NJHP repair to take two more years
Restoration work at the Neelum-Jhelum Hydropower Project (NJHPC) would take two more years to complete, Water Resources Minister Muhammad Moeen told the National Assembly on Friday, as a committee investigating the issues
was expected to finalise its report soon.
Speaking during the Question Hour, the minister said that the main contract for carrying out the repair work on the project - which was shut in May 2024 - had not yet been awarded in accordance with the government's instructions.
So far, Rs6.6 billion was spent to repair the project's Tail Race Tunnel (TRT). After the TRT was fixed, the plant resumed full operations in March 2024, generating 969 megawatts of electricity. However, the plant had to be shut down again two months later due to issues in Head Race Tunnel (HRT)," he said.
He said that the project is currently working under a provisional tariff on a 'take-and-pay' basis. There are no fixed payments or returns on investment. The company is managing its expenses through its own resources and pending payments from power sales to the Central Power Purchasing Agency (CPPA-G)."
According to the National Power Control Centre (NPCC), the minister stated, the country has enough power generation to meet demand, and no load-shedding is being done due to shortages. He added that local electricity supply had not been affected by the shutdown.
The minister informed the house that the project's consultants had been told to review and improve maintenance procedures to avoid such issues in the future. He stressed the importance of operating and maintaining the plant as per equipment manufacturer's guidelines to prevent unexpected closures.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Business Recorder
a day ago
- Business Recorder
Payments to Chinese IPPs: PQEPC seeks help of Aurangzeb
ISLAMABAD: Port Qasim Electric Power Company Private Limited (PQEPC) has formally approached Finance Minister Senator Muhammad Aurangzeb, seeking urgent release of funds to the Central Power Purchasing Agency–Guaranteed (CPPA-G) for onward payment to Chinese Independent Power Producers (IPPs). Currently, the outstanding dues owed to Chinese IPPs stand at approximately Rs 480 billion. A portion of this amount is expected to be paid before Prime Minister Shehbaz Sharif's upcoming visit to Beijing, as a gesture to reassure Chinese stakeholders. In a letter to the finance minister, PQEPC's Chief Executive Officer, Wang Dongfang, emphasised that the 1,320 MW Port Qasim Coal-Fired Power Project—developed under the China-Pakistan Economic Corridor (CPEC)—has consistently supplied clean, reliable, and cost-effective electricity to the national grid, even during the COVID-19 pandemic. Chinese IPPs face Rs500bn in unpaid dues He noted the project's active contribution toward mitigating circular debt. According to Wang, the total outstanding dues for the Port Qasim project have reached Rs 87.5 billion (approximately $308.2 million) as of June 30, 2025. These payments have been delayed by over six months and risk further escalation. The CEO warned that the shareholders and sponsors from China and Qatar have expressed deep dissatisfaction over the growing payment backlog, and have urged the government of Pakistan to take immediate action to reduce the outstanding amount. He also pointed out that the current situation legally entitles PQEPC to suspend operations under Section 9.10 of the Power Purchase Agreement (PPA), without incurring any liquidated damages. Wang emphasised that the project enjoys a comparative advantage in Energy Purchase Price (EPP) tariffs when compared to oil- and RLNG-based power plants. A suspension of operations, he cautioned, would be a 'lose-lose' scenario for both parties and must be avoided through timely payments. He further warned that failure to settle dues could result in a breach of the Loan Agreement and default under the Government of Pakistan's Sovereign Guarantee, jeopardizing the country's financial credibility and investor confidence. Given the critical nature of the situation, Wang has requested the finance minister's intervention and coordination with relevant authorities to expedite financial support to CPPA-G, enabling it to clear outstanding dues to the Port Qasim project at the earliest. The Finance Ministry typically releases Rs 5 billion per month to CPPA-G through an escrow account, set up in coordination with Chinese authorities, for the payment of energy costs to Chinese IPPs. Copyright Business Recorder, 2025


Business Recorder
5 days ago
- Business Recorder
EPQL seeks PD's support for early gas supply from Badar field
ISLAMABAD: The Engro Powergen Qadirpur Limited (EPQL) has approached the Power Division for support in expediting the signing of a Supplementary Agreement (SA) to utilise low-BTU indigenous gas from the Badar-1 gas field. In a letter to the Power Division, EPQL CEO Adeel Qamar stated that the company operates a 225-MW power plant running primarily on permeate gas from the Qadirpur gas field under a Power Purchase Agreement (PPA) signed with the Central Power Purchasing Agency Guarantee Limited (CPPA-G) on October 26, 2007. Since the commencement of commercial operations in March 2010, the plant has maintained a high position in the Economic Merit Order (EMO) and supplied 18.9 billion units of electricity to the national grid with high gas-based utilisation. Engro Powergen plant: PD and CPPA-G at odds over gas pricing mechanism The EPQL claims that its operations have delivered substantial benefits to electricity consumers and the Government of Pakistan, including: (i) Rs 89 billion in savings through procurement of low-cost electricity;(ii) $1.6 billion in foreign exchange savings by using indigenous gas; and (iii) Rs 96 billion in revenue for fuel suppliers (SNGPL and OGDCL) from the sale of permeate gas that was previously being flared. 'These benefits were only possible due to the extensive cooperation and support from the Government of Pakistan and its departments, including PPIB, CPPA-G, and NTDC,' said Qamar. To address the declining gas supply from Qadirpur and to enhance the plant's utilization, EPQL, in collaboration with stakeholders such as PPIB and CPPA-G, explored alternative fuel sources. As a result, NEPRA, in its determination dated February 20, 2024, approved the use of low-BTU gas from the Badar-1 field as an additional fuel source for the EPQL's operations. Following NEPRA's approval, the EPQL entered into an agreement with Petroleum Exploration Limited (PEL) on August 5, 2024, for the supply of 8–13 mmscfd of low-BTU gas from Badar-1. Subsequently, the EPQL submitted a draft Supplementary Agreement to the PPA for CPPA-G's review on August 26, 2024, after detailed consultations. However, the company says the matter remains unresolved. 'We note with deep concern that, despite a lapse of 10 months, the matter is still pending with CPPA-G, delaying the opportunity for EPQL to generate additional electricity using low-BTU gas from Badar-1,' Qamar stated. EPQL says the infrastructure for gas supply from Badar-1 is fully operational, and off-take can begin immediately upon receiving the necessary approvals. The transaction is structured on a Take-and-Pay basis, meaning gas will only be used if it qualifies under the Economic Dispatch Merit Order. The company estimates that had the approval been granted by October 2024, it could have generated an additional 122 million units of electricity, resulting in:Rs 787 million in potential savings for power consumers, and$9 million in foreign exchange savings. 'We have consistently followed up with CPPA-G and responded promptly to all queries, but the approval remains pending. Given that we are currently in the peak summer season and relying on high-cost imported fuels for electricity generation, it is imperative to finalize the Supplementary Agreement without further delay,' Qamar added. The EPQL has urged the Power Division to facilitate the earliest possible approval to unlock the economic and operational benefits associated with the project. Copyright Business Recorder, 2025


Express Tribune
6 days ago
- Express Tribune
NA panel okays Civil Servants Act tweaks
PML-N-led coalition government in the Centre now has 229 members in the NA. PHOTO: APP The National Assembly's Standing Committee on Cabinet Secretariat on Thursday approved the Civil Servants (Amendment) Bill 2024 with a majority vote. The bill proposes several provisions, including mandatory asset declaration for government employees, expediting the right-sizing process, and abolition of redundant departments. As per the amendment bill, all government employees will be required to declare their assets. The federal government is empowered to abolish or merge departments that are either dormant or have become a financial burden. The bill also proposed that redundant employees be retrenched after offering them a financial package instead of placing them in a surplus pool. The PBS1-5 jobs will be outsourced to the private sector to reduce pension bills. The bill also recommends age relaxation for recruitment of civil servants. Young officers may be given up to 10 years of age relaxation for new appointments. Various members expressed concerns regarding the proposed amendments during the meeting. PML-N leader Tahira Aurangzeb argued that laying off employees from grades 1 to 5 would lead to an increase in crime.