'Not even': New $5.6m Rolleston intersection to be repaired
Levelling work needed to be completed on the major Canterbury intersection, between Levi Road and Masefield Drive.
The Selwyn District Council issued a statement on May 6 via social media that it was "aware of the uneven surface(s) on Levi Road" and that contractors would be working on levelling the surface as soon as they can.
Council infrastructure and property executive director Tim Mason said the road was built to design, and there were no structural issues.
"The ride quality at the two entrances to the supermarket development along Levi Road that motorists are experiencing is a temporary issue.
"There are no safety concerns relating to this minor issue and currently a 30km/h temporary speed limit is in place as a precautionary measure.'
The issue was identified during the April 4-6 "super weekend" when the contractors, Isaac Construction, worked a straight 84 hours to install the traffic lights and complete the final roading, piping, electrical work, he said.
"Since then, the council, design consultants, and the contractor have been working on the final stage of design for remediation for the ride quality.
"We expect to have this completed by the end of May.
"We are currently working with our contractor and design consultants to prioritise remediation, while also confirming responsibility for costs as part of that process."
This issue was not caused by last week's heavy rain, but the bad weather delayed the remediation work, he said.
'We can confirm that the drainage around the intersection is working effectively and was not impacted by the recent weather event."
The intersection is a main arterial route linking traffic in and out of Rolleston to the Christchurch Southern Motorway.
The finishing touches, such as road markings, had been scheduled to be completed by the end of April. However, this was only partially completed due to the bad weather conditions in the last two weeks, Mason said.
Isaac Construction have been approached for comment.
The intersection upgrade was originally included in the council's 2021–31 long-term plan, ahead of Foodstuffs South Island announcing their development plans.
Foodstuffs was building the South Island's largest Pak'nSave, covering 8100 square meters, on the corner of Levi Road and Lincoln Rolleston Road.
It was scheduled to open by the end of the year.
It's understood that development contributions from the new supermarket will have offset some of the $5.6m cost, as well as a NZ Transport Agency subsidy.
LDR is local body journalism co-funded by RNZ and NZ On Air

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Scoop
16-07-2025
- Scoop
‘No Excuse For Speeding': New Limits Aim To Protect School Children
Cars speeding by the school in the Hawke's Bay village of Bridge Pā may not be such a big problem in future. Bridge Pā school principal Vanessa Sadler says cars coming along Maraekākaho Rd are asked to reduced speed from a 100km/h limit only 200m before the school gates. 'It's not much time to slow down and a lot of cars are travelling at more than 50km/h when they get to the school,' Sadler said. But now, about halfway between the 50km/h sign and the school, is a new 30km/h limit. This after Hastings District Council began its early rollout of lower vehicle speed limits outside schools. Hastings District Council Mayor Sandra Hazlehurst said the early adoption of the lower speed limits reflected the Council's strong commitment to improving safety outcomes for tamariki, whānau, and the wider community. 'We're taking a proactive step to protect our children and show leadership in road safety,' Hazlehurst said. Sadler says she is happy with the move. 'Speeding cars are a problem for us. In fact, sometimes there are police cars waiting in our car park for them. 'We have had many close calls with our tamariki and I've tried numerous times to get a school crossing, but we are on a state highway.' She said the signage was impressive. 'It's very visible. You can't miss them, so there is no excuse for speeding,' Sadler said. Hazlehurst said by rolling out variable speed limits before schedule, the council was ensuring safer journeys to and from school for everyone. The lower vehicle speed limits outside schools align the district with the Government's new Setting of Speed Limits Rule 2024. Over the next three months, all schools across Hastings will move to variable speed limits, operating during defined school travel periods during school terms. These periods typically cover 45 minutes before and after school, but up to an hour in areas where multiple schools are located nearby. Bridge Pā, Maraekākaho, Puketapu, Te Pōhue, and Waimārama schools are the first to have the new variable speed limits in place from July 14. The council's goal is to have the school speed limits operating at all Hastings schools by mid-September. The changes apply to both urban and rural schools and adhere to national rules that define school zone extents and classification criteria. Unlike the previous permanent speed zones, the new approach uses variable signs that are only active during designated school travel periods, improving clarity and consistency for drivers. All electronic signs have been purchased, with NZ Transport Agency Waka Kotahi support. Additional funding has been sought from NZTA to help with the installation of static variable signs.


Scoop
14-07-2025
- Scoop
Council Confirms City Centre Parking Changes
Tauranga City Council has confirmed the next phase of the City Centre Parking Management Plan, aiming to improve access to short-stay parking and balance demand across the city centre and city fringe. Council staff regularly monitor the demand for parking to ensure a balanced mix of options for residents, workers, shoppers, and visitors. Demand in the city centre and city fringe has increased significantly, and council receives ongoing feedback from residents about limited on-street parking availability. From Monday, 4 August 2025, paid on-street parking will be introduced around the city fringe, including Third Avenue, Fourth Avenue, Glasgow Street, Selwyn Street, McLean Street, Monmouth Street, Park Street, Cameron Road, Anson Street, and Dive Crescent. Existing paid parking will also be extended along sections of First Avenue, Second Avenue, Willow Street, and Devonport Road. The cost of parking in the extended area is $1 per hour for the first two hours, $2 for each additional hour, and a maximum charge of $10. Payment can be made at parking machines which will be installed in the area, or via the PayMyPark app. Concurrently, P120 time-limited car parking will be introduced along some sections of Cliff Road, Brown Street, Arundel Street, Fourth Avenue, Fifth Avenue, Sixth Avenue, Seventh Avenue, Eighth Avenue, Sheath Street, and Edgecumbe Road. Also, from Monday, 4 August, off-street parking prices in the city centre will be adjusted to better reflect demand. This includes a lower all day rate for the Elizabeth Street parking building to attract long-stay users and free up more convenient on-street spaces for short visits. Te Papa Ward Councillor Rod Taylor says that pressure on city centre parking will continue to increase. "It's important we take a proactive approach and act now, so that everyone in our community can get a park when they need it. 'While staff recommended introducing a resident parking permit to help ease the impact on those living in affected areas, Council ultimately voted against this option after considering a range of views. 'It may not be obvious, but there are now more carparks in the city centre than ever, including before The Strand carpark was removed. We have upgraded the Dive Crescent carpark, created additional spaces at the Spring Street building, and opened a new public parking facility at Haumaru on Cameron Road. These carparks remain free on weekends, public holidays, and after 5pm on weekdays.' With the upcoming changes, city centre workers are encouraged to use the parking buildings, long-term off-street carparks, public transport, or active travel like cycling and walking. Mount Maunganui also faces parking challenges, with Council first exploring the development of a Mount Maunganui Parking Management Plan in 2023 in response to community feedback. Following several deferrals of this work due to community concerns, Council is now revisiting the plan and is currently engaging with residents, businesses, and visitors to find out what's working, what's not, and what could work better - whether it's tried and tested solutions seen elsewhere, or out-of-the-box ideas. Community feedback for Mount Maunganui is now open at and will close on Friday, 25 July 2025.

1News
03-07-2025
- 1News
Frustration grows over Auckland road works 'mess'
Motorists are fed up with road works on a south Auckland road, which are expected to drag on for almost two years due to delays. The Paerata Rd culvert upgrade in Pukekohe started in April 2024 and was to be completed this Spring, but will now finish in February 2026. Auckland Council was upgrading the stormwater culvert on the southern end of Paerata Rd, after extreme weather and Cyclone Gabrielle caused severe flooding to nearby properties in 2023. Resident John Lewis said there seems to be no end in sight for the roadworks. "I know it has to be done and I'm all for improving infrastructure but for someone who frequents the road, it's been really annoying that it's taken this long," Lewis said. ADVERTISEMENT Pukekohe resident Marama Ratu said traffic was a mess and the potholes didn't help either. "They've [potholes] just gotten worse," she said. "It's already slow going through there, then we have to swerve to avoid these huge potholes that just keeps getting bigger... it's a mess." The project will be completed in February 2025. (Source: Local Democracy Reporting) She said she understood why the project was important, but questioned its delay. "They're saying its going to be completed next year, that's almost two years of this spectacle. Surely, they could complete it sooner?" Delays blamed on traffic-friendly approach ADVERTISEMENT Council said the reason for the delay was because they chose the most traffic-friendly construction approach, which means constructing the bridge in two halves. According to council, 17,000 vehicles cross the culvert everyday. Council's principal delivery of special projects, Leighton Gillespie, said the bridge was being constructed in halves to keep the roads open. "But, [it] ensures continued access for all road users," Gillespie said. He said they opted for the most traffic-friendly construction approach for the project. "While this means extending the overall programme duration, it allows us to maintain uninterrupted two-lane traffic flow throughout the works. "This decision was made to minimise disruption for the community and local businesses by avoiding full road closures or stop/go traffic control." ADVERTISEMENT Gillespie said they also encountered some unforeseen utility services that required relocation and coordination, which have contributed to delays in the programme. "These challenges have now been resolved, but the associated impacts on time remain." Council's upgrade of the stormwater culvert on the southern end of Paerata Road meant replacing the existing 1.8m x 1.8m box culvert with a 12-metre-long bridge across Whangapouri Creek. "Fortunately, we have been able to progress downstream works while approvals were being finalised, helping to maintain overall momentum. "We've received relatively few complaints about traffic to date, and we continue to adapt our traffic management in response to the needs of businesses and the wider community.' Gillespie said the work was important to help future-proof the stormwater network by reducing the frequency of flooding upstream, and the risk of the culvert overflowing. "We will also be completing erosion protection and securing downstream slopes." It was all part of wider stormwater upgrades in the area, to reduce flooding and support future growth, he said. LDR is local body journalism co-funded by RNZ and NZ On Air.