Urgent solutions for KwaZulu-Natal's housing crisis: Politicians debate budget challenges

Urgent solutions for KwaZulu-Natal's housing crisis: Politicians debate budget challenges

IOL News25-04-2025
Members of the KwaZulu-Natal Provincial Legislature were concerned about overcrowding and growth in informal settlements, a backlog of housing projects, and a lack of accountability.
Image: Supplied
KwaZulu-Natal politicians debated various methods to address the critical housing crisis in the province during the Department of Human Settlements' R3.5 billion budget vote on Friday.
Siboniso Duma, the MEC for Transport and Human Settlements, conceded that many housing projects have been delayed because contractors had gone bankrupt, and some projects had allegations of irregularities as well as logistical delays in supply chain processes.
According to Duma, non-compliant contractors will face legal action, be blacklisted, and may be forced to pay for repairs themselves.
He said there were problems with the houses' quality that went beyond standard snag lists.
According to Duma, the department prioritises eThekwini's transit camps and informal settlements, and was able to decommission 15 transit camps by the end of March 2024. In 2025, they want to decommission eleven transit camps.
He said 13 informal settlement projects are under planning and prefeasibility and expected to be completed by 2028, adding that land availability for sustainable human settlements was a challenge.
'Our focus remains on acquiring suitable land for human habitation to address informal settlements and relocating communities to safer and integrated areas. The people of this province cannot wait any longer for their houses because of protracted delays caused by local and district municipalities in terms of the provision of bulk infrastructure.'
Duma was referring to the Mbulwane Area H Housing Project under Alfred Duma Local Municipality with a budget of R120 million. According to him, his department invested more than R11 million in bulk infrastructure despite this being the responsibility of the district municipality.
He said the department experienced a similar problem with the Thubalethu Housing Project under UMthonjaneni Local Municipality. His department allocated R61 million for the installation of bulk water services and another R19 million for the construction of water infrastructure in the area.
Duma stated that settlement growth is occurring in the eastern and western portions of KZN, primarily around Durban, Pietermaritzburg, and KwaDukuza, where development and job opportunities are available
'The eThekwini Municipality has experienced the most significant increase in the demand for housing, which is due to rapid migration of indigent families to the city and its surroundings, thus increasing the number of informal settlements and informal dwellings,' Duma said.
Members of the Provincial Legislature (MPLs) expressed concerns about overcrowding, the growth of informal settlements, and a backlog of housing projects that lack accountability.
Simanga Mabaso, uMkhonto weSizwe Party (MKP) member, said there was a lack of transparency in the waiting list for houses.
Mabaso stated that there was no plan to deal with housing backlogs, suggesting that the department use the Shanghai affordable housing blueprint, which could solve South Africa's housing problem within five years.
IFP member Ncamisile Nkwanyana said corruption in the allocation of houses must come to an end. She was concerned about the reduction of the budgets and called for updates on stalled projects.
She said the department failed to monitor the use of money allocated to municipalities for housing projects.
'There must be stringent oversight and constant site supervision to improve the quality of houses and products purchased," Nkwanyana said.
DA member Riona Gokool said there was a need for transparency, accountability, and effective governance from the department.
The DA has called for a comprehensive turnaround strategy from the DHS which include:
• Effective oversight and accountability: Ensuring that all projects are subject to rigorous monitoring and evaluation
• Streamlined processes: Reducing red tape and inefficiencies that delay project implementation• Community engagement: Involving residents in the planning and execution of housing projects to ensure that their needs are met
• Financial discipline: Allocating funds judiciously and ensuring that every cent is spent effectively.
Gokool said the department failed to develop cohesive strategies that address the maintenance of existing housing, the issuing of title deeds, and the resolution of issues related to informal settlements.
'It has consistently failed to meet its targets even when resources were sufficient. The emergency housing response fund has been underutilised, with underspending in the 2023/24 financial year attributed to incomplete beneficiary lists, procurement delays, and a lack of standard operating procedures.'
Gokool added that after the April 2022 floods, the department redirected money to construct temporary homes for flood victims, which delayed progress on addressing KZN's existing housing backlog.
'This, while the department had already been allocated R476 million for emergency housing, yet only spent 5%,' Gokool said.
Gokool suggested that the department establish a transparent, accountable, and efficient housing list to ensure fairness and reduce instances of mismanagement.
Cynthia Shinga, an NFP member, said it was unacceptable that people should suffer because municipalities cannot deliver services on time.
'No elder should die waiting for a relocation, and no child should grow up in a hijacked building. A list of names of those contractors who are blacklisted along with officials responsible for failed projects must be made available to the community,' Shinga said.
zainul.dawood@inl.co.za
The KwaZulu-Natal Department of Human Settlements' R3.5 billion budget for the financial year 2025/26.
Image: Screengrab
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

eThekwini residents build shacks on cemetery graves
eThekwini residents build shacks on cemetery graves

The South African

time13 hours ago

  • The South African

eThekwini residents build shacks on cemetery graves

More than 400 community members are living in informal settlements at Seaview Cemetery in Ward 64, under the eThekwini Municipality. KwaZulu-Natal MEC for Transport and Human Settlements, Siboniso Duma, said some residents erected shacks directly on top of graves. Duma said that on Sunday, he instructed the Head of the Department of Human Settlements, Max Mbili, to work with the municipality to expedite the profiling of families living at the cemetery on Coedmore Road. He reminded residents that the democratic government under Nelson Mandela prioritised housing construction in the area shortly after 1994. 'Priority was given to families who had lived in the area since 1981. It is unfortunate that despite having relocated communities, some came back to the area and others built new informal settlements in the same area,' Duma said. Around 2000, officials relocated families from the cemetery area to new homes in Welbedacht, Chatsworth. These officials included the late KZN MEC for Housing, Dumisane Makhaye, former MEC for Housing, Mike Mabuyakhulu, former eThekwini Mayor, Obed Mlaba, and Nigel Gumede, former Chair of the Human Settlements and Infrastructure Committee. Duma acknowledged that people migrate to eThekwini in search of socio-economic opportunities due to housing and land shortages, but stressed the need to respect burial grounds. 'Cemeteries are sacred places where the dead must be allowed to rest in peace. We call on communities to respect the departed soul,' he said. The Department of Human Settlements continues to engage with Ratepayers Associations regarding state-owned land where housing projects face delays. According to The Citizen , Duma confirmed that the department is conducting comprehensive research into housing needs across four priority groups: Households living on privately owned land facing eviction Households in rural or informal settlements in disaster-prone areas Households living in graveyards, such as Seaview Cemetery Farm dwellers The research will involve institutions such as the Moses Kotane Research Institute, National Home Builders Registration Council, Stats SA, CSIR, and the Department of Co-operative Governance and Traditional Affairs. While research continues, the department has identified the Greater Kokstad Local Municipality as the pilot site for the Agri-Village programme. The initiative, involving the Department of Land Affairs and the Department of Agriculture, Forestry, and Fisheries, aims to improve living conditions for farm dwellers by ensuring access to decent housing, water, electricity, roads, and socio-economic opportunities. Let us know by leaving a comment below, or send a WhatsApp to 060 011 021 1 Subscribe to The South African website's newsletters and follow us on WhatsApp, Facebook, X and Bluesky for the latest news.

MEC denies interfering with tender process
MEC denies interfering with tender process

eNCA

time14 hours ago

  • eNCA

MEC denies interfering with tender process

DURBAN - A big fight is brewing in the multi-billion-rand KwaZulu-Natal School Nutrition Programme. The process is once again marred by controversy. Aggrieved service providers accuse the education department of rigging the new tender process to unfairly exclude bidders in favour of politically connected individuals. WATCH: Govt of Provincial Unity | Changes to KZN tender processes MEC Sipho Hlomuka denies there was political interference with the procurement process. The Service Providers Association wants the new tender process investigated and set aside. eNCA's Zanele Buthelezi has more.

MEC Siboniso Duma addresses contractor payment delays in KZN Transport
MEC Siboniso Duma addresses contractor payment delays in KZN Transport

IOL News

timea day ago

  • IOL News

MEC Siboniso Duma addresses contractor payment delays in KZN Transport

KwaZulu-Natal MEC for Transport Siboniso Duma says delays in the payment of contractors constructing and rehabilitating road infrastructure in KZN was a concern. Image: Supplied The delays in the payment of contractors constructing and rehabilitating road infrastructure in KwaZulu-Natal were a concern. The matter was highlighted by MEC of Transport Siboniso Duma during his budget hearing presentation and Annual Performance Plan (APP) at the KZN Legislature Transport Portfolio Committee, on Tuesday. Following the re-tabling of the national Budget by the Finance Minister Enoch Godongwana, provincial departments were also required to re-table their budgets. Riona Gokool, MPL and DA spokesperson on transport, was concerned about allegations that contractors are not being paid for services rendered. This despite the department's significantly increased 2025/26 budget of over R13 billion: a 6.2% increase compared to the adjusted 2024/25 appropriation. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Ad loading Gokool called for: A full disclosure regarding the total value of 2024/25 unpaid invoices and clarity on how the department plans to settle these in 2025/26. A full breakdown of all unpaid contractors from the 2024/25 financial year and the reasons. A timeline of when affected contractors can expect payments. Immediate steps within the DoT to ensure transparent and timely processing of contractor payments going forward. Ringfencing or conditional release of infrastructure and maintenance grant funds until the DoT provides a clear debt settlement plan and payment timeline. Clarity on whether non-payments will impact service delivery and infrastructure rollouts during the current year. The department's infrastructure programme has been allocated a substantial R9.2 billion, with R4.3 billion earmarked for maintenance and R3.8 billion for construction. Gokool said this highlights a mismatch between budget allocation and actual service delivery, particularly if contractors are not being paid or projects are not progressing as intended. According to Gokool, the APP and budget reports make repeated references to prior-year unpaid invoices, specifically noting a spike in expenditure during Quarter one of the 2024/25, which was attributed to late payments from the previous year. She said the department's over-expenditure in that period - R404 million instead of the projected R213 million - raises red flags regarding financial planning and invoice processing systems She added that the DoT's 2025/26 budget makes no clear provision or explanation for settling these outstanding contractor payments, and the progress on disbursing 2024/25 invoices remains unclear 'The ripple effect of non-payments not only affects businesses - it affects workers, their families and local economies - this despite a massive budget supposedly available,' she said. Duma stated that his department continues to prioritise the payment of contractors and that he requested a detailed report from his department heads of delays in payments for the contractors. He also called to prioritise contractors and service providers in rural areas where there is poverty. Duma said that DoT has made great progress in terms of the rollout of road infrastructure projects throughout the corners of the province. 'We have created job opportunities for thousands of people in deep rural areas. We have targeted young people who are worst affected by unemployment. The issue of floods and prolonged rainfall are natural disasters that are affecting our performance,' he said. Duma said that there would be penalties and punitive actions against contractors who squander money and abandon sites without finishing projects. He warned that contractors would be blacklisted and they will be taken to court to recover money.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store