ROAD REPORT: Bids opening July 2 for Adams Co. Schoonover Road project

ROAD REPORT: Bids opening July 2 for Adams Co. Schoonover Road project

Yahoo06-06-2025
Jun. 6—Key points:
* Work starting to ramp up on road projects throughout the region.
* Schoonover Road project in Adams County should start in August.
OTHELLO — Bids will be opened July 2 for the first phase of the rebuilding of Schoonover Road, with construction tentatively scheduled for early August. The first phase is a section about eight miles north of Ritzville; among other things, Schoonover Road connects Ritzville and Odessa.
"This is a reconstruction that is widening (the road), with a new subbase and surfacing with asphalt, drainage facilities and safety rail where needed," said Adams County Engineer Scott Yaeger in an earlier interview.
"We're very excited to get that going," he said Tuesday.
Schoonover Road is a multi-phase project; total cost for the first phase is about $3.13 million.
A project to surface a section of Lind-Hatton Road in Adams County is entering its final phase.
Yeager said guardrails will be installed next week in the project area, about five miles north of State Route 26 between South Damon Road and Phillips Road to the BNSF Railroad tracks. Repaving is scheduled to start June 12, with a second coat applied a week later, Yaeger said.
Total project cost is about $3.12 million.
People traveling on Highway 2 north of Wenatchee will encounter some delays between Leavenworth and Peshastin, beginning Monday.
Traffic signal cameras and pedestrian safety upgrades will be installed at the intersection of Peshashtin's main street and Highway 2. Contractors also will be working on the Wenatchee River bridge on Highway 2 in Leavenworth.
The project is scheduled for a maximum of10 working weekdays, according to a press release from the Washington Department of Transportation. Crews will be working from 7 a.m. to 6 p.m. Monday through Thursday. Crews will be working the night of June 12-13 from 6:30 p.m. to 7 a.m.
Some projects are ongoing, some getting close to conclusion and others continuing throughout the construction season. Crack-sealing is continuing on Moses Lake streets, as well as work on sidewalks and gutters on Westshore Road west of Moses Lake.
A misunderstanding led to some confusion about the Vantage Bridge project, which — as cross-state drivers know — is continuing with one lane open in each direction in June.
Originally the WSDOT announced all four lanes of the bridge would be open in June. Actually, traffic will be restricted to one lane in each direction Monday through Friday throughout the month of June. All lanes will be open on weekends.
Two lanes will be open in each direction over the July 4 weekend, July 3 through 8. But after July 8, the construction schedule shifts, Lott said, and one lane in each direction will be closed through the end of the construction season in November. The exception will be Labor Day weekend, Aug. 28 through Sept. 2, when both lanes will be open in each direction.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Interstate Bridge crash briefly blocks southbound traffic Friday morning
Interstate Bridge crash briefly blocks southbound traffic Friday morning

Yahoo

timea day ago

  • Yahoo

Interstate Bridge crash briefly blocks southbound traffic Friday morning

PORTLAND, Ore. (KOIN) — The southbound side of the Interstate Bridge was blocked for around an hour Friday morning after a crash. According to the Washington Department of Transportation, the crash happened near milepost 0 and blocked all southbound lanes just after 9:45 a.m. Close Thanks for signing up! Watch for us in your inbox. Subscribe Now At around 10:20 a.m. WSDOT said there was a two-mile backup reaching all the way to Exit 2 at 39th Street. Shortly before 11 a.m., the lanes began reopening as the crash was cleared. Officials warn drivers to expect delays and to be patient as traffic moves slowly through the area. Copyright 2025 Nexstar Media, Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed. Solve the daily Crossword

Expect delays: Everett traffic will be jammed by 14-week paving project
Expect delays: Everett traffic will be jammed by 14-week paving project

Yahoo

time2 days ago

  • Yahoo

Expect delays: Everett traffic will be jammed by 14-week paving project

The Washington State Department of Transportation (WSDOT) just announced a prodigious paving project on I-5, starting Saturday, July 19. Work is scheduled mostly evenings and overnight hours, but commuters may see occasional daytime work. No matter how you slice it, commuting through Everett is going to get rough at times during this 14-week project. 'Saturday evening in Everett, the contractors are going to start shutting down up to four left lanes to begin the grinding part of this repavement project,' WSDOT spokesperson Della Kostelnik Juarez said. 'The lanes are going to start shutting down at 7 p.m. (and) reopen at 9 a.m. on Sunday, close again at 7 p.m. Sunday and reopen by 5 a.m. Monday, there will be no work on Monday (evening).' The work starts on southbound I-5 between 41st Street and 100th Street Southeast, near the Everett Mall. Once contractors complete work in the southbound lanes, they will repave the same section in the northbound lanes of I-5. The schedule throughout the 14-week project includes closures: From 7 p.m. Saturday, July 19 to 9 a.m. Sunday, July 20. From 7 p.m. Sunday, July 20 to 5 a.m. Monday, July 21. From 7 p.m. to 5 a.m. nightly Tuesday, July 22 to Friday morning, July 25. WSDOT will inform us if there are any changes. The Broadway HOV on-ramp to southbound I-5 will also close during the roadwork, but the general purpose on-ramp from Broadway will remain open. Some of this work needs dry weather and may need to be rescheduled. The Everett pavement project will repave 4 miles on I-5 This pavement repair project will repave approximately 4 miles of southbound I-5 in Everett and is expected to finish later this fall. Motorcyclists should watch for grooved, uneven pavement and use extreme caution. 'We really encourage people to look at our travel page and look at our travel map to see what is going to be open and closed,' Juarez added. Solve the daily Crossword

SR 14, SR 142 closures snarls travel in Columbia River Gorge as Burdoin Fire burns nearby
SR 14, SR 142 closures snarls travel in Columbia River Gorge as Burdoin Fire burns nearby

Yahoo

time2 days ago

  • Yahoo

SR 14, SR 142 closures snarls travel in Columbia River Gorge as Burdoin Fire burns nearby

SR 14 and SR 142 remain closed in Klickitat County due to the Burdoin Fire, which started Friday, July 18, according to the Washington State Department of Transportation. As of Friday evening, SR 14 is closed in both directions between milepost 66 near Bingen and milepost 75.8 near the junction with SR 142. WSDOT described the closure as 'extended' and said there is currently no estimated time for reopening. SR 142 is also closed in both directions from milepost 1 near Klickitat County Park to milepost 4 near Knight Creek. Drivers are urged to avoid the area and seek alternate routes. Eastbound traffic may detour via the Hood River Bridge. Westbound travelers are being directed to use either the US 97 Sam Hill Memorial Bridge or the US 197 Dalles Bridge. However, WSDOT warned that US 197 is closed to commercial vehicles and any vehicles over 10,000 gross vehicle weight (GVW) between milepost 0 near the Oregon State Line and milepost 3.1 near SR 14. No additional details about the fire were immediately available. Solve the daily Crossword

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store