Tshwane BRT project faces R15 million irregular expenditure amid delays

Tshwane BRT project faces R15 million irregular expenditure amid delays

IOL News30-04-2025
The City of Tshwane is hopeful that a delayed project to construct a bus rapid transit route, known as Line 2C, in Pretoria East, will be completed this month.
Image: Oupa Mokoena / Independent Newspapers
A Tshwane council report has revealed that an ongoing bus rapid transit (BRT) project in Pretoria East has incurred a staggering amount of R15 million in irregular expenditure.
The DA first raised allegations of irregular expenditure on the project in March, but the city failed to respond to media inquiries about the claims.
However, a council report showed that the project's budget was increased by R15 million due to delays, which also led to a request for a time extension to complete the project.
The report cited specific delays, including late payment of the June 2023 payment certificate, prompting the contractor to request an extension.
Other delays were the relocation of a 700mm bulk water main pipeline, which halted work on a 400m road section, and the construction of a new retaining wall for a median slip lane due to level differences between the east and westbound roads.
The report noted that the project faced typical challenges for its scale, including delayed payments to subcontractors and labourers.
This, according to the report, caused work to slow down at the start of the month, only gaining momentum after payments were made.
The report was compiled after the Section 79 oversight committee for the municipal Department of Roads and Transport inspected the A Re Yeng Line 2B and 2C Lynwood Road Expansion project.
The committee was updated on the project's progress and challenges, learning that it was 82% complete with an expected completion date of April 2025.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Next
Stay
Close ✕
The committee was informed that the outstanding work included walkways and a cycle lane, and despite challenges, the project timeline remained on track.
Councillor Brendon Govender questioned the project's 82% completion status given the remaining work, and requested a more comprehensive report with detailed information.
On the other hand, DA councillor Dikeledi Selowa asked questions about the project's expenditure, public participation outcomes, and the resurfacing of new roads.
The project consisted of two work packages, which included upgrading intersections along Lynnwood Road and Atterbury Road, from University Road to Justice Mahomed Road.
The work included upgrading the existing Kings Highway Culvert, sewer diversion, and water relocation.
The construction involved relocating existing services like waterlines, widening intersections, and adding lanes.
In March, the DA demanded a thorough investigation into the delays plaguing the construction of Line 2C, a BRT route in Pretoria East.
At the time, Selowa expressed concern that the Line 2C route project had allegedly accumulated R15 million in irregular expenditure.
She criticised the city for not fulfilling its promises, especially regarding replanting trees removed during the project.
She also said the DA plans to scrutinise the project's financials to assess whether the city got value for money spent on each item.
The city had previously approved an extension of time and variation of scope for the Line 2C project, pushing the completion date to April 18, 2025.
Municipal spokesperson Lindela Mashigo said the project missed the deadline due to persistent rains, 'and there is an extension of time until the end of June, which does not have cost implications'.
Regarding the claim that the city incurred R15 million in irregular expenditure, he said: 'There is no irregular cost that has been incurred.'
This decision was made due to changes in scope, including relocating a 700mm water pipeline and constructing a new retaining wall to prevent collapses.
Mashigo had not yet responded to the DA's allegations that the BRT project had incurred R15 million in irregular expenditure due to delays, nor had he commented on potential consequences for those responsible, or the city's planned consequence management measures.
He had also not confirmed whether the contractor met the April 18 deadline.
rapula.moatshe@inl.co.za
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Final leg of national budget process in peril amid DA's plans to boycott budgets of compromised ministers
Final leg of national budget process in peril amid DA's plans to boycott budgets of compromised ministers

Eyewitness News

time13 hours ago

  • Eyewitness News

Final leg of national budget process in peril amid DA's plans to boycott budgets of compromised ministers

Lindsay Dentlinger 2 July 2025 | 13:24 Picture: @ParliamentofRSA/X CAPE TOWN - The final leg of the national budget process could hit another snag amid the Democratic Alliance (DA)'s plans to boycott the budgets of at least two departments presided over by compromised ministers. A parliamentary legal opinion suggests that the Appropriation Bill can only be passed if all departmental votes have been agreed to. If the DA follows through with this threat, it means the African National Congress (ANC) might again have to shop around for votes to ensure the bill crosses the line when it's put to the vote in three weeks' time. Over the weekend, DA leader John Steenhuisen said that while his party would reject some departmental votes, it would not vote against the Appropriation Bill as a whole. ALSO READ: • MKP, EFF reject transport dept's budget, say it lacks vision for transforming public transport • Majority of political parties in NCOP reject higher education dept's budget, call for Nkabane's axing Steenhuisen said the protest action was in response to the ANC not acting against those fingered in corruption, while firing a DA deputy minister for unsanctioned travel. But a legal opinion to Parliament's Standing Committee on Appropriations advises that all of the 42 separate votes have to be passed first, before the schedule to the bill can be put to the vote. This means if the Government of National Unity (GNU) is not united on even one of the departmental votes, the bill can not be put to the House for approval. "The Public Finance Management Act requires that Parliament first approves the votes in Schedule 1 to the Appropriation Bill and then consider Schedule 1 for approval. The National Assembly rule 328, gives effect to this provision by requiring the same procedure," reads the legal opinion. The DA's latest pushback against the ANC could once again put the ANC in a budget predicament. In March, it had to rely on parties outside of the coalition to shore up the votes needed to pass the fiscal framework, which underpinned a previous version of the budget, which was also rejected by the DA and Freedom Front Plus. Now it may have to do so again to ensure the budgets of all departments, including those run by ministers who don't meet the DA's approval, are passed. The Appropriation Bill must be passed within four months of the start of a financial year, which is the end of July, else departments' spending will be severely curtailed to only 10 percent monthly of the previous year's budget.

KDM cancels R350k Durban July Ballito Experience sponsorship
KDM cancels R350k Durban July Ballito Experience sponsorship

The Citizen

time15 hours ago

  • The Citizen

KDM cancels R350k Durban July Ballito Experience sponsorship

The KwaDukuza municipality (KDM) has officially withdrawn its R350 000 Durban July Ballito Experience sponsorship following political pressure and public scrutiny. The decision was made during a special council meeting held on Wednesday, July 2, just days before the first event on Friday, July 4. The sponsorship, intended to support the Durban July Ballito Experience, hosted by Enterprise iLembe, sparked widespread criticism after it was revealed that two of the three event days (July 4–6) would be held in eThekwini, outside KDM's jurisdiction. The event had already received R5-million in funding from the national Department of Sports, Arts and Culture, raising questions about the necessity and appropriateness of additional municipal support. Following deliberations, council decided the sponsorship would not be in line with the Municipal Finance Management Act and rescinded the funds. The Durban July Ballito Experience begins with a golf day at Umhlali Country Club for government officials and investors on July 4, ending with a cultural fashion, food and music event at Beach Bums in Westbrook on July 6. On Saturday, the business and tourism agency are also hosting a swish VIP Durban July event at Greyville Racecourse. Speaking at the event launch at the Sangweni Tourist Information Centre in Ballito on June 3, Enterprise iLembe CEO, Siyabonga Mazibuko said the event was expected to create up to 500 local jobs, although it was not confirmed whether these would be full-time or contract positions. Enterprise iLembe and KDM were met with criticism from the Democratic Alliance (DA) in KwaDukuza, who along with The MK Party, did not support the sponsorship. DA caucus leader Privi Makhan accused the KwaDukuza Council's leadership of misusing public funds to benefit politically connected individuals under the pretext of economic development. Makhan called it a victory for residents and ratepayers. She also accused the ANC-led council of attempting to 'steamroll' the payment through despite clear opposition. 'Their plan to bankroll an event outside our jurisdiction was a clear betrayal of responsible governance for an event being held outside KDM,' said Makhan. 'Our residents deserve leaders who put their needs first, not those leaders who are merely political side-shows, attempting to pay off their debt through council coffers.' Enterprise iLembe and KDM officials were unavailable for comment at the time of publication. Stay in the loop with The North Coast Courier on Facebook, X, Instagram & YouTube for the latest news. Mobile users can join our WhatsApp Broadcast Service here or if you're on desktop, scan the QR code below. At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Urgent need for private sector investment in South Africa's transport infrastructure
Urgent need for private sector investment in South Africa's transport infrastructure

IOL News

time17 hours ago

  • IOL News

Urgent need for private sector investment in South Africa's transport infrastructure

Transport Minister Barbara Creecy says Transnet will issue Requests for Proposals from the end of August 2025. Image: Ayanda Ndamane / Independent Newspapers Transport Minister Barbara Creecy on Wednesday said the limited availability of state resources to fund infrastructure development made private sector investment critical. Delivering her budget speech in the National Assembly, Creecy said they have just concluded a Request for Information process to guide the private sector investment in five priority rail and port corridors. 'Transnet will issue Requests for Proposals from the end of August 2025, and so begin the formal procurement process,' she said. Creecy also said they have to enhance the involvement of additional operators as a way of extending freight logistics capabilities of the country and region, beyond what the public sector alone would have been able to accomplish. 'It is important to point out that as an economy, we need freight logistics operators that can compete, but that can also complement each other when the need arises, for the benefit of our country and region.' Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Ad loading The minister explained that the Cabinet approved a Private Sector Participation (PSP) framework in 2023 to guide private sector involvement across the logistics sector value chain. 'The department has concluded a Memorandum of Agreement with the Development Bank of Southern Africa (DBSA) and the National Treasury, appointing DBSA as the hosting institution for the unit. We have established the Interim Rail Economic Regulatory Capacity to create fairness and transparency for third-party operators, improve network utilisation, increase competition, and reduce costs.' She also said the open access to the rail network will allow train operating companies to increase the volume of goods transported by rail, while the network infrastructure remains state-owned. 'As part of the rail reform programme, we have also created the new Transnet Rail Infrastructure Manager to have a dedicated focus on the management of the rail infrastructure. The Transnet Freight Rail operating company would now focus on the transportation of rail commodities through its rolling stock.' She added that they cannot afford to wait until the PSPs reach financial close before launching an ambitious programme to rehabilitate Transnet's rail network and rolling stock, as well as port infrastructure and equipment. DA MP Thamsanqa Mabena said Transnet must accelerate the process to issue rail concessions on the five priority lines. 'We believe the participation of the private sector will assist with injecting much-needed capital and expertise to provide relief to the constrained fiscus,' Mabena said. Creecy told the MPs that the Passenger Rail Agency of South Africa (Prasa) had, by the end of May 2025, successfully revived 35 out of 40 corridors and sections of service lines. 'We continue to deliver at pace with Prasa achieving an unaudited figure of 77 million passenger journeys for the last financial year and 116 million passenger journeys for the 2025/2026 financial year. Our competitive pricing model for commuter passengers will ensure that working-class communities take advantage of our offerings.' Prasa has been allocated R66.1 billion over the medium term. 'This significant budget is for maintaining, recovering, and renewing rail infrastructure, rebuilding the signaling system, rolling out new train sets to priority corridors, and increasing rail passenger trips.' Creecy also said the Airports Company of South Africa has been allocated R21.7 billion for infrastructure development. 'This will improve facilities for passenger safety and comfort, over the medium term, and build a new freight terminal at OR Tambo International Airport. In addition, we are fast-tracking projects to ensure reliable availability of jet fuel to all airlines at all our airports, as well as the general upkeep and upgrading of the facilities and technologies at each of our airports to improve both the security of passengers and cargo, as well as the convenience of airport users.' The minister further said the South African Airways (SAA) was pursuing a bold route expansion strategy to strengthen its regional and global footprint with new regional routes from Johannesburg and Cape Town. She said the airline has begun a measured fleet expansion to meet growing demand. Creecy also said the national carrier was self-funding its operations and fleet growth, while remaining open to a strategic equity partner as part of its long-term restructuring. 'With unencumbered assets and renewed profitability, SAA is well-positioned to drive economic value through expanded international services, job creation, and increased contributions to tourism and trade.'