Klein Boesmans River Bridge construction in KwaZulu-Natal: R29 million spent, yet incomplete

Klein Boesmans River Bridge construction in KwaZulu-Natal: R29 million spent, yet incomplete

IOL News30-05-2025
The construction of the Klein Boesmans River Bridge in Wembezi, KwaZulu-Natal, is incomplete despite R29 million being spent on the project by contractors. The project was supposed to be completed in May 2021.
Image: Riona Gokool / Supplied
The construction of the Klein Boesmans River Bridge in Wembezi, KwaZulu-Natal, is incomplete despite R29 million being spent on the project by contractors.
The KZN Legislature Transport Portfolio Committee conducted an inspection of the site on Wednesday to find the construction area deserted. The project began in 2020 and was scheduled for completion in May 2021.
The committee said that to date, only 65% of the project is completed.
Mncedisi Maphisa, the portfolio committee chairperson, said that according to the contractual agreement, the construction period to complete the job would be 15 months.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Next
Stay
Close ✕
Ad Loading
Maphisa said the site had since been deserted and there is no progress, which triggered the committee to visit the bridge in a mission to find answers from the provincial Transport Department, municipality, and contractors.
'The committee holds a firm view that these delays are unwarranted and result in unnecessary slow-pacing of service delivery. The first meeting was held at Department of Transport Cost Centre in Estcourt and the delegation then proceeded to Wembezi for physical assessment of the bridge, to be furnished with reasons as to why this project has taken this long to finish, and also to ascertain what the department has in store to ensure that this project is completed,' Maphisa said.
The KZN Legislature Transport Portfolio Committee conducted an inspection of the site on Wednesday.
Image: KZN Legislature
Riona Gokool, MPL and Democratic Alliance KZN spokesperson on Transport, said there must be full accountability, and that the DA stood with the affected communities to demand that public money be used to serve the public interest, not the pockets of failing contractors and indifferent officials.
'The residents of Zwelisha and surrounding areas deserve proper service delivery. They do not deserve to watch as tens of millions of rand are poured into a pit of incompetence and neglect,' Gokool said.
She added that this was gross mismanagement, a lack of oversight, and accountability from officials.
'The delays and abandonment have left residents stranded without a critical transport link, cutting off access to schools, health care, and economic opportunities,' she said.
Gokool said the department's internal report reads like a case study in failure.
'A contractor plagued by cash flow issues, construction delays exacerbated by avoidable mistakes, and an apparent breakdown in contract management and supervision. Excuses such as Covid-19 and weather conditions do not justify years of stagnation, nor do they absolve the department from failing to take decisive action sooner,' Gokool said.
Recently, the committee inspected the uMdloti River Bridge project in the Ndwedwe area, revealing staggering levels of mismanagement, incompetence, and neglect of a critical infrastructure project, said Gokool.
The committee found that despite construction having been under way for over eight years, only 44% of the work was complete as of April 2025
Construction of the uMdloti bridge has now dragged on since 2016, yet to date, it remains incomplete.
zainul.dawood@inl.co.za
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

MAJOR steps taken towards South Africa's first bullet train
MAJOR steps taken towards South Africa's first bullet train

The South African

time11 hours ago

  • The South African

MAJOR steps taken towards South Africa's first bullet train

South Africa's first bullet train means you'll be able to travel a 500 km loop from Limpopo to Gauteng in the blink of an eye. Better still, major steps towards its highly anticipated 2030 completion are being made. The Limpopo-Gauteng Speed Train Project was first announced in 2023 and is now entering feasibility and environmental impact assessment. As such, these studies will determine whether the project is safe, environmentally sound and economically viable. The launch of South Africa's first bullet train is being led by both national and provincial government, along with a consortium of private and foreign investors. The Department of Transport says one key challenge it has identified is land acquisition along the planned 500 km route. Therefore, successful negotiations with communities and landowners in Limpopo and Gauteng must still take place before South Africa's first bullet train comes to life. However, if all goes to plan, construction is expected to begin next year, in late 2026, reports BusinessTech . Talk of High-Speed Rail was first raised in South Africa back in 2010. Will it finally come to fruition two decades' later? Image: File According to reports, South Africa's first bullet train will significantly reduce travel time along the route. Currently, a six-hour journey by car from Pretoria to Polokwane would take just 90 minutes on South Africa's first bullet train. And that will include multiple stops in the likes of, Hammanskraal, Bela-Bela, Mokopane, Louis Trichardt, and Musina. Using a phased approach, the train is expected to exceed 200 km/h on specific segments of the route. And then travel at a slower speed between frequent stops, attaining an average speed of approximately 175 km/h between Pretoria and Polokwane. While South Africa's first bullet train won't match the speeds of others globally, it still technically qualifies as one: TRAIN COUNTRY YEAR TOP SPEED Maglev China 2003 311 km/h CRH380A China 2010 302 km/h Transrapid Germany 2008 279 km/h Shinkansen Japan 1964 275 km/h TGV France 1992 236 km/h Japan's impressive Skinkansen, which has been in operation since 1964, is actually a fleet of high-speed trains. Image: File Furthermore, Gauteng government has already committed R120 billion towards expanding its rail network over the next five years. Not only does this include South Africa's first bullet train, but also six new areas in Gautrain's revived rail network. It also says it hopes to see PRASA's commuter network reach 600-million passenger journeys annually by 2030. However, cost estimates for South Africa's first bullet train are high. This single line alone is said to cost in the region of R530 billion. Quite rightly, this is raising serious questions about funding and long-term feasibility. It will also not be the only one on the African continent. Morocco received a high-speed TGV back in 2018. Let us know by leaving a comment below, or send a WhatsApp to 060 011 021 1. Subscribe to The South African website's newsletters and follow us on WhatsApp, Facebook, X and Bluesky for the latest news.

BAD news for motorists with expired drivers' licences in SA
BAD news for motorists with expired drivers' licences in SA

The South African

time3 days ago

  • The South African

BAD news for motorists with expired drivers' licences in SA

Any South African motorists with expired drivers' licences are in for a longer-than-expected wait. Last week, it was revealed that the Department of Transport (DOT) filed papers with the Pretoria High Court to re-run its botched licence printing tender. The South African has been keeping track of the licence printing debacle that's several years behind schedule. However, the Organisation Undoing Tax Abuse (OUTA), has now revealed that papers have been filed to overturn the existing R886-million contract. This means we are no further along to resolving the issue of expired drivers' licences than we were years ago. Transport Minister Barbara Creecy has been under attack for her handling of the backlog debacle. Even though the irregularities took place before she was in office. Image: File In fact, so desperate is the DOT that it asked the Department of Home Affairs (DHA) to help print expired drivers' licences. However, even this hasn't gone smoothly, because the output needs to be approved the State Security Agency (SSA) before going ahead. The minister. had hoped for a three-month turnaround, but even this stop-gap solution looks unlikely. Meanwhile, it's estimated that the current backlog of expired drivers' licences now exceeds 600 000, reports TopAuto . Likewise, papers filed by the department in the High Court request a complete re-run of the tender process, which was originally awarded to French firm, Idemia. SA motorists will be given six months' grace if found driving without a valid driver's licence. However, you must be able to produce proof of renewal. Image: File Moreover, the sustainability of the DOT's ambitious new licence system is now in doubt. The department wanted fully digital, connected Driver's Licence Card Accounts (DLCA), but irregularities in the original tender procurement process could put pay to that elaborate idea, in favour of something more cost effective. The Audit General of SA's report found that Idemia had, 'failed to meet key bid technical requirements.' Primarily when it came to inadequate budget analysis and inconsistent application scoring. As a result, a backlog of expired drivers' licences continues to grow as the current, outdated printing machine suffers from frequent breakdowns. South Africa's aged card printing machine should have been replaced more than a decade ago. Image: File Furthermore, papers filed by the department outline other flaws in the tender application process. Including a R400-million cost escalation from the Cabinet-approved budget of R486 million, resulting in a total of R886 million. Even at this elevated cost, the successful tender used outdated pricing and omitted basic printing material costs, which would have increased taxpayer expense further still. It is unclear whether Idemia will oppose the DOT's court challenge. Meanwhile, anyone who awaiting expired drivers' licences is exempt from fines for six months. However, they must be able to show a renewal receipt as proof. At the start of July 2025, the number of expired drivers' licences waiting in the system were 602 831. 192 856 of which were destined for Gauteng, 86 862 for the Western Cape and 85 313 in backlog for KwaZulu-Natal. Let us know by leaving a comment below, or send a WhatsApp to 060 011 021 1. Subscribe to The South African website's newsletters and follow us on WhatsApp, Facebook, X and Bluesky for the latest news.

Motorists to benefit from waived fees and penalties for expired driving licences
Motorists to benefit from waived fees and penalties for expired driving licences

IOL News

time4 days ago

  • IOL News

Motorists to benefit from waived fees and penalties for expired driving licences

The Transport Ministerial and Members Executive Council meeting held on June 27 resolved to waive the payment of the R72.00 for temporary driving licence card when motorists renew their driving licence cards. Image: Independent Newspapers Archives The Transport Department has responded to advocacy group pressure by waiving fees for temporary driving licence cards and suspending penalties for motorists with expired licences. This decision follows the significant backlog in licence renewals caused by a breakdown of the department's card printing machine in February, leaving many motorists in limbo. Lobby group, Organisation Undoing Tax Abuse, has been arguing that fining motorists who are still waiting for their renewed card licences was unfair. Minister Barbara Crecy said the backlog stood at 635,976 as at June 23, down from 733,000 when its card production machine became operational in May. Creecy said the card production facility has, since the machine became operational, embarked on working overtime to wipe out the backlog. 'The facility, with the support of the department, is in the process of obtaining approval from the Department of Public Service and Administration for additional overtime work hours for 24 hours a day to catch up on the backlog,' she said. Creecy was responding to parliamentary questions posed by EFF MP Omphile Maotwe. She said motorists were urged to keep their old cards and apply for temporary driving licences to avoid being penalised by law enforcement officers should they be pulled over. 'Motorists can drive with an expired driving licence card for up to three months before being eligible to be fined, provided they can show proof that they applied for a new card before their current expires. "If their card had already expired when at the time of application for replacement, they must also apply for a temporary driver's licence as the time and keep proof thereof in the vehicle.' Creecy also said The Transport Ministerial and Members Executive Council meeting held on June 27 resolved to waive the payment of the R72.00 for temporary driving licence card when motorists renew their driving licence cards. 'It was further resolved to impose a moratorium not to penalise motorists who drive their vehicles with expired driving licence cards and have proof when stopped by a law enforcement officer that they have applied for or renewed their driving licence card until a replacement card is issued.' Responding to DA MP Chris Hunsinger, Creecy said her department was in the process of acquiring an interim solution with the Government Printing Works as a solution to the obsolete card production machine. She also said the permanent solution will be the procurement of a new driving licence card production machine. 'However, that process cannot be embarked upon until finalisation of the declaratory order process,' she said. 'The procurement of a new driving licence machine remains in the procurement plan of the Driving Licence Card Account. The department has approached a competent court for a declaratory order. It is only after that process has been completed that procurement of a card machine will be started,' she said in response to Freedom Front Plus MP Philip van Staden. Last September, the department announced Idemia Identity and Security - South Africa as the preferred bidder to produce new smart driving licence cards. However, the contract was put on ice when Creecy asked the Auditor-General to investigate allegations of an irregular procurement process. In papers filed in court, the department wants the court to set aside the Idemia contract, re-run the tender and allow the Department of Home Affairs to print the licence cards in the interim. Get your news on the go, click here to join the Cape Argus News WhatsApp channel. Cape Argus