Bombay High Court denies L&T relief in case against MMRDA over  ₹16,000-crore road projects

Bombay High Court denies L&T relief in case against MMRDA over ₹16,000-crore road projects

Mint20-05-2025
Mumbai: The Bombay High Court has denied relief to Larsen & Toubro (L&T) over its petitions contesting the opening of financial bids for the Thane-Ghodbunder to Bhayander tunnel and elevated road projects, valued at over ₹ 16,000 crore, undertaken by the Mumbai Metropolitan Region Development Authority (MMRDA). A detailed order is awaited.
On Tuesday a division bench led by Justices Kamal R. Khata and Arif S. Doctor delivered a ruling on two petitions filed by L&T, in which the company alleged that it had not been informed about the status of its bids, while the other bidders had received such updates.
On the plea contesting the opening of financial bids for the elevated road project, the court declined L&T's request to further extend the stay on the opening of bids.
The court also directed that the bids submitted electronically by L&T for both projects be preserved in a sealed cover for two weeks, giving the company time to approach the Supreme Court. The high court also instructed the MMRDA to communicate the tender award decision in accordance with the instructions to bidders (ITB).
The two infrastructure projects aim to connect Thane and Mira-Bhayandar —a tunnel from Gaimukh to the Fountain Hotel junction at Shilphata, and an elevated creek bridge linking Bhayandar to Ghodbunder Road in Thane. The proposed bridge would be the second-largest in the region after the Mumbai Trans Harbour Link (MTHL), also known as Atal Setu.
MMRDA invited tenders in July 2024, and on 8 October, in response to a separate petition by L&T, the agreed to extend the deadline to submit bids by 60 days.
Appearing on behalf of L&T, senior counsels Janak Dwarkadas and Abhishek Manu Singhvi told the bench both the technical and financial bids were submitted on 30 December 2024. They said MMRDA opened the technical bids on 1 January and began evaluating them, but L&T received no communication on the status of its bids.
The company said MMRDA then proceeded to schedule the opening of financial bids for 13 May, even though the company hadn't received any information on the outcome of the technical bid evaluation. It said while it wasn't informed about the opening of financial bids, other bidders were intimated.
The company therefore approached the high court, seeking an urgent stay on the process. It argued that opening financial bids while excluding it from participation would violate the principles of a fair and transparent tender process and established legal norms.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

One year after contractor approval, green nod for Madh-Versova bridge
One year after contractor approval, green nod for Madh-Versova bridge

Time of India

time11 hours ago

  • Time of India

One year after contractor approval, green nod for Madh-Versova bridge

Mumbai: Almost a year after issuing a letter of acceptance to the contractor, the BMC has obtained an NOC from the Union environment ministry for the proposed Madh-Versova bridge. The civic body now has to seek approval from the Bombay High Court, as the project will impact 2.3 hectares of protected mangroves -- a mandatory step for any construction in ecologically sensitive zones. "The exact number of mangroves affected is yet to be determined. Once all approvals are in place, the work order will be issued," a BMC official said. The total contract cost stands at Rs 2,395 crore, comprising Rs 1,990 crore for civil works, Rs 39.89 crore for operations and maintenance over three years, and Rs 365.36 crore as GST (18%). T he planned cable-stayed flyover will span 2.06 km, connecting Madh island to Versova by crossing over the Madh creek. Currently, the two areas are linked by a ferry service, with no direct road access. Motorists must take lengthy detours via Link Road, SV Road or Western Express Highway, often facing travel times exceeding 45 minutes during peak hours. The bridge is expected to cut commute times by 40 to 60 minutes. You Can Also Check: Mumbai AQI | Weather in Mumbai | Bank Holidays in Mumbai | Public Holidays in Mumbai Environmentalists have voiced strong objections, citing the destruction of natural stormwater buffers. Advocate Godfrey Pimenta said, "In the 1991 Development Plan, this was designated as a no-development zone (NDZ). However, the 2034 DP introduced a road network that includes the Madh-Versova bridge. This move will systematically destroy natural habitats and will burden local infrastructure beyond its capacity. "

Boeing Defense Workers Reject Contract in New Labor Turmoil
Boeing Defense Workers Reject Contract in New Labor Turmoil

Mint

time11 hours ago

  • Mint

Boeing Defense Workers Reject Contract in New Labor Turmoil

(Bloomberg) -- Boeing Co. faces the risk of a strike at its St. Louis defense hub after union workers rejected a contract offer that would boost their wages by 20% over four years. The International Association of Machinists and Aerospace Workers Local 837, which represents 3,200 Boeing defense workers in Missouri and Illinois, voted overwhelmingly against the new terms Sunday. The Boeing proposal 'fell short of addressing the priorities and sacrifices' of the company's skilled workforce, the union said in a statement. 'Our members are standing together to demand a contract that respects their work and ensures a secure future.' While the present contract expires at 11:59 p.m. Central Time on Sunday, management still has a chance to win over rank-and-file members by sweetening its offer during a seven-day 'cooling off' period. If that's unsuccessful, IAM Local 837 workers will walk off the job and shut down manufacturing in Boeing's military aircraft hub. The aerospace manufacturer is seeking to avoid another labor standoff after a strike by a Seattle-based Machinists union crippled manufacturing at its commercial jet factories for more than two months last year. Boeing could not be immediately reached for comment. Any labor strife would be costly for Boeing's defense division, which hasn't earned an annual profit since 2022 and is in the middle of a turnaround. A strike would shut down assembly lines for Boeing's F-15 and F/A-18 fighter jets, T-7A trainer, MQ-25 drone refueler and other weapons systems. The labor uncertainty will be a focus for analysts when Boeing reports quarterly earnings on Tuesday. It's also a bellwether as GE Aerospace launches contract negotiations with a separate IAM local on Sunday. St. Louis workers last went on strike in 1996 and don't have a history of activism, unlike Boeing's unions in the Pacific Northwest, according to Scott Mikus, an analyst with Melius Research. Union members initially rejected management's offer during the last negotiation with Boeing in 2022, before accepting a three-year deal with a 14% general wage increase and cost-of-living adjustments. While Puget Sound labor leaders endorsed Boeing's initial offer last year, they were rebuffed by rank-and-file members embittered by an earlier 10-year contract that stripped away pensions and locked in low wage increases while inflation soared. The lengthy strike squeezed the company's working capital and spurred Boeing to sell equity worth almost $24 billion. --With assistance from Bill Haubert. (Updates with comments from labor union in third paragraph, attempt to reach Boeing in fifth paragraph.) More stories like this are available on

Roshanara Club with revamped sport facilities, wellness and banquet areas, opens its doors after almost 2 years
Roshanara Club with revamped sport facilities, wellness and banquet areas, opens its doors after almost 2 years

Indian Express

time13 hours ago

  • Indian Express

Roshanara Club with revamped sport facilities, wellness and banquet areas, opens its doors after almost 2 years

After being closed for renovation for nearly two years, the century-old Roshanara Club reopened its doors to the residents of the Capital on Sunday. Renovated and restored by the Delhi Development Authority (DDA), the heritage club now boasts of revamped sport facilities as well as modern wellness and banquet areas, among others. The club, spread across 22 acres, was taken over by the DDA for renovation on September 29, 2023. This was after L-G V K Saxena – in his maiden visit to the club on January 12, 2023 – noticed that the 'majestic structure was lying in a dilapidated state with poor maintenance with a crumbling facade', the DDA said in a statement. Saxena, who unveiled the revamped club, said, 'It is a big moment for us, as this heritage club has been restored and relaunched. I congratulate the people of Delhi on this occasion. Delhi is a city of heritage and in the last three years, a number of heritage (sites) have been restored and we are committed towards (restoring) more in the future.' The club was established on August 15, 1922 as an elite recreational and social retreat for the Britishers residing in the area around present-day Delhi University and Civil Lines. It was named after Begum Roshanara, the daughter of Mughal Emperor Shah Jahan, who was buried in the neighbouring Roshanara Bagh. The club is considered the birthplace of the Board of Control for Cricket in India, which was formed in 1928 when Indian cricket administrators gathered at Roshanara Club. 'Particular attention was given to the preservation of the club's architectural legacy. The century-old façade, including the European-style doors and windows, Mangalore-tiled roof, and intricate wooden trusses, have all been carefully restored. Antique chandeliers and original furnishings were refurbished and reupholstered to revive their classic charm,' the DDA said in its statement. It added that indoor facilities at the club now include a main lounge, card and billiards rooms, banquet area, bar and dining hall, library, gym, squash and badminton courts, a swimming pool, and a wellness area with yoga, sauna, and steam rooms. Outdoor amenities include clay, grass, and synthetic tennis courts, cricket grounds, a mini football zone, basketball area, and a jogging track. The DDA said civil works involved anti-termite treatment, waterproofing, marble polishing, wooden flooring repairs, and renovations to sanitary facilities. Important upgrades were made to the squash and badminton courts, swimming pool, and various places in the club house building. While electrical systems were overhauled, AC cooling was enhanced by providing requisite units, ducting and wiring were concealed, and damaged fittings, switches and light fixtures were replaced. Chandni Chowk BJP MP Praveen Khandelwal, Model Town BJP MLA Ashok Goel, DDA Vice Chairman N Saravana Kumar, and senior officials also attended the launch. Devansh Mittal is a trainee correspondent with The Indian Express. He studied political science at Ashoka University. He can be reached at ... Read More

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store