Dr Syed Nawaz Al-Huda, a regional planner, was of the opinion that the Sindh government should be held accountable for the delay in the construction of the power plant, installation of bulk lines and the KB Feeder Lining Project. "Even if the federal government completes the K-IV project on time, water might not be available since the Sindh administration has deliberately delayed resolving the water crisis. Where water projects continue to face delays, executive engineers have strengthened the dirty business of the tanker mafia by creating an artificial crisis in posh and middle-class areas, due to which people are forced to buy tankers at high prices," confirmed Al-Huda.
According to a survey conducted by The Express Tribune, the connivance of the top officials of the KWSC with the tanker mafia has created an artificial water crisis in the city, which is particularly affecting areas like Clifton, Defence, Gulshan-e-Iqbal Block 13D-2 and 13D-3, North Nazimabad, Nazimabad, Liaquatabad and the Pakistan Employees Cooperative Housing Society (P.E.C.H.S) among other areas.
The Express Tribune tried contacting the Secretary of Irrigation Zarif Khedro to confirm the news concerning the delay in the completion of K-IV, but he chose not to respond.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Express Tribune
2 hours ago
- Express Tribune
UNSC report affirms BLA-TTP nexus
Listen to article Outlawed terrorist groups — Balochistan Liberation Army (BLA), including its Majeed Brigade, and Tehrik-e Taliban Pakistan (TTP) — have "close coordination", according to the annual report of the UN's 1988 Taliban sanctions committee monitoring team. The United Nations Security Council report pointed out that "some BLA attacks showed a high degree of complexity and brutality", citing Jaffar Express' dramatic hijacking in Pakistan's Balochistan province on March 11, 2025, killing 31 people, including 21 hostages. The report also took note of the April terrorist attack in Pahalgam, in Indian Illegally Occupied Jammu Kashmir (IIOJK), without giving any opinion on the incident. It mentioned The Resistance Front (TRF), which initially claimed responsibility for the attack, later retracted it. Despite intense Indian campaign, the report did not link TRF with the Lashkar-e-Tayyiba (LeT), but noted that a member state had insisted that the attack could not have happened without LeT's support. At the same time, another member state, it added, rejected these views, saying that LeT was defunct. The report said that regional relations remain fragile and "there is a risk that terrorist groups may exploit these regional tensions." It added that the TTP had approximately 6,000 fighters and continued to receive substantial logistical and operational support from the de facto authorities (Taliban). "Some member states reported that the TTP maintained tactical-level connections with ISIL-K or Daesh," it said. "TTP continued to carry out high-profile attacks in the region, some of which incurred mass casualties," said the report. It reported that the TTP had continued access to a range of weapons, enhancing the lethality of attacks — a reference to the military equipment left behind by the departing American troops in 2021. "One member state reported that in January 2025, the TTP provided training to terrorists in Balochistan." The report also said that the de facto authorities in Afghanistan — Taliban — continued to maintain a permissive environment for a range of terrorist groups, including Al-Qaeda and its affiliates, posing a serious threat to the security of Central Asian and other countries. The ISIL-K or Daesh, it added, continued to represent the most serious threat, both regionally and internationally. "With about 2,000 fighters, ISIL-K continued to recruit both inside and outside Afghanistan, including among Central Asian States and the Russian North Caucasus, as well as disaffected fighters from other groups," the report said. "There are concerns that some extremist fighters could move from the Syrian Arab Republic to Afghanistan and further to stage operations against regional States, firstly in Central Asia." "In North Afghanistan and areas close to the Pakistani borders, the ISIL-K indoctrinated children in madrassas, establishing a suicide training course for minors aged approximately 14 years old," the report said. "The ISIL-K continued to prioritise attacks on Shia communities, the de facto authorities and foreigners. Under the leadership of Sanaullah Ghafari, fighters were scattered across the northern and north-eastern provinces of Afghanistan." The ISIL-K, it added, tried to establish operations in the states neighbouring Afghanistan and globally. The efforts of the de facto authorities diminished the ISIL-K capabilities, but it continued to operate with relative impunity, exploiting discontent with Taliban governance. "While the leadership remained predominantly Afghan Pashtun, the rank and file were now mostly of Central Asian origin. Some of the ISIL-K supporters attempting to cross borders were female, including wives of Central Asian fighters," the report added.


Business Recorder
3 hours ago
- Business Recorder
Order issued by Sindh ombudsman: KE CEO denies charges
KARACHI: K-Electric (KE) CEO Moonis Alvi vehemently denies charges of harassment in the 22-page order by the Sindh ombudsman on Thursday, categorically stating that he is set to appeal the decision that his lawyer termed an 'unreasoned order'. In a series of tweets on X, Alvi – the longest-serving CEO of KE – said that he was going to fight back. 'The recent verdict is deeply distressing to me,' he said on X. 'While I respect the legal process and the institutions that uphold it, I must, in good conscience, state that the findings do not reflect the truth of the situation as I experienced it. 'I am currently reviewing the decision with my legal counsel and will be exercising my right to appeal… I remain committed to ensuring that the truth is fully brought to light, through all lawful means available.' On behalf of Alvi, Senior Counsels Barrister Abid S Zuberi and Barrister Ayan Memon announced the intention to appeal. 'We respect the honourable court and all its decisions. However, in light of serious procedural and legal inconsistencies, we are moving to appeal this decision before the appropriate forum and are confident that justice will prevail. 'The distorted framing of performance feedback as harassment, imposition of severest penalty without reasoned rationale and anchoring of baseless allegations are massively concerning. 'Mr Alvi gave full disclosure of work performance-related issues of the complainant and retaliatory complaints after her termination. These facts have been totally ignored. 'A substantial portion of the order has been dedicated to frivolous allegations, not backed by hard evidence.' In his message on X, KE Spokesperson said that today's decision by the Ombudsman has been a challenging moment for the KE family, for our stakeholders and well-wishers alike. On behalf of KE, want to state unequivocally: KE stands by the principles of truth, due process, and the values of a professional and respectful workplace. Copyright Business Recorder, 2025


Express Tribune
14 hours ago
- Express Tribune
Sindh Ombudsman finds KE CEO guilty of harassment, orders removal
Listen to article The Sindh Provincial Ombudsman has ordered the immediate removal of K-Electric's Chief Executive Officer, Moonis Alvi, and imposed a fine of Rs2.5 million after finding him guilty of workplace harassment. The order came in response to a complaint filed by Mahreen Aziz Khan, a former consultant and the company's first female CxO since its corporate restructuring began in 2009. The complaint, lodged in November 2020 under the Protection Against Harassment of Women at the Workplace Act, 2010, accused Alvi of harassment and creating a hostile environment. In his verdict, Justice (retd) Shahnawaz Tariq, who presided over the case, stated that Alvi had committed harassment and caused psychological distress to Khan and her team. Also Read: Pakistan launches new remote sensing satellite from China 'Accused No.1 Moonis Abdullah Alvi has committed harassment, created hostile environment and caused mental agony at the workplace to the complainant Mahreen Aziz Khan and her team,' the ruling said, citing Section 2(h) of the Act. The Ombudsman ordered Alvi's removal from service under Section 4(ii)(d) of the Act and directed him to pay the fine within one month. In case of non-compliance, the verdict allows for the seizure of his movable and immovable assets, and the blocking of his national identity card and passport. Three other individuals — Rizwan Dallal (Chief People Officer), Col (R) Wahid Asghar (Chief of Security), and Khalid Rafi (Board Member, HR Committee) — were also named in the original complaint but were discharged due to lack of evidence. 'In the absence of direct evidence, the allegations against the three co-accused could not be substantiated,' the ruling said. In a statement shared on social media platform X (formerly Twitter), Alvi expressed disappointment with the ruling. I have always upheld the values of integrity and dignity in professional interactions, and I deeply believe in fostering safe and inclusive workplaces for all. The recent verdict is deeply distressing to me. While I respect the legal process and the institutions that (1/4) — Moonis Alvi (@alvimoonis) July 31, 2025 'I have always maintained professionalism and integrity in all workplace relationships,' he said. 'The recent verdict is extremely distressing. I respect the legal system, though the outcome does not reflect the reality of my experience.' Alvi added that he is reviewing the decision with legal advisors and intends to appeal.