Greater Dublin Drainage Project gets green light seven years after it was first proposed
The major water treatment plant, which will have the capacity to serve 500,000 people, is to be located on a 30-hectare site in Clonshagh in Fingal. Uisce Éireann says people in north Dublin, as well as parts of Meath and Kildare will benefit from it.
Objections to the development over environmental concerns had slowed the planning process, and had knock-on effects for housing projects in the area.
The cost of the project has doubled over the last seven years,
now sitting at €1.3 billion
.
An Coimisiún Pleanála deemed it unnecessary to hold more public meetings and said there would be net positive long-term effects on public health.
It also said there would be 'significant negative temporary impacts' on the public, from noise, vibrations, and other disturbances during construction.
As well as nearby houses, Connolly Hospital and St Francis hospice may be impacted.
However, the Commission said mitigation measures, such as the construction of a 1km tunnel for an orbital pipeline through the plant's site, will help.
Temporary rehousing of local residents may be considered, if the disturbances still prove too much.
The Commission doesn't believe that odour from the site will be a problem for locals.
Advertisement
On the environmental impact, the Commission said there will be 'a number of slight or short and very localised negative impacts' to marine biodiversity.
There could also be 'short-term moderate' impact on birds due to the noise and visual disturbance.
'The cumulative benefits of the totality of the treatment system extend beyond the impact of the emissions,' the Commission said.
A map of the scale of the GDDP
Uisce Éireann
Uisce Éireann
Uisce Éireann
had warned
that the drinking water supply in north Dublin was going to be tight over the coming years if delays with projects such as the water treatment plant persisted.
The chair of the utility's board Jerry Grant also said the delivery of homes had become 'very challenging' due to various judicial reviews involving this project and others.
Uisce Éireann described it as an essential project.
In a statement today, a spokesperson for Uisce Éireann said: 'The Greater Dublin Drainage Project was first submitted for planning in 2018 and since that time, population and economic growth means the volume of wastewater we are producing has continued to grow, so the delivery of this critical infrastructure project is more important than ever.
'This project will increase the development potential of Dublin and parts of the surrounding counties by providing new infrastructure that will alleviate pressure within the existing wastewater network.'
The utility said the next step is completing the remaining pre-construction statutory processes and progressing the procurement of contractors to construct the project.
The project is anticipated to take four years to complete.
Readers like you are keeping these stories free for everyone...
A mix of advertising and supporting contributions helps keep paywalls away from valuable information like this article.
Over 5,000 readers like you have already stepped up and support us with a monthly payment or a once-off donation.
Learn More
Support The Journal
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

The Journal
2 days ago
- The Journal
Please don't object any further against Greater Dublin Drainage Project, appeals Taoiseach
TAOISEACH MICHEÁL MARTIN has urged the public not to object further to the Greater Dublin Drainage Project, stating it is urgently needed. During the week, the project was given the green light after seven years of uncertainty caused by legal challenges. The major wastewater treatment plant, which will have the capacity to serve 500,000 people, is to be located on a 30-hectare site in Clonshagh in Fingal. Uisce Éireann says people in north Dublin, as well as parts of Meath and Kildare will benefit from it. Objections to the development over environmental concerns had slowed the planning process, and had knock-on effects for housing projects in the area. The cost of the project has doubled over the last seven years, now sitting at €1.3 billion . Advertisement Speaking this morning in Cork city, Martin said: 'I'm not sure that people are as aware of the urgency of all of this.' 'I would appeal to people not to object any further. I would appeal to people not to engage in judicial reviews of that An Bord Pleanala planning decision in terms of the drainage project, because the people of Dublin need it and surrounding counties need it,' he added. He went on to state that as a society, there is now a need to 'balance our concerns about particular projects with the overall common good in society'. Water supply is the most fundamental common good of all, said the Taoiseach. 'We do not have the luxury or the capacity for extended judicial review mechanisms and processes anymore. Because the situation, in respect of the most fundamental of all, infrastructure, is serious,' said Martin. Investment in infrastructure will be a key pillar in this year's budget, he said, stating that if it is not done now, future generations 'will not forgive us'. Readers like you are keeping these stories free for everyone... A mix of advertising and supporting contributions helps keep paywalls away from valuable information like this article. Over 5,000 readers like you have already stepped up and support us with a monthly payment or a once-off donation. Learn More Support The Journal


RTÉ News
2 days ago
- RTÉ News
EU sets sights on climate target deal by September
Most European Union countries have backed plans to agree a deal on their new climate change target by September, sources familiar with the discussions have said. EU countries are negotiating their new 2040 climate change target, which the Commission last week proposed should be a 90% emissions reduction from 1990 levels, although countries would be allowed to buy international carbon credits to meet a limited share of the goal. Denmark, which took over the EU's rotating presidency this month and is chairing negotiations among countries on the target, aims to strike a deal at a summit of ministers in September, Denmark's energy and climate ministry said in a statement. "It is extremely important that we unite the EU around new climate goals ... We have a very small window to put a bow on these negotiations," Danish climate minister Lars Aagaard said, following a meeting of EU countries' climate ministers in Aalborg, Denmark, which concluded today. In the meeting, most of the EU's 27 member countries backed the plan to land a deal on the 2040 climate target in September, three sources familiar with the talks said. But a handful of countries, including Poland, Hungary and the Czech Republic, opposed a fast-tracked deal, while others demanded changes to the Commission's proposal, the sources said. "This is not a decision that we can just take lightly, it's affecting the whole economy. Working under such time pressure is just not reasonable," Polish deputy climate minister Krzysztof Bolesta said, of the proposed September deadline. Spokespeople for Hungary and the Czech Republic's EU representations each confirmed their governments opposed the September deadline. Climate change has made Europe the world's fastest-warming continent, fuelling deadly heatwaves and fires. But the 2040 target has stoked political tensions over how ambitious to be in tackling climate change, at a time when Europe is sharply raising defence spending and attempting to support struggling local industries. To attempt to win over sceptical governments, the Commission proposed flexibilities that would soften the 90% emissions target for European companies. Bolesta said countries had raised concerns in Friday's meeting over issues including a lack of clarity on how these flexibilities would work. The EU faces a mid-September deadline to submit a new 2035 climate target to the UN, which the Commission has said should be derived from the 2040 goal.


Irish Independent
3 days ago
- Irish Independent
Road closure in Meath to facilitate major water project between Duleek and Navan
To facilitate works, a 24-hour temporary road closure will be in place on the R153 from the R153/R150 Junction in Kentstown to the R153/N2 Balrath Cross Junction, from 7am on Monday, July 14 to 7pm on Friday, July 25. Diversion routes will be clearly signposted, with local and emergency access maintained at all times. According to Uisce Éireann, this closure will not come into effect until the L1610 Duleek to Balrath Crossroads route has been reopened, ensuring ongoing route availability for local traffic. The works form part of a major infrastructure project aimed at securing a more reliable water supply for Navan. The project includes the construction of a 16km regional trunk water main and a pumping station, creating a strategic link between the Staleen Water Treatment Plant and the Proudstown and Carn Hill reservoirs that serve Navan. Uisce Éireann's William McKnight said: 'This infrastructure will maintain supply in the event of planned or unplanned disruptions at the Liscarton Water Treatment Plant and will support development in an area that has seen unprecedented growth in recent years.' The project is expected to support both residential and economic growth while safeguarding against future service interruptions. A dedicated Community Liaison Officer remains active in the area to keep residents informed about traffic management and construction updates. 'We would like to thank the community for their continued patience and cooperation as we deliver this essential infrastructure for Navan and apologise for any inconvenience these necessary works may cause,' Mr McKnight added. Funded by the Local Democracy Reporting Scheme.