Regional Ratepayers To Fund $3.58m Loan For Tarawera Sewerage Scheme

Regional Ratepayers To Fund $3.58m Loan For Tarawera Sewerage Scheme

Scoop28-05-2025
Wednesday, 28 May 2025, 8:05 pm
Article: Laura Smith - Local Democracy Reporter
Bay of Plenty regional ratepayers are set to fund a $3.58 million loan towards Rotorua's controversial Tarawera Sewerage Scheme.
The decision comes as Rotorua Lakes Council prepares to deliberate today on how to split costs of the $32.3m scheme between general Rotorua ratepayers, Tarawera property owners and other funders.
Tarawera households currently face a lump sum cost of $50,315 each to connect to the reticulation scheme, which replaces septic tanks.
The cost would rise to $55,601 for those who do not agree to on-site work on their properties by June 1.
Bay of Plenty regional ratepayers are set to fund a $3.58 million loan towards Rotorua's controversial Tarawera Sewerage Scheme.
The decision comes as Rotorua Lakes Council prepares to deliberate today on how to split costs of the $32.3m scheme between general Rotorua ratepayers, Tarawera property owners and other funders.
Tarawera households currently face a lump sum cost of $50,315 each to connect to the reticulation scheme, which replaces septic tanks.
The cost would rise to $55,601 for those who do not agree to on-site work on their properties by June 1.
A report in the meeting's agenda said the loan would not necessarily reduce Lake Tarawera residents' lump sum contribution, but could 'give RLC an opportunity to reduce its interest costs and the targeted rate payable'.
Making the loan interest-free would result in BOPRC forgoing about $150,000 per annum, or about $1.30 per ratepayer.
Regional councillor Kevin Winters said the decision showed the council was helping Tarawera residents, while also signalling it wanted them to sign off work on their properties so stage two of the scheme could be implemented 'en masse'.
He acknowledged it was not a grant as had been requested by RLC.
BOPRC's chief executive could potentially further negotiate conditions, such as capping Tarawera households' costs.
Councillor Jane Nees supported this cap being the $36,600 some Tarawera residents sought.
Councillor Lyall Thurston said BOPRC wanted to see 'some finality to this ongoing saga at Tarawera', and hoped the decision would be well received by RLC.
He said he understood some colleagues held concerns and apprehensions.
Councillor Ken Shirley said spreading the cost among regional ratepayers was a 'slippery slope' in what other councils might expect in future, but he believed schemes should be considered on their own merits.
The regional council also voted to have an independent review of the scheme funding and project management completed by the councils prior to loan drawdown.
It came after Tarawera resident Tracey McLeod raised potential issues with the stated costs and funding of this and other sewerage schemes.
She presented at a prior regional council meeting and emailed both councils the results of her investigation on Friday.
Thurston said in Monday's meeting that McLeod had gone to 'great lengths to emphasise that costs have been overstated in the scheme' and there were calls for an inquiry and audit.
He believed there could be pushback from both councils on that, but believed some of the 'figures bandied around need to be analysed very closely'.
'I'm starting to get totally confused with the size and the quantum of the figures that members of the community say are grossly inflated, overstated and quite frankly, I want to know what the real story is.'
He said the figures in question had been circulating in the public domain for a long time and needed to be challenged, acknowledged and this issue 'put to rest once and for all'.
BOPRC chairman Doug Leeder agreed some 'forensic analysis' was needed to either validate or reject what was claimed.
RLC infrastructure and assets group manager Stavros Michael told Local Democracy Reporting the council was aware BOPRC was working on a response to McLeod's claims about the Rotorua Te Arawa Lakes programmes deed funding, which BOPRC administered.
He said the Tarawera Sewerage Scheme is not part of those programmes and had its own funding plan.
RLC would be considering the scheme's costs and funding as part of the 2025/26 Annual Plan.
RLC councillors will meet today to begin Annual Plan deliberations.
Funding options for Tarawera the council consulted the community about included retaining the status quo, or reducing Tarawera households' contribution by $1m or $4m and splitting it among general Rotorua ratepayers instead.
Of 344 public submissions on the matter, 232 wanted the $4m taken off Tarawera households.
© Scoop Media
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Rotorua Lakes Council takes back control of parking services
Rotorua Lakes Council takes back control of parking services

RNZ News

time10-07-2025

  • RNZ News

Rotorua Lakes Council takes back control of parking services

The current parking system has had its detractors among users. Photo: LDR / Mathew Nash One-hour-free parking everywhere and a three-hour limit in the core CBD are among ideas on the table as Rotorua begins a parking overhaul. Rotorua Lakes Council has begun the process of bringing many of the city's parking services in-house by July 2026. This after a decision not to renew its contract with current provider i-Park. It marks the end of the fully outsourced parking model introduced in mid-2018, which has been a source of frustration for some residents, business owners and community leaders. On Wednesday, the council's Community and District Development Committee adopted a hybrid service delivery model. This followed a public-excluded decision on 28 May not to extend the existing arrangement. From next year, the council will directly employ parking wardens and take over responsibility for customer service and financial administration. The council's Community and District Development Committee adopted a new hybrid model of service delivery in Wednesday's meeting. Photo: LDR / Mathew Nash Meanwhile, infrastructure and technology, such as pay machines and software, will remain outsourced after procurement by tender. The adopted report highlights the desire for a "simplified" approach to parking. This could potentially include one-hour-free parking citywide, fewer meters and maximum three-hour parking limits in the core CBD, with longer stays allowed in the off-street parking building and CBD fringe. The operational details of the new model would be mapped out over the next 12 months, including as part of Annual Plan consultations. The move brings Rotorua in line with other councils, including six visited as part of a review into best-practice approaches to parking. Concerns were raised by some councillors around the validity of the comparison of the six sites in question - Auckland, Hamilton, Napier, New Plymouth, Tauranga and Wellington - to Rotorua. Councillor Gregg Brown wanted to ensure the new parking system served to improve "CBD vibrancy". "We don't want this to be a handbrake to that and there are potentially other models out there that need to be taken on board." One such model he alluded to was Taupō's. Councillor Robert Lee sought and was given assurance Taupō's system and model would be evaluated as part of any ongoing process. Councillor Fisher Wang acknowledged that this decision was a matter of process but insisted on the importance of taking this step now. "From my perspective it's to make sure we do things right now so that later on, when it comes to any following decisions, we have a smooth process of transfer," Wang said. "Clearly, we see that the current system has its issues, and we want to make sure we do a good job in finding the best system that works for our unique requirements." The sun is setting on the current Rotorua CBD parking model. Photo: LDR / Mathew Nash Rotorua's current parking system has been managed entirely by private provider i-Park for the past seven years. The technology-driven approach, including app-based payments and automated enforcement, has drawn complaints over usability, unfair fines and a lack of transparency. In early 2020, CBD business leaders met with the council to discuss their concerns, while locals were left frustrated later in the year with the cost of implementing the new model. As recently as May, issues with the i-Park app delayed charges and led to some drivers being charged a month's worth of fees at one time. A spokesperson for i-Park said its partnership with Rotorua Lakes Council had been "broadly positive" but they respected the move and remained open to future involvement. "When we began, Rotorua had parking infrastructure that no longer reflected modern standards or community expectations. We're proud to have delivered a significant transformation, introducing up-to-date technology and professional operations in line with the scope and direction provided by [the] council." A transition plan is being worked on to ensure continuity of service and to minimise disruption for the public. "Our contract includes clear provisions for an orderly transition, and we are fully committed to supporting this process. We'll work closely with [the] council and our priority is a seamless and professional handover that serves the best interests of Rotorua's residents, businesses, and visitors." The council aims to go live with the new system from 1 July, 2026. The election in October meant the new council would be responsible for final decisions around contract awards, parking fees and bylaw updates. Community consultation will take place, while wider public engagement will occur through the 2026/27 Annual Plan process, where final fees and layout decisions will be confirmed. LDR is local body journalism co-funded by RNZ and NZ On Air.

Affordable Homes To Address Rotorua Housing Shortage
Affordable Homes To Address Rotorua Housing Shortage

Scoop

time15-06-2025

  • Scoop

Affordable Homes To Address Rotorua Housing Shortage

Associate Minister of Housing Rotorua whānau will enjoy greater access to modern affordable housing thanks to a community-led partnership delivering 189 affordable homes backed by the Government, Associate Housing Minister Tama Potaka says. Up to 150 of these will be social housing homes to be delivered by end-June 2027 under a new community-led approach through the Rotorua Lakes Council (RLC), the Ministry of Housing and Urban Development (HUD), and Community Housing Providers. In addition, a project consisting of 39 affordable rentals will be delivered in 12-months by Ōwhata Kōhanga Rākau, which is partly funded by HUD's Māori Housing programme. 'Rotorua is a priority location for housing,' Mr Potaka says. 'We're backing community-led solutions to address the need here, which has seen disproportionate numbers of people in emergency and temporary housing, and about 700 applicants waiting on the social housing register. 'Rental affordability has been a long-standing issue. Some whānau have struggled to find an affordable rental home so they've been limited to emergency and social housing. 'The new homes will complement RLC's new Rotorua Housing Plan to enable iwi and hapu housing aspirations, increase housing choice and support diverse housing needs. The plan was developed with extensive local engagement. 'As promised, we are also making solid progress toward ending Contracted Emergency Housing. We prioritised exiting two motels located near Whakarewarewa Village and this will be followed by the exit of a further two motels by the end of July, with all remaining motels exited before the end of the year. 'Progress has been the result of the Government's significant investment in the city, working with central government agencies such as HUD, leadership from Rotorua Mayor Tania Tapsell and the RLC, as well as by Iwi and other local parties to increase social and affordable housing. 'The 150 social homes to be delivered are part of the 1,500 homes to be built by CHPs and funded from Budget 2024. The Government committed $140 million in new funding for 1,500 new social housing places in May last year. Funding has been approved for these Rotorua social homes under this pathway. 'The 39 affordable rental homes are part of a $200 million package announced in February that will enable the delivery of 400 affordable rentals in high-need areas by the end of June 2027. 'Further to the 189 new homes announced today, the Government is also in the early stages of progressing a further 80 affordable rental homes for whānau Māori in Rotorua and we'll have more details on this next stage soon.'

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store