
Eskom bets big on renewables with new ‘green' subsidiary
In a presentation to Parliament's portfolio committee on energy and electricity, Eskom shared more details about its strategy to be a player in the renewable energy sector.
The utility's executive was briefing members on their strategic corporate plan for 2025-2030, their shareholder compact for 2025-2026 and budget for 2025-2026.
Eskom board chairperson Mteto Nyati explained that one of the utility's four strategic objectives was to 'facilitate a competitive future energy industry'. As part of this, Eskom aims to significantly increase its renewable energy portfolio, committing to around 5.90GW of clean energy projects by 2030. A part of this objective includes the accelerated establishment of Eskom Green Co, the company's renewable energy business.
Eskom Green will be one of the four unbundled entities that will fall under the Eskom holding company. The other companies are National Transmission Company of South Africa, which is already a legal entity, National Electricity Distribution Company of South Africa and Eskom Generation, which are due to be legally separated next.
'We have embraced, as Eskom, the renewables agenda,' said Nyati. 'In the past, our strategy involved only us managing the current fleet and not participating in new generation capacity.
'That has changed. We are going to be participating in renewables in a big way, and we have already started to operationalise a business unit that makes us to be a relevant player within the space.'
Almost two weeks ago, Eskom issued an invitation to tender for 'firms with a proven track record in establishing renewable energy businesses' to help it start this process. It said the objective of Eskom Green Co would be to 'operate independently of the main Eskom entity to allow for greater governance agility, competitive market positioning and enhanced Public-Private Partnerships (PPPs)'.
Eskom, in a statement, said it had an 'executable initial pipeline' of at least 2GW of low and zero-carbon energy projects by 2026 and had developed a pipeline of more than 20GW of low and zero-carbon energy projects to diversify its energy mix. It plans to 'realise' roughly 5.9GW of renewable energy projects by the end of this decade.
At Friday's meeting, DA MP Kevin Mileham asked for more information about the proposed new entity.
'Why are we breaking out a new entity when it's clearly part of generation? It's a division of generation. It's not a new entity. I mean, nuclear is not an entity by itself. Coal is not an entity by itself. Why is Green Co or Eskom Green a new entity? Why is it going to have its own board of directors? Why is it going to have its own finance team? Why is it going to have its own legal team and HR team, and things like that?
'Aren't we just duplicating already existing personnel capacity infrastructure and therefore increasing our costs?'
In response, Eskom CEO Dan Marokane explained that the unbundling was an operationally motivated decision.
'I want to address the issue that deals with the structure of Eskom going forward, as to why are we having a separate green entity, why is it not within generation?'
'These are all aspects that are operational, that deal with how we bring into reality the strategic intent that we have. Our strategic intent is to unbundle to set up separate entities that will be efficient in their part of the value chain,' said Marokane.
The new green generation part of Eskom's business, he explained, 'is an entity that is required to enable us to unbundle the generation business in a manner that does not make us run the risk of losing all the licences. These are operational matters about structuring and how to set up these transactions in a manner that allows the realisation of the objectives.
'The renewables business is going to be a different business in terms of thinking. It will involve partnerships so that Eskom's balance sheet is not the only one that is exposed. We can't afford to go to the previous levels of debt. So we'll do business as a transaction with others, with their money, on our land, with our people, using our skills and choosing to de-risk those projects because it will be in a competitive world.
'So how it's structured needs to enable that kind of a setup in line with the mandates that we're seeking to have.' DM

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Citizen
8 hours ago
- The Citizen
Eskom clarifies R1b Koeberg payment after court battle with French contractor
Eskom has confirmed that two contractual disputes with Koeberg Nuclear Power Station contractor Framatome are being addressed through an agreed resolution process. This follows media reports that the French energy company won a high court order instructing the power utility to pay about R1b to the company after contractual issues. Framatome was contracted for the Steam Generator Replacement Project at the nuclear power station in the Western Cape. 'In accordance with the contract, disputes are first referred to adjudication and, if not resolved, to arbitration. 'Two disputes were adjudicated between December 2022 and February 2023. As Eskom was not satisfied with the adjudicator's decisions, the two matters were escalated to arbitration as per the agreed process. The arbitration was held from June to July 2025, and a decision is expected in the last quarter of Eskom's financial year. 'Recent media reports appear to have mixed separate legal processes. To clarify, no new payments are currently due, and all actions taken by Eskom have been in line with the applicable legal and contractual procedures,' the power utility said in a statement yesterday. Eskom added that although it 'disagreed with the adjudicator's decisions', it complied with the outcomes and made payments. 'All payments had been made by March 2024 as part of standard contract processes – not as penalties or fines,' the utility said. Simultaneously, Eskom approached the courts. 'Eskom approached the Cape High Court to have the adjudicator's decisions set aside due to procedural irregularities (independent of the merits of the decisions). The court only delivered its judgment on July 17, 2025, over a year late. Eskom is currently reviewing the judgment to determine the appropriate next steps. 'We encourage the public and media to trust the integrity of this process. Eskom is following the proper legal channels to resolve these matters responsibly, and we remain committed to transparency and accountability throughout. 'Most importantly, despite these disputes, the core technical work – replacing the steam generators on Koeberg Unit 2 – has been completed. This is a major milestone that contributes to the safe and extended operation of the power station, helping to ensure energy security for the country,' Eskom said. – Read original story on At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!


The Citizen
15 hours ago
- The Citizen
No fines or penalties over Koeberg delays, Eskom says
The two disputes stem from the Steam Generator Replacement Project of Unit 2 at Koeberg Nuclear Power Station. Eskom has sought to clarify that two contractual disputes with Framatome, the contractor for the Steam Generator Replacement Project at the Koeberg nuclear power station, are being addressed through agreed resolution processes. The two disputes stem from the Steam Generator Replacement Project of Unit 2 at Koeberg Nuclear Power Station, which has now seen significant progress, following problems that contributed to a bout of stage 3 load shedding in March. Steam generators Framatome had taken over the contract to supply and install replacement generators at the power plant's two reactor buildings from Areva NP in 2018. The recent Long-Term Operation (LTO) programme for Unit 2 included the replacement of three steam generators, extensive inspections, and refuelling activities, ensuring continued safe and efficient performance. ALSO READ: Koeberg Unit 2 back online, but what caused the 'unplanned' trip? Eskom needed to replace the plant's six steam generators – three in each of its two units – to prolong its life by another 20 years. Media reports Eskom issued a statement on 21 July, following media reports, that the utility had been ordered by the high court to pay more than R1 Billion to Framatome over delays to the Steam Generator Replacement Project at Koeberg. According to reports, the Western Cape High Court agreed with the findings of an adjudicator who investigated the delays two and a half years ago, ruling that Eskom was at fault for the stoppage of work and had to pay for breaching its contract. Disputes The utility's spokesperson, Daphne Mokwena, said the two disputes were adjudicated between December 2022 and February 2023. Mokwena said in accordance with the contract, disputes are first referred to adjudication and, if not resolved, to arbitration. 'As Eskom was not satisfied with the adjudicator's decisions, the two matters were escalated to arbitration as per the agreed process. The arbitration was held from June to July 2025, and a decision is expected in the last quarter of Eskom's financial year. ALSO READ: Load shedding: Hiccup in Eskom's power plans 'Recent media reports appear to have mixed separate legal processes. To clarify, no new payments are currently due, and all actions taken by Eskom have been in line with the applicable legal and contractual procedures,' Mokwena said. Disagreement Mokwena added that although Eskom disagreed with the adjudicator's decisions, the utility complied with the requirement to implement the outcome and made payments in the interim. 'All payments had been made by March 2024 as part of standard contract processes—not as penalties or fines. At the same time, in March 2023, Eskom approached the Cape High Court to have the adjudicator's decisions set aside due to procedural irregularities.' Mokwena said the court only delivered its judgment on 17 July 2025, over a year late. 'Eskom is currently reviewing the judgment to determine the appropriate next steps. We encourage the public and media to trust the integrity of this process. Eskom is following the proper legal channels to resolve these matters responsibly, and we remain committed to transparency and accountability throughout. 'Most importantly, despite these disputes, the core technical work, replacing the steam generators on Koeberg Unit 2, has been completed. This is a major milestone that contributes to the safe and extended operation of the power station, helping to ensure energy security for the country,' Mkowena said. Eskom stated that it anticipates a decision on the arbitration hearing in the last quarter of its financial year. Koeberg Koeberg's units 1 and 2 have undergone life extension exercises. In July last year, the National Nuclear Regulator (NNR) granted Eskom a licence to continue operating Koeberg Nuclear Power Station Unit 1 until 21 July 2044. As a result, Koeberg Unit 1 is expected to contribute over 930MW to the grid for another 20 years,' Mokwena said. ALSO READ: Eskom takes action after breach of online vending system

IOL News
a day ago
- IOL News
Brian Molefe's ongoing legal battle over R32m Eskom pension fund payout
MK Party MP and former Eskom chief executive Brian Molefe. Image: Jacques Naude / Independent Newspapers Former Eskom chief executive Brian Molefe will continue his fight against the power utility's pension and provident fund over the millions of rand he received in a payout in 2017. In 2018, the DA, trade union Solidarity, and the EFF obtained a Gauteng High Court, Pretoria, order reviewing and setting aside Molefe's reappointment as Eskom boss as well as the proposal granting him early retirement. At the time, the full bench of the high court – Judges Keoagile Matojane, Hans Fabricius, and Segopotje Mphahlele – also declared any payment or sum of money received by Molefe under any purported agreement between him and Eskom invalid and ordered him to repay the amounts within 10 days. Molefe unsuccessfully applied for leave to appeal to both the Supreme Court of Appeal and the Constitutional Court. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Ad loading In their scathing ruling, the judges found Eskom's decision to waive penalties and buy Molefe an extra 13 years of service totalling R30.1 million after only 15 months' service at the age of 50 stretched incredulity and was unlawful for want of compliance with the Eskom Pension and Provident Fund's (EPPF's) rules. 'What is most disturbing is the total lack of dignity and shame by people in leadership positions who abuse public funds with naked greed for their benefit without a moment's consideration of the circumstances of fellow citizens who live in absolute squalor throughout the country with no basic services,' the high court reasoned. In July 2022, the EPPF was later directed by Judge Norman Davis to repay Eskom the R32.3m payout, including employer contributions, Molefe's monthly pension contributions, and his performance bonus pension contributions. Molefe was ordered to repay the fund about R10m together with mora interest, which is charged when payment is not made. The former Transnet chief executive has maintained that based on his calculations, the net amount that he has to repay is just less than R1.5m. The EPPF then became entitled to set-off against the amount due by Molefe against the net balance of the Transnet Retirement Fund lump sum he received upon receipt of a tax directive from the SA Revenue Service (Sars) on the tax payable on the amount. Molefe appealed the July 2022 judgment, and on July 11, 2025, another full bench of the high court – Judges Ronel Tolmay, Mmonoa Teffo and Rochelle Francis-Subbiah – upheld his challenge. Parts of Judge Davis' order were set aside and substituted. 'The matter is referred to oral evidence to determine the amount payable by the appellant (Molefe) to the first respondent (EPPF), before a different judge. 'The first respondent must discover all documents relating to the calculation and flow of money as well as all documents it intends to use during the leading of evidence within 15 days of this order,' the court ruled. Additionally, according to the judgment, Molefe must discover all documents relating to the calculation and flow of money and all documents he intends to use during the leading of evidence within 15 days of the filing of his documents. The judges continued: 'The judges stated that actuaries may file supplementary reports after receiving the aforementioned documents, and must do so at least 45 days before the matter is heard.' Molefe did not respond to requests for comment on Tuesday.