OPW neglected value analysis of €335k bike shed before go-ahead
It found that there was an 'absence of some fundamental good practices' in the OPW, which led to the spending of €335,000 on the bike shelter. The report also found that a proposal by the OPW to locate the bike shelter in front of the 1966 block beside the Members' Dining Hall was discounted after a security review by the Oireachtas and gardaí.
This was despite a bike shelter being used underneath the Agricultural building, which is less than 200 metres from the site of the new bike shelter. The report found: 'On June 21, 2021, a proposal to install a covered bicycle parking shelter with capacity for 36 bikes beside the railings at the western end of the National Gallery was proposed to, and approved by, the Houses of the Oireachtas Commission (HoC) without costs being provided. Bike shelter at Leinster House. Pic: Sasko Lazarov / RollingNews.ie
Throughout this time (December 2019 to June 2021) when options were being proposed to the HoC, the option of doing nothing, as required by the Public Spending Code, was not formally presented to the HoC by the OPW.'
The Deloitte report said: 'A value-for-money assessment was not conducted for the bike shelter project and currently is not standard practice for elective capital expenditure less than €500k.' The report also found that the OPW did not communicate the estimates of the cost to the HoC. 'The estimated cost for the project, prepared in April 2023, was €350,000.
The OPW did not communicate this estimate of costs to the HoC.' While many of the established and good practices were followed, the report added: 'However, our internal audit review has identified the absence of some fundamental good practices in how certain elective capital works (including the bike shelter) below the €500k threshold are being initiated, approved, managed and delivered. Frontage of Leinster House. Pic: Shutterstock
The most fundamental of these control gaps is the absence of a value-for-money assessment which would have allowed informed OPW personnel to evaluate the cost-benefit of building a covered bicycle shelter in the requested location within the Leinster House campus.
'While we understand from our discussions with the OPW that they were primarily focused on delivering to the HoC, the reasons for the costs associated with the bike shelter project should have been documented in a value-formoney assessment which should have been performed within the OPW as part of a robust options appraisal process.
'We understand that some of the reasons for the cost levels included alignment of the bike shelter with the fabric of existing structures and maintaining the important city centre space to a high standard. Bicycle area. Pic: Shutterstock
'Regardless of the reasons, a value-for-money assessment should have been performed and the outcome of this value-formoney assessment (in effect a formal and documented sense check on cost vs benefit) together with lower-cost alternatives, and the option of doing nothing, should then have been presented back to the HoC as part of a robust options appraisal.'
The report added: 'There is currently no governance structure within the OPW for ensuring Value For Money (VFM) assessments are performed for capital projects with a projected budget below €500k.'
Public Accounts Committee member and Social Democrat TD Aidan Farrelly said: It is shocking, but not surprising, that the audit published today by Deloitte confirms there was no value-formoney evaluation carried out on this project, which cost taxpayers a whopping €335,000.'

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Extra.ie
6 days ago
- Extra.ie
€2 a week? – ‘Sweetheart' rent deals set to face probe
Pressure is growing on the Office of Public Works to fully explain why it lets out State-owned properties to retired civil servants, with two Oireachtas committees now set to investigate the issue. last weekend exclusively revealed that current civil servants are living effectively rent-free under a sweetheart deal in secret 'ghost houses' in the Phoenix Park. Today's top videos STORY CONTINUES BELOW There are six residential properties in the Phoenix Park that are managed by the OPW but do not exist on any publicly available official asset register. There are six residential properties in the Phoenix Park that are managed by the OPW but do not exist on any publicly available official asset register. Pic: Google Maps The OPW has refused to confirm what rents the current and former State employees are paying, but overall figures released in 2021 suggest the average rent could be as low as €135 a month. The Department of Agriculture was previously found to be charging €2 a week in rent to a former employee who was living in a cottage owned by the State. A team from the Comptroller and Auditor General discovered the Georgian farmhouse known as 'Stacumny Cottage' during a visit to Backweston in Kildare, where the Department of Agriculture have facilities. The Department of Agriculture was previously found to be charging €2 a week in rent to a former employee who was living in a cottage owned by the State. Pic: File It found the cottage was not recorded on the department's or the OPW's asset register. Aidan Farrelly, a Social Democrats TD who sits on the Public Accounts Committee (PAC), confirmed that he had written to the chair of the committee seeking answers on the matter. Mr Farrelly said: 'It would be my hope that we write to the OPW with a series of questions about these properties.' Public Expenditure Minister Jack Chambers. Pic: Fran Veale The Public Expenditure Minister, Jack Chambers, yesterday also confirmed that Kevin 'Boxer' Moran would appear before the Finance Committee next week on the matter. Mr Chambers is now the third Government figure this week to have no update on the matter. Taoiseach Micheál Martin this week said he was 'unaware' of the reports when he was questioned on the matter by Micheál Martin. Pic: Simon Wohlfahrt/Bloomberg via Getty Images Housing Minister James Browne was asked about the properties yesterday morning but said he had only just become aware of the story. Parliamentary questions in 2017 indicate that Mr Moran is aware of the issue, as he previously served as a minister for state. He said: 'My officials have advised that there are occasions where the properties remain occupied by retired staff and widowed spouses on compassionate grounds. 'Decisions in relation to extended occupancy are made on a case-by-case basis. Duration of occupancy varies from a minimum of three years to life.'


Irish Independent
6 days ago
- Irish Independent
Fields at foot of Rock of Cashel to be transformed into new town park
Phase one of construction is due to begin by the latter end of the summer, which will see a contractor fully on site, and works are expected to take several months. The Cashel Town Park will feature gravel walkway, a scenic boardwalk, reinforced grass paths, natural play elements, sensitive landscaping, seating and signage, a low level maze and an amphitheatre. At the sod turning were elected members of Tipperary-Cahir-Cashel municipal district, Bru Ború, Cashel Heritage and Development Trust, local gardaí, the OPW, chief executive of Tipperary County Council Sinéad Carr, directors of services Brian Beck and Dave Carroll, district officials, project manager and engineer Frank Cussen, while Muintir Na Tire was represented by National President, Jackie Meally. Cashel resident Cllr Burgess told the Irish Independent that the new park is a transformative project for the heritage town and one that has been on his agenda for the past few years ever since he was elected to the council. 'I was delighted back in 2020 in proposing the Part 8 process planning permission to drive this project forward. Last year, we secured €495,000 in additional funding under the Town and Village Renewal Scheme to support this important work. 'We are going to deliver a low-level maze for recreation for kids to play in. We are going to have some organic play material, a new boardwalk improving accessibility in the site. 'But today, in marking the turning of the sod, acknowledges the journey we've been on as a local authority in securing the lands, in driving the new enhancement of the Bishop's Walk, the Bóthar na Marbh, and the Town Wall Walkway at the back of the courthouse. 'All three elements have been delivered already. This main starting point is going to be enjoyed by not just locals, but also visitors. Being under the shadow of the Rock, where hundreds of thousands of visitors are attending every year – the town has always missed that bridge, that connectivity between the Rock and the town centre.' Cllr Burgess said the enhanced town park will act as that bridge. 'It's going to be really transformative for outdoor space in the town. This is a really exciting journey that we're on and I'm delighted as cathaoirleach to be officially turning the sod today.' Cllr Burgess thanked all the council officials who worked on the project over the years, procuring the design, securing planning permission and authorisations from many agencies such as the National Monument Service, the OPW, and the Department of Heritage. ADVERTISEMENT Learn more 'It's quite a sensitive site,' said Cllr Burgess. 'I think that brings a unique aspect to our Town Park that no other town park has. This is going to be something exceptional and it's going to have that outdoor amenity that the town has missed for many years.' The new boardwalk will take some time to install, said Cllr Burgess. 'That accessibility element of the Town Park is really important.' There were many in Cashel who felt the Town Park would never get started, but it is, and when people see the end result, people will appreciate the outdoor space to bring their children, walk their dogs, and enjoy picnics, said Cllr Burgess. The entire project will deliver a new entrance to the Rock of Cashel site on the Camus Road side, at the existing gate. There will be new walkways, and a new amphitheatre which will be of huge benefit to the community. 'I can see the brass band practising there,' said Cllr Burgess. 'I can see Cashel Arts Festival utilising the space in the future, maybe some Irish dancing. It's going to be space for shows and that space for really notable experiences.' Phase one should be completed before Christmas, and, depending on funding, it's hoped that this time next, work will have moved on to phase two. Both phases will be opened separately. The three elements of Bóthar na Marbh, the Bishop's Walk, and the Town Wall Walkway are the three components of the project, with phase one leading from the top gate leading into the Bishop's Walk, down towards the Palace. 'That's going to be delivered in the coming months. That will be open to the public, and that side of the development is really geared towards families. It will be a really welcome addition to the town. 'The design concept respects the sensitivities of the site. It respects the heritage of our town and also provides that unique offering to visitors and locals so I'm really looking forward to it,' added Cllr Burgess.


Irish Times
24-06-2025
- Irish Times
Dispute over boat trips to Skellig Michael resolved, court told
The High Court dispute over boat trips to Skellig Michael has been resolved. Mr Justice Garrett Simons was told on Tuesday that the parties had reached a settlement and a hearing date for the main case in the dispute next month could be vacated. Earlier this month the judge granted an application by the Office of Public Works (OPW) to lift an automatic suspension on landing at the Unesco heritage site and former monastic island which was also used as a film location for the Star Wars films , The Force Awakens and The Last Jedi. It meant boat trips to the island off the Kerry coast could begin for the summer 2025 season immediately. READ MORE Annual landing permits issued by the OPW for mid-May to September were automatically suspended when two unsuccessful bidders for the licences brought a High Court challenge to the decision. The OPW then had to apply to the court asking that the stay be lifted pending hearing of the substantive challenge. The unsuccessful bidders, Atlantic Endeavour Ltd and SMBT Ltd trading as Skellig Michael Boat Trips, disagreed with the OPW interpretation of the legal effect of the automatic suspension. They contended that there are a number of mechanisms open whereby landing permits might legitimately be granted to the successful tenderers for the balance of the 2025 season, while preserving their own right to challenge the allocation of landing permits for the 2026 and subsequent seasons. Mr Justice Simons, following a hearing, ordered the stay be lifted. He said his judgment entailed no finding whatsoever on whether the outcome of the tender process allows the OPW to confine the right to land passengers to the 15 successful tenderers for a five-year period. The proper interpretation of the request for tender and associated documentation, and the legal consequences of the tender process, remain open for debate at the trial of the action, he said. On Tuesday, David Dodd BL, for Atlantic and SMBT, said the matter had been resolved and a hearing date for July could be vacated. He said his clients were very happy with the outcome especially in light of the judge's decision earlier this month. The OPW had agreed to pay his side's costs. The judge struck out the case.