Report into Leinster House bike shed found OPW failed to carry out 'value-for-money' assessment
A new report outlines the OPW did not conduct a value-for-money assessment for the bike shelter project in advance of the work taking place.
External auditors Deloitte found the Houses of the Oireachtas Commission, which oversees Leinster House, was not informed of the potential cost of the project ahead of construction beginning.
Deloitte found in April 2023, the OPW estimated the bike shelter project would cost €350,000, but these costs were never provided to the commission.
While it states some standard practices were followed by the OPW in the project, others were not.
The audit reads: 'Our internal audit review has identified the absence of some fundamental good practices in how certain elective capital works (including the bike shelter) below the €500K threshold are being initiated, approved, managed, and delivered.
The most fundamental of these control gaps is the absence of a value-for-money assessment which would have allowed informed OPW personnel to evaluate the cost-benefit of building a covered bicycle shelter in the requested location within the Leinster House campus.
'Where there is a lack of oversight of projects, there is a risk that these projects may not represent value for money or may not deliver to exact requirements in an efficient and effective manner.'
While the OPW was primarily focused on delivering the project, pricing options for the bike shelter should have been documented in a value-for-money assessment as part of a 'robust options appraisal process', the audit said.
The report also found the high cost of the shelter was due to the alignment of the project with 'the fabric of existing structures'.
However, it states regardless of the reasons, a value-for-money assessment should have been carried out, alongside other lower-cost alternatives.
These alternatives should have included the option of doing nothing, which was not presented to the Houses of the Oireachtas Commission, as required by the Public Spending Code.
'Approval to proceed with the project should only have been formalised when these evaluations were complete,' the audit report reads.
The report also found there was some paperwork related to the bike shelter that was 'not signed or dated by the individual completing the form'.
Among the recommendations from Deloitte include the overhaul of project management rules for any OPW project that costs less than €500,000, including the need for value-for-money assessments.
In particular, this includes the establishment of a mechanism to 'oversee and review elective capital projects with an estimated budget of below €500K'.
These mechanisms should include value-for-money assessments, project option appraisals, and expenditure monitoring.
Deloitte has also recommended all cost estimates should be 'communicated to all relevant parties before elective projects are approved'.
It also adds the option of doing nothing must be presented to stakeholders in advance of approval.
In its response to the audit, the OPW has opted to accept all recommendations from Deloitte for future projects with the Houses of Oireachtas Commission and others.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Irish Examiner
7 hours ago
- Irish Examiner
Insolvencies steady but companies face 'significant headwinds' for rest of the year
Company insolvencies have declined slightly so far this year, but given the significant international trade tensions, businesses are facing 'significant headwinds to consider for the rest of the year'. According to Deloitte, so far this year there have been 407 insolvencies — down by 1% compared to the same period in 2024 — with the majority of these being seen in the services and hospitality sectors. There have been 173 insolvencies in the broad services sector, while there have been 66 in the hospitality sector. While the hospitality sector saw a 14% drop in insolvencies year-on-year, Deloitte said the sector continued to face a high level of insolvencies. The firm said hospitality had the highest number of insolvencies of any industry in this country when services are split into subsectors. 'Restaurants are disproportionately impacted within this sector, due to legacy debt issues, difficulty attracting and retaining staff, and energy in Ireland being the most expensive in Europe,' Deloitte said. Deloitte Ireland turnaround and restructuring partner James Anderson said while insolvency rates were 'broadly in line with 2024', given the 'ongoing geopolitical and trade tension, there are significant headwinds to consider for the rest of the year'. According to Mr Anderson, company-led closures are down so far this year, while company-led restructuring has increased. There were 14 Small Company Administrative Rescue Processes (Scarp) during the first half of this year — up from seven during the same period in 2024. The Scarp scheme was introduced in late 2021 to help small and micro firms which are still viable, yet insolvent, restructure their debts and avoid liquidation. However, uptake of the scheme remains low. 'Scarp has proven to be a successful process that saves companies and jobs. It is disappointing that awareness remains low despite a success rate of over 70%. It is crucial that an awareness campaign is invested in, so more people are aware of it,' Mr Anderson said. There have been 99 Scarp appointments since its introduction, which represents just 4% of all insolvencies in that time period. However, creditor-led enforcement activity has increased significantly across both court-appointed liquidations and corporate receiverships. 'Court-appointed liquidation activity arising from unresolved debts are up by 121%, with Revenue petitioning in 64% of these appointments,' he said. Deloitte said the rise in court liquidations could be attributed to companies being unable to meet phased payment agreements with Revenue as part of the covid debt warehousing programme. 'Corporate receiverships have increased by 37%, with significant activity by alternative lenders enforcing on real estate-backed loans which have defaulted or matured without resolution.' Read More Bar and pub sales drop 7% despite wider retail sales rise


Extra.ie
6 days ago
- Extra.ie
€2 a week? – ‘Sweetheart' rent deals set to face probe
Pressure is growing on the Office of Public Works to fully explain why it lets out State-owned properties to retired civil servants, with two Oireachtas committees now set to investigate the issue. last weekend exclusively revealed that current civil servants are living effectively rent-free under a sweetheart deal in secret 'ghost houses' in the Phoenix Park. Today's top videos STORY CONTINUES BELOW There are six residential properties in the Phoenix Park that are managed by the OPW but do not exist on any publicly available official asset register. There are six residential properties in the Phoenix Park that are managed by the OPW but do not exist on any publicly available official asset register. Pic: Google Maps The OPW has refused to confirm what rents the current and former State employees are paying, but overall figures released in 2021 suggest the average rent could be as low as €135 a month. The Department of Agriculture was previously found to be charging €2 a week in rent to a former employee who was living in a cottage owned by the State. A team from the Comptroller and Auditor General discovered the Georgian farmhouse known as 'Stacumny Cottage' during a visit to Backweston in Kildare, where the Department of Agriculture have facilities. The Department of Agriculture was previously found to be charging €2 a week in rent to a former employee who was living in a cottage owned by the State. Pic: File It found the cottage was not recorded on the department's or the OPW's asset register. Aidan Farrelly, a Social Democrats TD who sits on the Public Accounts Committee (PAC), confirmed that he had written to the chair of the committee seeking answers on the matter. Mr Farrelly said: 'It would be my hope that we write to the OPW with a series of questions about these properties.' Public Expenditure Minister Jack Chambers. Pic: Fran Veale The Public Expenditure Minister, Jack Chambers, yesterday also confirmed that Kevin 'Boxer' Moran would appear before the Finance Committee next week on the matter. Mr Chambers is now the third Government figure this week to have no update on the matter. Taoiseach Micheál Martin this week said he was 'unaware' of the reports when he was questioned on the matter by Micheál Martin. Pic: Simon Wohlfahrt/Bloomberg via Getty Images Housing Minister James Browne was asked about the properties yesterday morning but said he had only just become aware of the story. Parliamentary questions in 2017 indicate that Mr Moran is aware of the issue, as he previously served as a minister for state. He said: 'My officials have advised that there are occasions where the properties remain occupied by retired staff and widowed spouses on compassionate grounds. 'Decisions in relation to extended occupancy are made on a case-by-case basis. Duration of occupancy varies from a minimum of three years to life.'


Irish Independent
6 days ago
- Irish Independent
Fields at foot of Rock of Cashel to be transformed into new town park
Phase one of construction is due to begin by the latter end of the summer, which will see a contractor fully on site, and works are expected to take several months. The Cashel Town Park will feature gravel walkway, a scenic boardwalk, reinforced grass paths, natural play elements, sensitive landscaping, seating and signage, a low level maze and an amphitheatre. At the sod turning were elected members of Tipperary-Cahir-Cashel municipal district, Bru Ború, Cashel Heritage and Development Trust, local gardaí, the OPW, chief executive of Tipperary County Council Sinéad Carr, directors of services Brian Beck and Dave Carroll, district officials, project manager and engineer Frank Cussen, while Muintir Na Tire was represented by National President, Jackie Meally. Cashel resident Cllr Burgess told the Irish Independent that the new park is a transformative project for the heritage town and one that has been on his agenda for the past few years ever since he was elected to the council. 'I was delighted back in 2020 in proposing the Part 8 process planning permission to drive this project forward. Last year, we secured €495,000 in additional funding under the Town and Village Renewal Scheme to support this important work. 'We are going to deliver a low-level maze for recreation for kids to play in. We are going to have some organic play material, a new boardwalk improving accessibility in the site. 'But today, in marking the turning of the sod, acknowledges the journey we've been on as a local authority in securing the lands, in driving the new enhancement of the Bishop's Walk, the Bóthar na Marbh, and the Town Wall Walkway at the back of the courthouse. 'All three elements have been delivered already. This main starting point is going to be enjoyed by not just locals, but also visitors. Being under the shadow of the Rock, where hundreds of thousands of visitors are attending every year – the town has always missed that bridge, that connectivity between the Rock and the town centre.' Cllr Burgess said the enhanced town park will act as that bridge. 'It's going to be really transformative for outdoor space in the town. This is a really exciting journey that we're on and I'm delighted as cathaoirleach to be officially turning the sod today.' Cllr Burgess thanked all the council officials who worked on the project over the years, procuring the design, securing planning permission and authorisations from many agencies such as the National Monument Service, the OPW, and the Department of Heritage. ADVERTISEMENT Learn more 'It's quite a sensitive site,' said Cllr Burgess. 'I think that brings a unique aspect to our Town Park that no other town park has. This is going to be something exceptional and it's going to have that outdoor amenity that the town has missed for many years.' The new boardwalk will take some time to install, said Cllr Burgess. 'That accessibility element of the Town Park is really important.' There were many in Cashel who felt the Town Park would never get started, but it is, and when people see the end result, people will appreciate the outdoor space to bring their children, walk their dogs, and enjoy picnics, said Cllr Burgess. The entire project will deliver a new entrance to the Rock of Cashel site on the Camus Road side, at the existing gate. There will be new walkways, and a new amphitheatre which will be of huge benefit to the community. 'I can see the brass band practising there,' said Cllr Burgess. 'I can see Cashel Arts Festival utilising the space in the future, maybe some Irish dancing. It's going to be space for shows and that space for really notable experiences.' Phase one should be completed before Christmas, and, depending on funding, it's hoped that this time next, work will have moved on to phase two. Both phases will be opened separately. The three elements of Bóthar na Marbh, the Bishop's Walk, and the Town Wall Walkway are the three components of the project, with phase one leading from the top gate leading into the Bishop's Walk, down towards the Palace. 'That's going to be delivered in the coming months. That will be open to the public, and that side of the development is really geared towards families. It will be a really welcome addition to the town. 'The design concept respects the sensitivities of the site. It respects the heritage of our town and also provides that unique offering to visitors and locals so I'm really looking forward to it,' added Cllr Burgess.