Regional body's bungled handling of contract will cost the taxpayer £5.25m

Regional body's bungled handling of contract will cost the taxpayer £5.25m

Wales Online05-06-2025
Regional body's bungled handling of contract will cost the taxpayer £5.25m
An independent investigation has been launched how the Cardiff Capital Region handed the process
Aberthaw Power Station
(Image: John Myers )
Taxpayers will have to pay £5.25m bill after a regional body responsible for handling the Cardiff City Deal bungled the awarding of a demolition contract for Aberthaw power station.
The Cardiff Capital Region, a public body which was set up to invest more than £500m in the south Wales as part of the 2016 City Deal, was taken to court over how it awarded a demolition contract for Aberthaw power station, the disused power station it controversially bought from energy giant RWE.

The body, which represents 10 councils, lost a high-court legal challenge brought by a losing bidder, Brown and Mason Group, which concluded in February.

The former coal-powered station was acquired for £8m by the city region in 2022, with contractors Erith beginning demolition work last year. For our free daily briefing on the biggest issues facing the nation, sign up to the Wales Matters newsletter here
Today, the region's chair Mary Ann Brocklesby gave an update to the Senedd, telling the economy committee that a settlement of £5.25m had been agreed. Brown and Mason had previously said they were seeking £10m.
"I'm not able to say much more at this point because we are undergoing an independent review which we commissioned as political leaders to set in train precisely at the point that we knew we were going through a legal process," she said.
Article continues below
Cllr Brocklesby said: "We had to wait until that legal process was over before that independent review could start. "We are awaiting the findings which – subject to legal caveats – we will be making public."
Kellie Beirne, chief executive of the south-east Wales c orporate joint committee and Cardiff Capital Region, said: "We're taking this extremely seriously, we recognise the gravity of it and again yes, [it's] something that we don't come and report.
"Apologies again for the short notice but we had clearance, we briefed our internal stakeholders and we felt it important to be as transparent as we possibly could by conveying that this morning at this committee."

She said a full independent review has been ordered. "When that review concludes and we have findings, we'll be able to be much more open about what happened and take steps to ensure that this can't happen again," she said.
Asked whether the court case has impinged on work at the 500-acre site, Cllr Brocklesby insisted: "No, it continues at pace."
Conservative MS Andrew RT Davies said: "When you came before this committee in September 2023, Kellie you said that £40m is but a drop in the ocean.

"I think the words you used were hundreds of millions of pounds will be required. Obviously, this court case has not helped instil confidence in the private sector in coming on board as partners… so, how are you progressing in that goal?"
Cllr Brocklesby replied: "Let's look at the wider ecosystem of CCR: one of the absolute strengths of it is that we have people across the region who are highly valued within their own sectors… who are highly respected not just in Wales but globally."
"In terms of the future of Aberthaw, it does actually look very bright and we're not feeling any effects from the impacts of this highly regrettable procurement issue."
Article continues below
Ms Beirne said Cardiff Capital Region does not have deep enough pockets for what Aberthawr requires following the initial demolition and remediation phase.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Major update on new £18m train station near Glasgow
Major update on new £18m train station near Glasgow

Scottish Sun

time3 days ago

  • Scottish Sun

Major update on new £18m train station near Glasgow

The new stop will be a great addition for residents and for visitors to the area FULL STEAM AHEAD Major update on new £18m train station near Glasgow Click to share on X/Twitter (Opens in new window) Click to share on Facebook (Opens in new window) WORK has officially started on a brand new £18.3 million train station. The new rail link at Balgray will serve Barrhead, on the south-west edge of Glasgow, and its growing communities. Sign up for Scottish Sun newsletter Sign up 1 The new station near Barrhead will be on the line from Glasgow Central It will make it easier for people to travel to and from the city for work, education and leisure, while also improving access to local destinations and attractions. Once complete, the station will feature two platforms connected by a footbridge with lifts, along with waiting shelters, ticket machines and secure cycle storage. Margaret Gibb, commercial director at Network Rail Scotland, said: 'Breaking ground at Balgray is a major step forward in improving transport for the Barrhead area. 'The new station will make it easier for people to travel to and from Glasgow, and for locals and visitors to connect with places like Dams to Darnley Country Park. 'It's exciting to see work begin on a project that also supports active travel, encouraging more walking and cycling too. 'We're proud to be part of a partnership delivering real change and long-term benefits for people in Barrhead and the surrounding area.' An 80-space car park at the station will include electric vehicle charging points, with new walkways linking the platforms directly to nearby housing developments and reservoir paths. A new bus turning circle and stop have already been delivered on Springfield Road by East Renfrewshire Council (ERC). The Balgray Station project, which is part of the wider Glasgow City Region City Deal, is being delivered by Network Rail in partnership with ERC, Transport Scotland, ScotRail and Story Contracting. Preparatory work and planning for the station began in October 2023, with the final proposal approved by the Glasgow City Region City Deal panel in September 2024. Laughing gas 'epidemic' sweeping party island with tourists left foaming at mouth, having seizures & permanently scarred Construction will continue into next year, with the station expected to open to passengers in Autumn 2026. Councillor Owen O'Donnell, leader of East Renfrewshire Council, said: 'I'm delighted to see work start on the new Balgray station which will greatly improve transport links between Barrhead and other parts of East Renfrewshire with stations on the Neilston line - Williamwood, Whitecraigs and Patterton. 'Like many of our communities, Barrhead is growing, and this new station will also provide another route from the town into Glasgow. 'We're proud to be working with our partners on delivering this new station which is one of our biggest City Deal projects.'

Stockton MP criticises approval of Byers Gill solar farm
Stockton MP criticises approval of Byers Gill solar farm

BBC News

time3 days ago

  • BBC News

Stockton MP criticises approval of Byers Gill solar farm

An MP says he is "disappointed and angry" over a government decision to approve a large, £200m solar Matt Vickers, who represents Stockton West, has warned the Byers Gill Solar Farm near Darlington and Stockton will harm the local landscape."It will damage our rich tapestry of wildlife and biodiversity and could have a huge impact on our village communities and food security," Vickers government said it would reduce bills and provide energy security, while developer RWE said the facility would be removed at the end of its estimated 40-year lifespan. Vickers previously spoke against the solar farm during a House of Commons debate in 2024, as large swathes of nearby greenbelt land have been obtained by developers for solar to the Local Democracy Reporting Service, the 180MW farm would be made up of several blocks of development located in Brafferton, Hauxley Farm, Byers Gill Wood, Great Stainton and two near said the development will cover about 490 hectares (1,211 acres) of land in total. Speaking after the government's decision to approved the plans, Vickers said: "Labour is so obsessed with net-zero and solar farms that they're happy to bulldoze through the views of local residents to push ahead with it."He claimed Labour "couldn't give a damn about the views of local people".But the energy consumers minister Miatta Fahnbulleh said: "Families in the North East have seen their energy bills go through the roof as a result of our exposure to volatile gas prices. "The only way to make British people better off in the long term is by securing clean, homegrown power that we control." Follow BBC Tees on X, Facebook, Nextdoor and Instagram.

Miliband's net zero crusade won't end until we are all poorer
Miliband's net zero crusade won't end until we are all poorer

Telegraph

time3 days ago

  • Telegraph

Miliband's net zero crusade won't end until we are all poorer

When it comes to the real cost of renewables, the cat is well and truly out the bag. Ed Miliband can carp on all he likes about how his precious net zero revolution is going to magically lead us down the merry path to cheaper energy bills, but he can't change facts – and his green dreams continue to collide with reality in the most damning fashion. The latest blow to his clean energy fantasy comes once again in the form of wildly unaffordable offshore wind power after Miliband unveiled the prices the Government is willing to pay for yet more offshore wind farms to be built in UK waters. When Claire Coutinho, the shadow energy secretary, describes them as 'eye-watering', she isn't exaggerating. International developers are being wooed with a maximum guaranteed price of up to £113 per megawatt hour (MWh) for the power they generate from the farms – far above the wholesale price of power, which last year averaged about £72. The price has been confirmed ahead of the latest round of subsidy awards for developers. You might think Miliband had learnt from past debacles, such as 2023's auction, which was such a catastrophic failure that there wasn't a single bid despite seven contracts to build new farms being put forward. True, it was late 2023 when Labour was in opposition, but still. That was such a shambles it was obvious that the economics of offshore wind were evaporating faster than it takes a giant spinning metal blade to turn a passing gull into mincemeat and feathers. The guaranteed prices on offer were so low that Tom Glover, chairman of energy company RWE's UK arm, warned that no more offshore wind farms would be built unless the Government increased the guaranteed long-term prices by as much as 70pc. By Glover's calculations that would have meant promising developers between £65 and £75 per MWh for the power generated from wind farms, as opposed to the £44 that was actually on the table. And yet look where we are today, less than two years later. The strike price for offshore wind in the subsequent round actually turned out to be even higher than Glover's demands, at £82. Now Miliband is willing to pay up to £113 in the upcoming round, a 38pc leap from that and a whopping 57pc more than the wholesale price of electricity last year. He has clearly allowed the disastrous cancellation of several major wind projects to spook him into being even more generous this time around. The biggest of these was the vast Hornsea 4 wind farm, which was abandoned earlier this year. The reason? Because it would never be profitable, Danish developer Ørsted said a mere nine months after it was awarded the contract. It was even willing to fork out €500m (£423m) in 'break-away' costs to relinquish itself from the burden.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store