Meghalaya has made progress in execution of hydro projects: Minister
Mondal said the government is proposing to revive the Kynshi hydroelectric project and securing the clearance for setting up the 210-MW Leshka Stage-II hydroelectric project.
In 2022, the government had decided to cancel the agreement signed with Athena Power Pvt Ltd and the JayPee Group for the construction of 270MW Kynshi Stage 1 and 325MW Kynshi Stage 2 hydro projects after the power developers expressed their inability to move forward with the project.
Mondal said the government is optimistic in reviving the long-stalled Kynshi hydro power project to its original Run-of-River (RoR) configuration after years of uncertainty and delay to enhance power requirement in the state.
The implementation of the Kynshi project, originally awarded to M/s Athena Pvt Ltd, was delayed due to lack of provisions in the state's power policy to convert the project into a hybrid model, combining RoR and Pump Storage Project (PSP)
'The old MoU (memorandum of understanding) was based only on the run-of-river model. As they wanted to add the PSP component, and since our earlier power policy didn't include PSP, the cabinet decided to scrap the old MoU. Now, they want to revert to the original RoR model without the PSP. So, we'll have to take it to cabinet again to reinstate the old MoU,' Mondal said.
He clarified that no fresh MoU has been signed yet, but the government plans to revive the old one.
On Thursday, members of the Joint Committee of Local People on Kynshi Hydro Power Project (JCLPKHPP) met Mondal and demanded that the state government expedite the implementation of the Kynshi project.
'The most important thing is that the local people from those areas now want to cooperate with the government and the agency that will execute the project. I am very optimistic because we need more power generation. Without generation, we cannot enhance our power position,' the Power Minister said.
With regard to the Rs 2,100 crore Leshka hydro power project stage-II, Mondal said the final hurdle in the project is expected to be cleared this year.
'The 210 MW RoR project has already cleared 11 out of 12 chapters, including environment and forest clearances, required for its implementation. The remaining chapter is the most critical and challenging one,' he said while expressing optimism that the project will be cleared by the end of the year.
UNI RRK PRS
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


India.com
16 minutes ago
- India.com
Days after getting married to Lauren Sanchez, Jeff Bezos gets richer by Rs 63000000000 due to…
Jeff Bezos, the founder of Amazon, has sold a major chunk of his Amazon shares within days after his wedding to Lauren Sanchez. According to a regulatory filing in the US and a report by Bloomberg, Bezos sold more than 3.3 million Amazon shares and earned around $736.7 million from the deal. This will value around Rs 6,300 crore in Indian currency. Why Jeff Bezos Sold Amazon Shares? This stock sale was actually a pre-planned agreement known as a 10b5-1 trading plan. It was already adopted by Bezos in March 2025. These trading plans allow top executives and insiders to sell company shares at scheduled times to avoid any concerns related to the insider trading. As per this plan, Bezos wants to sell up to 25 million Amazon shares by the end of May 2026. What Is Jeff Bezos's Net Worth Bezos, who is now the third-richest person in the world. According to Bloomberg Billionaires Index, he has sold share sales in the past. In 2023 also he sold around 75 million shares of $13.6 billion as per the same method. He had used this method to support other ventures like space exploration company, Blue Origin. His current net worth is around $241 billion. The timing of this latest stock sale was discussed more in the news because it happened after Bezos' wedding to Sanchez in Venice, Italy. The wedding ceremony, held for three days. Many celebrities from the world were invited for the same. According to media reports, the overall cost of the wedding events was around $50 million. Although the share sale happened after the wedding, it has no connection with it and was executed as part of his scheduled trading plan.


Time of India
29 minutes ago
- Time of India
Centre seeks two weeks to submit its decision at HC
Kochi: The Union govt on Friday sought two more weeks to inform the high court its decision on the matter of loan waivers for the victims of the landslides at Chooralmala and Mundakkai in Wayanad on July 30, 2024. Assistant solicitor general ARL Sundaresan made the submission in response to the suo motu petition concerning the rehabilitation of the Wayanad landslide victims. He added that deliberations on the matter are ongoing between the ministries concerned. Accordingly, the court adjourned the petition to July 25 for further hearing. Additionally, advocate Renjith Thampan, the amicus curiae, suggested that a report be called from the state govt regarding the utilisation of the Rs 120cr from the state disaster response fund (SDRF), which had been permitted by the bench earlier in March 2025 for the rehabilitation works in Wayanad. Advocate general K Gopalakrishna Kurup, in response, informed the court that the report in that regard can be furnished on the next posting date. The state disaster management authority also placed before the court videos and photographs showing the removal of debris from the disaster-affected areas in Wayanad. The AG further informed the court that environmental clearance from the ministry of environment, forests and climate change (MoEFCC) for the proposed four-lane tunnel corridor from Kozhikode to Wayanad was granted on June 17, and that a detailed project report has also been prepared. The Court instructed the AG to produce the report and share a copy with the amicus curiae. The court also directed the amicus curiae to review the report and assess its feasibility.


Time of India
29 minutes ago
- Time of India
Wayanad township to be ready by Dec: Rajan
Kozhikode: Revenue minister K Rajan said the homes for Mundakkai–Chooralmala disaster survivors at Elstone Estate township will be completed by Dec 2025. The township will house over 1,662 people in 410 homes. Of these, 140 people have each received a seven-cent plot. Rajan said the govt spent Rs 108 crore on survivor rehabilitation. He also instructed the use of more machinery to clear landslide debris from Punnapuzha. The minister said Rs 3.6 crore was allocated for Kudumbashree's micro plan and Rs 43.7 crore was spent on land acquisition at Elstone Estate. A total of Rs 13.3 crore was given as compensation to the families of 220 deceased people and Rs 15.6 crore was provided to 104 people as financial support of Rs 15 lakh each instead of housing. For livelihood support, Rs 10.1 crore was given to 1,133 people. Another Rs 20 crore was approved for running the township's special office. Emergency aid of Rs 1.3 crore and rental support of Rs 4.3 crore were also provided. The minister said foundation work of 51 homes is complete. Dynamic cone penetration tests were done for 54 homes and plain cement concrete work was finished in 41. Foundation work is in progress for 19 more homes. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like 5 Books Warren Buffett Wants You to Read In 2025 Blinkist: Warren Buffett's Reading List Undo Site preparation for the second phase of construction is progressing rapidly. Rajan said the model home will be completed by the end of July. At present, 110 workers are working on site and more labourers will be brought in soon to speed up the work, he added. Responding to the concerns raised by people in Padavettikunnu who are not on the township beneficiary list, the minister said their requests would be examined. He assured that the government would not abandon disaster-affected families. He said that a separate bank account was opened to handle all financial transactions related to construction of the township. A monitoring committee including the chief minister, the opposition leader and sponsor representatives is overseeing the full process to keep it transparent.