NTPC Green Energy share price edges higher despite weak bias in Indian stock market; here's why

NTPC Green Energy share price edges higher despite weak bias in Indian stock market; here's why

Mint2 days ago
NTPC Green Energy share price rose less than a per cent in Monday's trading session despite weak market sentiments on June 30. The stock opened at ₹ 107.21 apiece on Monday, as compared to previous close of ₹ 105.93.
NTPC Green shares have witnessed significant fall over 12 per cent in last one year and nearly 17 per cent in six months.
NTPC Green Energy shares gained after the company said that it has successfully commissioned third and last part capacity of 120 MW out of 220 MW Shajapur Solar Project (Unit-II) of NTPC Renewable Energy Limited.
' We wish to inform you that consequent upon successful commissioning, third and last part capacity of 120 MW out of 220 MW Shajapur Solar Project (Unit-II) of NTPC Renewable Energy Limited, a wholly owned subsidiary of NTPC Green Energy Limited at Shajapur, M.P, is declared on Commercial Operation w.e.f. 00:00 Hrs. of 29.06.2025,' the company said in an exchange filing dated June 28.
On June 27, the company had informed the exchanges of successful commissioning of the first part capacity of 142.2 MW out of 300 MW Khavda Solar Energy Project of NTPC Renewable Energy Limited and the second part capacity of 146.7 MW out of 1255 MW Khavda-I Solar PV Project of NTPC Renewable Energy Limited.
' We wish to inform you that consequent upon successful commissioning: the first part capacity of 142.2 MW out of 300 MW Khavda Solar Energy Project of NTPC Renewable Energy Limited, a wholly owned subsidiary of NTPC Green Energy Limited at Khavda, Bhuj, Gujarat, under 450 MW Hybrid Tranche V Project is declared on Commercial Operation w.e.f. 00:00 Hrs of 28.06.2025 and the second part capacity of 146.7 MW out of 1255 MW Khavda-I Solar PV Project of NTPC Renewable Energy Limited, a wholly owned subsidiary of NTPC Green Energy Limited in Gujarat under CPSU scheme Phase-II Tranche-III, is declared on Commercial Operation w.e.f. 00:00 Hrs of 28.06.2025,' it said in the filing.
Disclaimer: This story is for educational purposes only. The views and recommendations above are those of individual analysts or broking companies, not Mint. We advise investors to check with certified experts before making any investment decisions.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

NTPC REL adds 97.5 MW capacity at Khavda solar projects in Gujarat
NTPC REL adds 97.5 MW capacity at Khavda solar projects in Gujarat

Time of India

timea day ago

  • Time of India

NTPC REL adds 97.5 MW capacity at Khavda solar projects in Gujarat

New Delhi: NTPC Renewable Energy Limited (NTPC REL), a wholly owned subsidiary of NTPC Green Energy Limited , has declared commercial operation of a total of 97.5 MW additional solar capacity across two projects in Khavda, Gujarat, from 00:00 hours on June 30, 2025. According to an official release, a 32.8 MW capacity (Second Part) of the 300 MW Khavda Solar Energy Project under the 450 MW Hybrid Tranche-V scheme was declared commercially operational. The First Part of this project, comprising 142.2 MW, was made operational on June 28, 2025. Simultaneously, NTPC REL commissioned 64.7 MW capacity (Third Part) of the 1255 MW Khavda-I Solar PV Project, being developed under the CPSU Scheme Phase-II, Tranche-III. The First and Second Parts of 110.25 MW and 146.7 MW, respectively, were declared commercially operational earlier on June 6 and June 28, 2025. The projects are part of NTPC REL's solar development portfolio at Khavda, Bhuj, in Gujarat. The company is executing large-scale solar projects as part of India's national renewable energy expansion programmes. NTPC REL is undertaking solar installations under government schemes including the CPSU and Hybrid initiatives aimed at boosting domestic renewable capacity.

NTPC Green declares commercial operation of additional 32.8 MW at Khavda Solar Energy Project
NTPC Green declares commercial operation of additional 32.8 MW at Khavda Solar Energy Project

Business Standard

timea day ago

  • Business Standard

NTPC Green declares commercial operation of additional 32.8 MW at Khavda Solar Energy Project

NTPC Green Energy announced that consequent upon successful commissioning, the second part capacity of 32.8 MW out of 300 MW Khavda Solar Energy Project at Khavda, Bhuj, Gujarat under 450 MW Hybrid Tranche-V Project of NTPC Renewable Energy, a wholly owned subsidiary of NTPC Green Energy, is declared on Commercial Operation w.e.f. 00:00 Hrs. of 30 June 2025. The first part capacity of 142.2 MW of aforesaid Solar Energy Project has already been declared on commercial operation w.e.f. 28 June 2025.

NTPC Green Energy commissions further 64.7 MW Khavda-I Solar PV Project
NTPC Green Energy commissions further 64.7 MW Khavda-I Solar PV Project

Business Standard

timea day ago

  • Business Standard

NTPC Green Energy commissions further 64.7 MW Khavda-I Solar PV Project

NTPC Green Energy announced that consequent upon successful commissioning, third part capacity of 64.7 MW out of 1255 MW Khavda-I Solar PV Project of NTPC Renewable Energy, a wholly owned subsidiary of NTPC Green Energy in Gujarat under CPSU scheme Phase-II Tranche-III, is declared on Commercial Operation w.e.f. 00:00 Hrs. of 30 June 2025. The first part capacity of 110.25 MW and second part capacity of 146.7 MW of aforesaid Solar PV Project has already been declared on commercial operation w.e.f. 06 June 2025 and 28 June 2025 respectively.