
MYT impact estimated at over Rs300b
The Power Division has challenged the regulator's decision on granting a multiyear tariff (MYT) to K-Electric (KE), alleging that it will allow the company to collect over Rs300 billion from consumers.
"The total financial impact is in excess of Rs300 billion of the interventions identified for review by the government of Pakistan in the KE MYT," the division said in a review petition submitted to the National Electric Power Regulatory Authority (Nepra).
It has asked Nepra to revisit its recent approval of electricity rates for KE, Karachi's main power supplier. KE's new tariffs come into effect from financial year 2024-25 and will run through FY30.
The government believes that Nepra has allowed several cost items and profit margins to KE that are higher or more favourable than for any other utility in Pakistan, resulting in unnecessarily high bills for consumers and extra pressure on public finances.
The Power Division has raised serious concerns over the preferential treatment granted to KE. Nepra set KE's fuel cost benchmark at Rs15.99 per kilowatt-hour (kWh), significantly higher than the rates paid by other utilities purchasing power from the national grid. This discrepancy adds Rs28 billion in FY24 and Rs13 billion in FY25 to the federal budget, shielding KE customers from these costs.
KE also received a "recovery loss allowance," despite its actual recoveries exceeding the threshold set by Nepra. No other utility enjoys this privilege, which has generated Rs36 billion in FY24 and Rs35 billion in FY25 for KE, amounting to over Rs200 billion in seven years.
Furthermore, Nepra allowed KE a 24% markup on working capital – higher than any other utility – boosting revenue by Rs2.4 billion in FY24 and Rs15 billion over seven years. Additionally, a higher distribution loss target of 13.90% (vs KE's own 13.46%) was set, passing Rs3.1 billion in FY24 and Rs21 billion over the seven-year period on to consumers. A unique 2% "law and order" margin was granted to KE, despite an improved security situation. This adds Rs14 billion in FY24 and Rs99 billion over seven years. KE was also allowed to retain "other income" from fines and investments, which should have offset customer costs.
Transmission losses were overestimated at 1.30% (vs actual around 0.75%), and KE keeps 75% of savings, creating inefficiency and costing Rs4 billion in FY24 and Rs28 billion over the seven-year period.
Excessive returns were also permitted. KE enjoys a 12% return on equity (RoE) in US dollar (around 24.46% in Pakistani rupee) on generation, compared to National Transmission and Despatch Company's (NTDC) 15% in rupees, and 14% RoE in US dollar (around 29.68% in PKR) on distribution, far exceeding the 14.47% RoE in rupees for others like the Faisalabad Electric Supply Company (Fesco).
Idle KE power plants still receive capacity payments, costing Rs12.7 billion in FY25 and Rs82.5 billion overall. Generous inflation indexation and a 17% RoE for these plants further strain finances.
The Power Division urged Nepra to align KE's tariff structure with national standards to ensure fairness, transparency and affordability, stressing the need to eliminate unjustified allowances and ensure equal treatment for all utilities.
KE eyes DISCO acquisitions
K-Electric held a corporate analyst briefing on Monday to provide insights into its recently approved tariffs and operational updates. The company expressed openness to acquiring other DISCOs (distribution companies), should the privatisation process move forward, according to Arif Habib Limited.
Its management highlighted that KE's total generation capacity currently stands at 2,397 megawatts (MW) from internal sources, while it procures over 1,600 MW externally. With the anticipated completion of NTDC interconnection projects, an additional 400 MW is expected to be integrated into its grid.
The utility's robust transmission network now comprises 7,095 MVAs capacity, 74 grid stations and 1,394 km of lines, while its distribution infrastructure includes 8,964 MVAs capacity, 2,112 feeders and over 31,000 pole-mounted transformers (PMTs).
Since its privatisation in 2005, KE has added 1,957 MW to its generation capacity, improved efficiency from 30% to nearly 46%, doubled transmission capacity and cut transmission and distribution (T&D) losses from 34.2% to 16%.
The utility estimates a cumulative saving of Rs900 billion for the government and consumers, alongside annual fiscal savings of Rs164 billion due to lower aggregate technical and commercial (AT&C) losses. Nepra has approved a multi-year tariff (MYT) structure of Rs39.98/kWh for KE, lower than the utility's request for Rs44/kWh. Return on equity (RoE) has been set at 14% for generation/distribution and 12% for transmission, with a 70:30 D/E ratio. The cost of local and foreign debt has been capped at Karachi Interbank Offered Rate (Kibor) + 2% and Secured Overnight Financing Rate (SOFR) + 4.5%, respectively.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Business Recorder
11 hours ago
- Business Recorder
PD in a quandary over less RLNG off-take by power plants
ISLAMABAD: Petroleum Division is still in a quandary over less off-take of Regasified Liquefied Natural Gas (RLNG) by the power plants, which is resulting in rapid saturation of Sui Northern Gas Company Limited (SNGPL) system, well informed sources told Business Recorder. 'SNGPL is continuously reporting reduced RLNG consumption by the power sector against its committed demand of 600 MMCFD for July 2025,' said Deputy Director (Tech Gas) Salahuddin Khan. M/s SNGPL in a letter of July 15, 2025 has reiterated that consumption remained 327 MMFCD on July 16, 2025, with a monthly average of 501-MMFCD, leading to surplus gas accumulation that has pushed system pack beyond critical levels. Short on commitment with SNGPL: Power sector uses 28pc less RLNG SNGPL further highlighted that power consumption on July 17, 2025 was recorded at 300 MMCFD, leading to continued gas accumulation in the system, which is unsustainable. 'If RLNG off-take is not immediately increased and maintained as per demand, the resulting high pressures may disrupt re-gasification at terminals, risking cargo discharge delays and potential financial losses in the form of demurrages and take-or-pay applicability. Alternatively, SNGPL shall be constrained to further curtail supplies from local gas fields,' said Directorate General (Gas) Petroleum Division. According to sources, Power Division has been requested to advise the concerned quarters to increase RLNG off-take as per demand for the month of July 2025 with re-coupment of previously unconsumed volumes to ensure smooth operation of the SNGPL system and to avoid any untoward situation in the national interest. On July 10, 2025, responding to the comments of Minister for Petroleum and Natural Resources Ali Pervaiz Malik on underutilisation of RLNG by the IPPs, Minister for Power, Sardar Awais Ahmad Khan Leghari staunchly defended the Economic Merit Order (EMO), declaring that any attempt to alter it would be a 'grave sin' (Gunnah Kabeera). He urged the Petroleum Division to review Liquefied Natural Gas (LNG) contracts—if necessary—just as the Power Division had done with Independent Power Producers. 'Ali Pervaiz Malik is a close friend, and his concerns are valid if the contracts are flawed,' Leghari said. 'Power plants operate under the EMO, which prioritises electricity generation from the cheapest sources. If RLNG plants don't qualify under EMO, they simply can't be operated,' he further explained. National Electric Power Regulatory Authority (Nepra) has been sharing violations of EMO by the System Operator during the public hearings on FCAs, on the basis of which billions of rupees of NGC (former NTDC) were withheld. However, this exercise has now almost been stopped without any reason. Nepra has directed that the System Operator and NGC must present a comprehensive update that includes covering outages of economic power plants, the resulting financial impact, and reliance on out-of-merit generation. The update should also include the status of identified system constraint, progress made, revised completion timelines and associated financial implications. At a recent meeting on gas issues, the representative of Power Division commented that challenges need to be met and disruptions need to be looked into. The Chair responded that the tactical issues would be discussed later and, presently, the focus needs to be on sustainability of the gas sector and how LNG over supply/ less off-take is affecting it. Secretary Petroleum framed the key issues to be addressed by the Committee, namely rationalisation of gas tariffs (for both indigenous and imported gas), synchronisation of LNG demand with the power sector along with resolution of circular debt within the gas sector. Copyright Business Recorder, 2025


Express Tribune
13 hours ago
- Express Tribune
PAC seeks remedy for post-200 unit billing
Junaid Akbar was elected unopposed as Chairman of the Public Accounts Committee in January 2025. Photo: Express/ File The Public Accounts Committee (PAC) on Tuesday took notice of the electricity tariff slab hike that penalises consumers for exceeding 200 units, directing the Power Division to propose a solution for inflated bills that persist for six months even after a single unit crosses the limit. The committee meeting, chaired by MNA Junaid Akbar Khan, reviewed audit paras related to the Ministry of Energy. Expressing concern, the chair demanded an explanation for the prolonged penalty on consumers who exceed the 200-unit threshold once. Officials briefed the committee on the status of Independent Power Producers (IPPs), revealing a sharp rise in installed capacity over the years. Committee member Shazia Marri questioned why provinces like Sindh and Khyber-Pakhtunkhwa continue to endure up to 16 hours of load-shedding despite a surplus in electricity generation. The power secretary informed the committee that 58% of electricity users fall under the 200-unit slab, with subsidised rates now benefiting 18 million consumersup from 11 million previously. He acknowledged the issue of high bills lasting months for consumers who breach the limit once. "To increase the slab limit, a higher subsidy will be needed," he said, adding that the government aims to reform the system by 2027, shifting to direct subsidies using BISP data. The Energy Ministry also noted that the installed capacity of IPPs rose from 9,765MW in 2015 to 25,642MW in 2024, with annual capacity payments jumping from Rs141 billion to Rs1.4 trillion. Committee member Syed Naveed Qamar disputed the Power Division's claim that coal was the main driver of high electricity costs. Meanwhile, Junaid Akbar raised doubts over reports of 200% electricity generation from bagasse, calling the numbers unrealistic.


Business Recorder
a day ago
- Business Recorder
Panels formed to address issues facing gas sector
ISLAMABAD: The government has established four specialised panels to address key issues in the gas sector, including circular debt, LNG tariffs, unaccounted-for gas (UFG) losses, and the increasing share of LNG in the national gas system, official sources told Business Recorder. According to sources, a Committee on Implementing Structural Reforms in the Petroleum Sector— formed by the Prime Minister and chaired by the Minister for Petroleum and Natural Resources— has convened multiple meetings to deliberate on these matters. The composition of the Committee is as following: Minister for Petroleum (Convener), Advisor to Prime Minister on Privatisation, National Coordinator on Energy Reforms, Lt General Muhammad Zafar Iqbal (retd) Secretary, Power Division, Secretary, Petroleum Division, Secretary, Cabinet Division/ representative and Chairman, OGRA. Pakistan faces LNG glut: minister The Minister for Petroleum emphasised that while the foundational work for the committee's assignment had been done through its Integrated Energy Study (Woodmac) conducted by the Petroleum Division, the present focus is to chalk out an implementation plan. He highlighted the importance of aligning the Committee's recommendations with the preparation of the Annual Delivery Plan (ADP) to be settled with LNG suppliers. The representative of Power Division commented that challenges need to be addressed and disruptions need to be looked into. The Chair responded that the tactical issues would be discussed later and, presently, the focus needs to be on sustainability of the gas sector and how LNG over supply/ less off-take is affecting it. The Secretary Petroleum framed the key issues to be addressed by the Committee, namely: rationalisation of gas tariffs (for both indigenous and imported gas), synchronisation of LNG demand with the power sector along with resolution of circular debt within the gas sector. He noted that most of the required data and foundational analysis is already available through the Woodmac study and will serve as the basis for the committee's deliberations. The Chair commented that Committee should focus on implementation as a Plan. The Committee needs to focus on 2026 ADP's preparation and to devised policy of Integrated Energy strategy for Pakistan. The Committee constituted a sub-committee comprising Secretary Power (Lead), DG Gas, MD SNGPL and a nominee from the Task Force. The chair can co-opt any member if he/she deems it necessary to effectively carry out the work and decided to constitute the following (ToRs) for the four sub-committees: Subcommittee 1: work out a comprehensive proposal to synchronise LNG demand of the power sector in a manner that ensures timely and adequate supply without causing abrupt fluctuations in demand. GCEP submission to Woodmac to be considered; and identify causes and propose solutions to avoid sudden changes in LNG requirements by the power sector that lead to diversion of LNG cargo to other sectors. Net Proceeds Differential (NDP) claims, if any, arising due to reduced off-take by Power Division to be considered. Sub-Committee -2 comprising Muhammad Ali (Lead), a nominee of KPMG, Islamabad and any co-opted member to formulate proposals to deal with circular debt stock in the gas sector. Sub-Committee 3 is on LNG tariff rationalisation. Its scope will formulate proposals for LNG tariff rationalisation by revisiting all compositions of tariff (terminal charges, importer margins and LNG service agreement charges etc.) RLNG demand maximization options to be proposed (especially in domestic sector). Sub-Committee 4- domestic gas tariff efficiency and transparency will address efficiency and transparency in tariff for domestic gas tariff including revenue requirements of the gas utilities, actual UFG losses taking into account growing LNG share in gas system, etc. Sui Companies Return on Assets formula revision to be considered to bring better efficiencies. Copyright Business Recorder, 2025