Plans to restart construction of VC Summer reactors gain traction

Plans to restart construction of VC Summer reactors gain traction

Reuters21 hours ago
July 3 - South Carolina's state-owned utility and project owner Santee Cooper has selected 'fewer than five' proposals from 14 received in a request for interest (RFI) to potentially acquire and finish building the reactors, which sit next to Dominion Energy's Summer 1, an active reactor, a Santee Cooper spokesperson told Reuters Events.
The selected entities will now conduct additional due diligence and submit final proposals for Santee Cooper's evaluation.
"We expect to complete this process by the end of 2025. Santee Cooper does not intend to own or operate the units, but rather to enable interested entities to pursue completion and operation of the units for the benefit of all South Carolina," the spokesperson said.
In May, Santee Coooper said it received a 'robust' response to the RFI, with applications from "leading construction, financial, utility, and technology firms from around the world,' and that a detailed review of the proposals would take 9 to 18 months to complete.
When construction of Summer 2 and 3 was cancelled in 2017 due mainly to cost overruns and the bankruptcy of the primary contractor, Westinghouse, over $9 billion had been spent to complete less than 50% of the reactors.
However, in recent years strong demand for clean power from hyperscale data centers and decarbonization efforts has led to new investments to restart mothballed reactors. Holtec International is set to restart the Palisades Nuclear Plant in Michigan later this year and Constellation Energy aims to reopen the Three Mile Island Unit 1 in New York in 2027.
CHART: Growth in commercial sector power consumption by state (2019-2023)
In May, President Trump issued a raft of executive orders to usher in a 'nuclear renaissance' and said the U.S. aims to initiate the construction of 10 new large reactors by 2030. The new policies are part of government efforts to expand U.S. nuclear energy capacity from around 100 GW today to 400 GW by 2050.
Thanks to the advanced stage of construction and existing infrastructure on-site, VC Summer 2 and 3 could be among this batch of new reactors.
Following an inspection in September 2024, the South Carolina Nuclear Advisory Council (SCNAC) concluded that the site was in mostly 'excellent condition,' with unit 2 at approximately 48% completion and unit 3 with 'significantly less' completion.
'There is an extensive inventory of materials, assemblies and electrical and instrumentation systems that is well maintained and inventoried in a series of warehouses,' the council noted.
This assessment suggests that VC Summer 2 and 3 could be "the easiest new large nuclear site" to be completed in the U.S., according to Adam Stein, director of Nuclear Energy Innovation at the Breakthrough Institute.
"A significant amount of work has already been done, many long lead-time components are still on site ready to be used,' he told Reuters Events. 'If you can get around the other challenges such as public perception and state-level government approval, then this is, in terms of large nuclear plants in the U.S., the low-hanging fruit.'
Download exclusive insights from the Reuters Events: SMR & Advanced Reactor 2025 conference in May.
Between 80% and 90% of the hard parts required to complete the project are still in inventory, Santee Cooper's director of Nuclear Development, Steve Nance, said during a SCNAC public meeting on March 31.
After construction of VC Summer 2 and 3 was terminated, Santee Cooper and Westinghouse agreed to sell parts of the AP1000s under construction to other sites overseas, but many components have not yet been delivered.
'These parts are earmarked for Ukraine, which I don't need to tell you, is quite sensitive in terms of how that may ever actually go to fruition or not," Nance told the SCNAC meeting, adding that commercial commitments on those parts expire if they are not withdrawn "by a certain date."
Some long-lead items still available at the site include four circulating pipes, part of the simulator, and most of the transformers needed, according to Nance.
Lessons from Vogtle 3 and 4
Vogtle 3 and 4 in neighboring Georgia were concluded in 2023 and 2024, respectively, approximately seven years after the original estimated completion date, with costs more than doubling from the initial projection of $14 billion.
They were the first U.S. nuclear projects to feature the Westinghouse AP1000 nuclear reactors, the same Generation III+ pressurized water reactors that would be installed in VC Summer 2 and 3.
CHART: US nuclear power capacity additions by year of initial operation
The delays that hampered Vogtle 3 and 4 were in part related to reactor design changes, with around 200 license amendments with the Nuclear Regulatory Commission (NRC) that resulted in construction halts while waiting for reviews and approvals, according to Stein.
But VC Summer 2 and 3 are unlikely to face the same type of delays thanks to the knowledge acquired following the completion of the Vogtle projects.
'Vogtle units 3 and 4 showed that AP1000s can be built. There are a lot of lessons learned that came out of that project that could presumably be leveraged to make sure that future AP1000s go more smoothly and faster and at lower costs,' said Sidney Fowler, energy attorney at Pillsbury Winthrop Shaw Pittman law firm in Washington, DC.
The supply chain and construction expertise developed for the construction of Vogtle 3 and 4 is still available to complete VC Summer 2 and 3, according to Keith Drudy, chief commercial officer at nuclear technology firm Studsvik Scandpower and chair of the Operations and Power Division of the American Nuclear Society.
Strong momentum
A long-term power purchase agreement (PPA) with a hyperscaler – as is the case with Three Mile Island, which signed a 20-year PPA with Microsoft in September – could further strengthen the economics of the project, said Drudy.
"I'd say now will be the time to build additional AP1000s. Every day that we wait, we lose momentum," said Drudy, who has worked for Westinghouse and the Vogtle 3 and 4 projects. "We are in a very good place for a reasonably low-risk large capital project," he added.
For exclusive nuclear insights, sign up to our newsletter.
A May 23 Trump executive order instructing the NRC to accelerate construction and operation permits for new reactors could help ensure that VC Summer 2 and 3 are completed in a timely manner.
"The regulatory case is pretty rock-solid for this one. Some of the things that folks putting together this project would need to keep an eye on is the availability of large components. As long as that is on the schedule, I think it can mimic the work done at Vogtle and speed up through lessons learned," said Katy Huff, associate professor of Nuclear, Plasma, and Radiological Engineering at the University of Illinois at Urbana-Champaign.
The upward trend in electricity prices caused partly by the increase in demand supports nuclear deployment – the Energy Information Administration forecasts a 7% increase in average wholesale electricity prices across most regions in 2025.
'The biggest risk to any nuclear project is a dramatic drop in electricity prices which undercuts the economic case for the project, and right now we are not going in that direction,' Huff said.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

UK's biggest energy supplier is ‘on verge of splitting from tech arm' in £10billion demerger
UK's biggest energy supplier is ‘on verge of splitting from tech arm' in £10billion demerger

The Sun

timean hour ago

  • The Sun

UK's biggest energy supplier is ‘on verge of splitting from tech arm' in £10billion demerger

OCTOPUS Energy Group has sparked a £10 billion pound demerger from tech arm Kraken. The UK's biggest energy supplier is planning to separate from its technology arm Kraken with plans to hire bankers to oversee the deal. It is expected that the demerger will take place in the next year and would see existing investors given shares in the newly independent Kraken firm. A minority stake in Kraken of up to 20% is expected to be sold to external shareholders. One banking source told Sky News that Kraken could be valued at as much as £10.25bn. It has now been revealed that Octopus is looking to hire bankers to oversee the demerger with Citi, Goldman Sachs, JP Morgan and Stanley Morgan invited to pitch for the demerger mandate. Kraken is an operating system which is licensed to other energy providers and water companies. Octopus Energy has around 7.5 million retail customers in Britain and a further 2. million outside the Britain, in January it announced that it was the country's biggest supplier. The firm passed British Gas with a 24% market share. The £10 billion valuation of Kraken would reportedly suggest that the whole group, including the retail supply business was worth around £15 billion. 1

US fiscal folly could create big, beautiful debt spiral
US fiscal folly could create big, beautiful debt spiral

Reuters

time2 hours ago

  • Reuters

US fiscal folly could create big, beautiful debt spiral

LONDON, July 3 (Reuters) - The U.S. tax and spending bill passed on July 3 is expected to add more than $3 trillion to the country's deficit over the next decade. If the current debt trajectory continues unabated, it could set off a slow motion debt spiral that could endanger the Federal Reserve's independence. The sobering long-term debt projections of the Congressional Budget Office, opens new tab may actually understate the likely impact on U.S. debt-to-GDP levels of President Donald Trump's "One Big Beautiful Bill". The CBO based its estimate on the assumption that temporary increases in government spending and tax cuts will sunset at a projected date. But this new budget bill, which extended previous tax cuts and other measures, has shown that this sunset often never arrives. Thus, the long-term projections in the U.S. Treasury's annual financial report, opens new tab may be more realistic since they assume the current rate of government spending will continue indefinitely. In the Treasury forecast, the U.S. debt-to-GDP ratio is projected to increase to over 200% in 2050 compared to the CBO's estimate of around 145%. Scarier still, the Treasury forecasts that the U.S. debt-to-GDP ratio will reach 535% by 2100 if current spending plans continue. Proponents of tax cuts argue that they boost GDP growth and thus will slow the rise in debt-to-GDP, but the CBO estimates that the House Bill will only increase real GDP by an average of 0.5%, opens new tab over 10 years or 0.04% per year relative to the CBO's January 2025 projections. The Tax Foundation estimates that the Senate Bill will boost GDP growth by 1.2%, opens new tab in the 'long run'. That hardly makes a difference compared to an expected debt increase totalling almost 10% of GDP. If today's debt dynamics persist, the risk premiums in the U.S. Treasury market will almost certainly climb over the long run. Economists Martin Ademmer and Jamie Rush, opens new tab have analysed the drivers of 10-year Treasury real yields since 1970. They concluded that investors typically demand more risk compensation as the U.S. deficit increases, especially when there is competition from an ample supply of safe assets globally. Thus, Treasury yields rise. Their analysis concludes that these two factors together lifted the natural 10-year real yield for Treasuries by 1.3 percentage points between 2005 and 2023. If the deficit projections for the next decade are realized, this trend should continue. With all this in mind, it was notable that U.S. Treasury Secretary Scott Bessent said last week, opens new tab that he would not boost long-term Treasury bond sales given today's high interest rates. Since the pandemic, the average duration of U.S. government debt has declined significantly as the Treasury has favoured bills over longer-term instruments in an effort to keep interest expenses under control. One reading of Bessent's comments is that the Treasury is concerned about the country's ability to continue servicing its long-term debts if it borrows at today's elevated yields, a message that could push Treasuries' risk premium even higher, making long-term borrowing even less tenable. This reminds me of a similar episode in which a heavily indebted country faced a sudden spike in its already large deficit. As investors lost trust in the country's ability to pay back its debt, long-term yields rose, which in turn forced the government to issue debt at shorter and shorter maturities. This signalled to the market that the government would struggle to pay the existing debt, and this pushed long-term government bond yields even higher. The country's debt entered a doom loop. The country in question: Greece after the 2009 financial crisis. To be clear, I do not expect the U.S. to experience a similar implosion. There are crucial differences between the U.S. and Greece that should prevent this, not least the ability of the U.S. to devalue the dollar and inflate away some of its debt. Greece, as a euro zone member, had no such flexibility. But the new U.S. budget increases the possibility that the U.S. could face a similar debt drama, only in slow motion. If long-term Treasury yields remain higher for longer, the Treasury is apt to continue shortening the duration of its debt. This, in turn, could create a vicious cycle by making government interest expenses more volatile, further imperiling U.S. fiscal health and making longer-term debt even riskier. There appear to be three main off ramps for the U.S. One: politicians could become fiscally prudent and significantly reduce the deficit to a sustainable level. This seems unlikely given both parties' recent track records. Two: the Treasury could impose capital controls to artificially increase demand for Treasuries. As I have written previously, this move would likely spell the end of the dollar as the main global reserve currency. Three: the Fed could create artificial demand for long-term Treasuries by scooping up bonds itself – that is, restarting quantitative easing – to keep yields low. The danger with this form of QE, however, is that it represents fiscal dominance, where the central bank loses control over monetary policy because of imprudent government actions. How such a development would play out is impossible to predict, especially when it involves a global superpower, but it's fair to assume the Fed won't want to find out. (The views expressed here are those of Joachim Klement, an investment strategist at Panmure Liberum, the UK's largest independent investment bank). Enjoying this column? Check out Reuters Open Interest (ROI),, opens new tab your essential new source for global financial commentary. ROI delivers thought-provoking, data-driven analysis of everything from swap rates to soybeans. Markets are moving faster than ever. ROI, opens new tab can help you keep up. Follow ROI on LinkedIn,, opens new tab and X., opens new tab

Two popular apps loved by millions to shut down forever in DAYS – and you might be owed some cash
Two popular apps loved by millions to shut down forever in DAYS – and you might be owed some cash

The Sun

time4 hours ago

  • The Sun

Two popular apps loved by millions to shut down forever in DAYS – and you might be owed some cash

TWO popular apps used by millions of mobile users are set to shut down next week - and it might mean you're owed some cash. Mobile apps Pocket and Glitch will both close on 8 July. 3 Pocket was removed from app stores in late May, when sales of subscriptions also stopped. But Pocket's Premium subscribers may be owed refunds for the remaining time left on their subscriptions. A subscription for the read-it-later app costs $4.99 per month or $44.99 (£32.99) per year. So if you paid for an annual membership that will not be fulfilled, you should expect some money to be deposited back onto the card you used for payments. Mozilla, which owns the app, said annual subscribers will receive their refunds after 8 July. No action is necessary - just wait for the money to land. It's worth noting that while the app will shut down next week, users will have until 8 October to download their saved data before all Pocket data is permanently deleted. The Glitch app, aimed at web developers, is also handing out refunds to its subscribers. Those who forked out $96 (£70) for an annual Glitch Pro subscription and have paid time left will receive a refund. Users have until the end of the year to download their projects before all the data is wiped for good. Huge Global Data Breach: 16 Billion Accounts at Risk 3

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store