Second phase waste-to-energy plant at Jawaharnagar to begin in August, GHMC tells NGT

Second phase waste-to-energy plant at Jawaharnagar to begin in August, GHMC tells NGT

Time of India16-06-2025
Hyderabad: The Greater Hyderabad Municipal Corporation has informed the National Green Tribunal, southern zone, that the second phase of the waste-to-energy (WtE) plant at Jawaharnagar, with a capacity of 24 MW, is expected to commence operations in the first week of Aug.
In an affidavit submitted by
GHMC
commissioner RV Karnan, it was stated that a power purchase agreement was signed on May 12 between Hyderabad MSW Energy Solutions Private Ltd and the Southern Power Distribution Company of Telangana Limited (TGSPDCL). The agreement is currently awaiting approval from the Telangana Electricity Regulatory Commission.
The boilers department has granted permission to operate both boilers following successful hydro tests.
Steam blowout tests are scheduled for the third week of July, signaling that mechanical systems are on track for commissioning.
The tariff for the energy generated will be determined by TGERC under section 62 of the Electricity Act, 2003. It will include considerations such as the tipping fee, with interim arrangements possibly sought through a separate petition. Any govt incentives availed by the operator must be passed on to the discom in line with TGERC directives.
The affidavit clarified that no transmission, wheeling, or additional charges will be imposed by TGTransco or the discom for energy purchased. The plant can draw power from the grid only during shutdowns or maintenance, limited to auxiliary consumption (11% of installed capacity).
Status of other WtE projects
The GHMC is also progressing on other WtE plants. A revised NOC was issued on June 9 to Sri Venkateshwara Green Power Projects Ltd, enhancing the Yacharam plant's capacity from 12 MW to 14 MW.
GHMC has requested TGSPDCL to initiate a PPA. This project is expected to be commissioned by Dec 2026.
Meanwhile, the stalled Bibinagar project—idle since 2017–18 due to IL&FS's financial troubles—is under review for possible revival.
The affidavit was submitted in response to a petition filed by Shankar Narayanan Bala Krishnan and others on waste management and environmental compliance.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Telangana HC halts action on Khajaguda property until owners hearing
Telangana HC halts action on Khajaguda property until owners hearing

Time of India

time2 days ago

  • Time of India

Telangana HC halts action on Khajaguda property until owners hearing

Representative Image HYDERABAD: The Telangana high court has restrained the Greater Hyderabad Municipal Corporation (GHMC) from taking any coercive action against Abubakar Bin Mohammed and Omer Bin Mohammed - owners of a property affected by the proposed multi-level flyover at Khajaguda Junction - until they are granted a hearing. Justice NV Shravan Kumar granted interim relief while disposing of a petition challenging the acquisition of additional land under the Hyderabad City Innovative and Transformative Infrastructure (H-CITI) project. The petitioners said their family had already surrendered 1011 square yards for road widening in 2008, after which GHMC granted them permission to construct a multi-storey building in the remaining land. You Can Also Check: Hyderabad AQI | Weather in Hyderabad | Bank Holidays in Hyderabad | Public Holidays in Hyderabad However, the remaining 219 square yards are now part of the proposed alignment for the flyover, prompting fresh acquisition efforts, they said. The GHMC, in a June 2025 order, asked them to hand over possession of the land and promised structure compensation, according to the petitioners. They claimed that although they submitted a representation to GHMC on Jan 23, 2024, they received no response until they were asked to accept the acquisition and compensation, including Transferable Development Rights (TDR). by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like An engineer reveals: One simple trick to get internet without a subscription Techno Mag Learn More Undo GHMC's counsel told the court that objections to the acquisition could be filed until July 31, 2025, and assured that the petitioners' concerns would be duly considered. The court directed GHMC to resolve the representation within four weeks after giving the petitioners a fair hearing, and barred any coercive steps during this period.

Anti-Corruption Bureau probes solar plant linked to Telangana ex-irrigation chief's son in disproportionate assets case
Anti-Corruption Bureau probes solar plant linked to Telangana ex-irrigation chief's son in disproportionate assets case

Time of India

time4 days ago

  • Time of India

Anti-Corruption Bureau probes solar plant linked to Telangana ex-irrigation chief's son in disproportionate assets case

Hyderabad: Former engineer-in-chief of the irrigation department, C Muralidhar Rao, was remanded in judicial custody and shifted to Cherlapally Central Prison on Wednesday in connection with a disproportionate assets (DA) case. The Anti Corruption Bureau (ACB), which arrested Rao on Tuesday, is now scrutinising a wide trail of documents, property transactions, and financial records linked to the case. One major focus of the investigation is a 2 MW solar power plant in Zaheerabad, operated by a Jubilee Hills-based private company where Rao's son is listed as a director. The firm, incorporated in 2016 and located on Road No. 92, had entered into a 20-year power purchase agreement with TGSPDCL starting April 2017. You Can Also Check: Hyderabad AQI | Weather in Hyderabad | Bank Holidays in Hyderabad | Public Holidays in Hyderabad According to ACB officials, the company secured a ₹10 crore loan for the plant and cleared it by 2021, while paying ₹5 lakh quarterly as maintenance charges. 'When our team visited the registered company address, a different renewable energy firm was operating from the premises since 2016,' an ACB official said, adding that further verification is underway. ACB has also identified three unopened bank lockers tied to Rao and his family. Officials plan to move a custody petition after examining the seized material in detail. During Tuesday's statewide raids on 12 locations connected to Rao and his family members, the ACB unearthed assets valued in hundreds of crores, including multiple villas, flats, and plots in Hyderabad, 11 acres of agricultural land in Warangal and Shabad, 12 acres in Zaheerabad, three acres of plotted land in Mominpet, and a 6,500 square yard plot in Mokila. Officials also seized a Mercedes Benz car, 30 tolas of gold, and incriminating documents.

SC rules in favour of Himachal in power dispute with JSW Hydro Energy
SC rules in favour of Himachal in power dispute with JSW Hydro Energy

Business Standard

time4 days ago

  • Business Standard

SC rules in favour of Himachal in power dispute with JSW Hydro Energy

The Supreme Court on Wednesday ruled against JSW Hydro Energy, a subsidiary of JSW Energy, in its dispute with the Himachal Pradesh government over the supply of 18 per cent free power to the state. JSW Hydro Energy had argued that, under the Central Electricity Regulatory Commission (CERC) Tariff Regulations, it was required to supply no more than 13 per cent as free power. 'We have allowed the appeal by the State of Himachal Pradesh by interpreting the provisions of the Electricity Act, 2003 and the CERC Regulations, 2019 in the context of the subsisting and continuing contractual relationship between the parties,' said a Bench of Justices P S Narasimha and Joymalya Bagchi. The Bench held that the CERC Regulations, 2019, did not prohibit the company from supplying free power beyond 13 per cent and that the Implementation Agreement remained valid and enforceable. While CERC must give effect to its regulations and allow a pass-through of up to 13 per cent free power in tariff calculation, any additional supply is a contractual obligation governed by the Implementation Agreement. On interpreting the CERC Regulations, the court stated that the 13 per cent limit applies only for tariff purposes and does not prevent the company from supplying more than that amount of free power. 'Further, a writ petition before the High Court for aligning the Implementation Agreement with the CERC Regulations, 2019, and the CERC's order dated 17.03.2022 is not maintainable,' the court held. In allowing the state's appeal, the Supreme Court criticised the High Court for intervening in the tariff fixation domain, which falls within the exclusive jurisdiction of the CERC. 'Considering the expertise and specialisation of the CERC as a statutory regulator and the wide-ranging jurisdiction it exercises under the Electricity Act, as well as Respondent No. 1's (JSW Hydro Energy) conduct in not seeking relief against the appellant (State of Himachal Pradesh) before the CERC, we have held that the present writ petition was not maintainable before the High Court,' the Bench added. JSW Hydro Energy Limited operates a 1,045 MW hydroelectric project at Karcham Wangtoo, originally allotted to Jaiprakash Industries Limited under a Memorandum of Understanding signed in 1993. Under the subsequent Implementation Agreement with the Himachal Pradesh government, JSW (through its predecessor) had agreed to provide 18 per cent of net power generation to the state free of cost after the first 12 years of commercial operation. Later, JSW approached the CERC and then the High Court when the state declined to revise the free power obligation to 13 per cent in line with the 2019 regulations. The High Court had ruled in favour of JSW and directed the state to align the Implementation Agreement with the CERC Regulations. The Supreme Court has now overturned that ruling.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store