Anti-MPRP group considering legal response to PSEG court order filing for land access
The Public Service Enterprise Group (PSEG), an energy company based in New Jersey, announced Wednesday its intention to file a court order asking for access to properties on or near the route of the Maryland Piedmont Reliability Project (MPRP).
The MPRP is a proposed 500,000-volt transmission line that could cut through northern Baltimore County, central Carroll County and southern Frederick County, ending at the Doubs substation.
PSEG has a contract with PJM Interconnection, the company that coordinates the movement of electricity in 13 states and Washington, D.C., to build the MPRP to address anticipated power demand on the regional grid.
PJM has predicted a significant increase in power demand partially due to new data centers to be sited in Maryland and Virginia, which could require up to 7,500 megawatts of power.
Additionally, more than 11,000 megawatts of power generation have been recently deactivated, meaning less power is being created as the demand rises.
PSEG said it needs access to the hundreds of properties along the route to conduct environmental studies and field surveys to move the MPRP forward.
In order to obtain a certificate from Maryland authorizing the company to build the MPRP, the state is requiring PSEG to conduct these studies to verify the scope of the project's environmental and socioeconomic impacts.
PSEG plans to file a court order on Tuesday asking for temporary access to about 90 properties to conduct these surveys. This could be the first of many filings if PSEG can't successfully negotiate voluntary rights-of-entry with other property owners.
Jason Kalwa, the project's director, said in an interview that gaining temporary access to properties through a court order would not be the same as PSEG using eminent domain.
Eminent domain is a governmental power to seize private property for public use with just compensation.
PSEG will not have access to the properties anymore after completing the field surveys. A judge would decide how much time to grant the company access.
"The property owners are not giving up any other rights. This is temporary access. This is effectively to allow our experts, environmental and otherwise, to walk on the property, take an assessment of what they see there,' Kalwa said.
"... It's not eminent domain. It gives us no permanent rights to the property. It merely gives us access to the property to conduct surveys, which are necessary for many types of permits out there."
PJM has set a deadline of June 1, 2027, for PSEG to finish the MPRP and start operating it.
'We're going to stand together'
Since the project was announced in June, thousands of residents have joined to form a fierce wave of opposition to the project.
At public meetings, they've yelled at PSEG representatives and expressed frustration and fear of how the MPRP cutting through private properties could destroy businesses or drive people out of their homes.
Stop MPRP, which has members from all three counties the MPRP would be in, was formed for the purpose of stopping the project and advocating on behalf of people who will be affected by the transmission line.
Its website, stopmprp.com, includes resources like how to access the proposed route map and what actions people can take to oppose the project.
It also sells items like shirts, bumper stickers and yard signs so people can show their opposition to the project.
When cars drive on areas where the MPRP would go in Frederick County, several properties may have yard signs stuck at the edge of their properties.
They say "No eminent domain for corporate gain" and "Stop Maryland Piedmont Reliability Project," next to a picture of a power line tower being crossed out.
Stop MPRP also has a Facebook group, which had about 10,300 members as of Wednesday afternoon.
After PSEG announced the MPRP's final path in October, it sent out about 800 letters in the fall to the owners of about 600 tracts of property who will be impacted by the route. Some of the land parcels have multiple owners.
Joanne Frederick, president of Stop MPRP's Board of Directors, sent a statement after the final route announcement that said the organization's members are committed to stopping the project completely, regardless of the proposed route.
Land agents on behalf of PSEG have been reaching out to affected property owners to discuss rights-of-entry to properties.
Some owners have been offered compensation of $1,000 for a temporary right-of-entry. Most people have either not responded or denied PSEG's requests.
When Frederick learned about the news of the requested court order Wednesday morning, she said, she wasn't surprised.
Although Stop MPRP doesn't know yet what specific legal response it may pursue — they need to see PSEG's court order filing first — she said the organization "won't sit idly by" and does plan to respond.
She questioned a court's ability to compel people to give up land rights and said PSEG has acted aggressively, now "threatening to take land owners to court," she said.
"These people are scared," Frederick said. "... We're going to stand together."
Frederick County spokesperson Vivian Laxton said the county's stance on the MPRP is still the same in light of news of the court order filing, such as that PSEG should've had a more transparent public engagement process before moving forward with the project.
In September, County Executive Jessica Fitzwater and the Frederick County Council signed a letter urging the state to reject any certificate application from PSEG for the MPRP.
The letter criticized PSEG and PJM for not providing enough information or prior notice of the project to the public. It also said the MPRP "will directly and negatively impact current homes, businesses and farms ... historical preservation sites, and will diminish the property values of thousands of Frederick County residents.'

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Chicago Tribune
2 days ago
- Chicago Tribune
ComEd CEO seeks rules to prevent AI from boosting energy bills
The head of Chicago's biggest energy supplier has called for new rules to curb the impact of the artificial intelligence boom on consumers' electricity bills. Commonwealth Edison Co. has proposed modifications to tariffs that include higher deposits for data centers, according to Chief Executive Officer Gil Quiniones. He also wants data centers to post collateral in case 'loads and revenues do not materialize as planned.' 'What really needs to happen is to make sure that we're not shifting costs due to data centers powered by AI to all the other customers,' Quiniones said in the interview Wednesday. Concerns are growing about the impact on ordinary consumers from the massive build-out of AI-related infrastructure. The boom is spurring the largest increase in US electricity demand in decades, but power suppliers struggling to keep pace. Quiniones spoke at the Global Quantum Forum in Chicago, where utility executives including ComEd's owner, Exelon Corp., and Southern Co. also addressed the issue. Southern's CEO Chris Womack said Americans will revolt if they end up on the hook for soaring power costs associated with AI. Earlier this week, the operator of the largest US grid offered more evidence of how power prices are being bid higher. The outcome of an electricity auction Tuesday meant businesses and households served by PJM Interconnection LLC will spend a record $16.1 billion to ensure power supplies in the year starting June 2026. The region supplied by PJM includes Chicago. Prices would have been even higher if Pennsylvania Governor Josh Shapiro hadn't sued to place a cap on increases, Exelon CEO Calvin Butler said during a panel discussion. 'When you look at the prices that came out yesterday, they're only going to continue to increase,' Butler said. 'Policy is very important, because we have to get this right. And I wish I could tell you today that we have an answer for the short term.' The growth of quantum computing in Illinois alongside the AI and data centers boom needs to be closely watched, Quiniones also said. While quantum computing is less energy-intensive than AI, Chicago's quantum and microelectronics park, a project spearheaded by Illinois Governor JB Pritzker, has already attracted more than $1 billion in investment from companies including PsiQuantum Corp., International Business Machines Corp. and Infleqtion. 'For now, we are a state that exports power,' Quiniones said. 'We need to be very, very closely monitoring this, working with PJM and our regulators in the state to make sure that we make appropriate additions in the future, not only in generation capacity, but investment on the transmission system.'
Yahoo
2 days ago
- Yahoo
FERC approves $16.4B Constellation-Calpine deal
This story was originally published on Utility Dive. To receive daily news and insights, subscribe to our free daily Utility Dive newsletter. The Federal Energy Regulatory Commission Wednesday approved Constellation Energy's proposal to buy Calpine from Energy Capital Partners in a deal valued at $16.4 billion, subject to conditions aimed at reducing the expanded company's ability to exert market power. With a proposed mitigation plan in place — which includes Constellation selling five power plants in the PJM Interconnection — 'the proposed transaction will not have an adverse effect on competition,' FERC said. An agreement between Constellation and Monitoring Analytics, PJM's market monitor, imposes offer caps in the PJM capacity market on all of the independent power producer's power plants selling into the PJM market through the 2035-36 delivery year, FERC said. Although Constellation agreed not to enter into colocation data center deals until mid-2026 or until FERC issues an order clarifying PJM's rules on the issue, Jefferies equity analysts said Thursday that the company will be free to enter into above-market data center transactions under the approved conditions. In its decision, FERC dismissed arguments from Public Citizen, PennFuture and the Clean Air Council that Constellation could withdraw its nuclear capacity from the market to sell power directly to data centers, saying there was no evidence that would happen. As part of the plan, Constellation will sell four power plants in the PJM Interconnection totaling 3,546 MW. They are the: 1,134-MW gas-fired combined cycle Bethlehem Energy Center; the 569-MW dual-fuel combined cycle York Energy Center Unit 1; the 1,136-MW dual-fuel combined cycle Hay Road Energy Center; and the 707-MW, gas-fired simple cycle Edge Moor Energy Center. In its agreement with PJM's market monitor, Constellation agreed not to sell any of the power plants to Dominion Energy and American Electric Power, which own the most capacity in PJM. FERC rejected concerns raised by the Monitoring Analytics that PJM's capacity market is structurally uncompetitive and that consolidation of power plant owners makes market power problems worse. PJM has rules to mitigate the ability of power plant owners to drive up capacity prices using their market power, FERC said. The U.S. Department of Justice must approve the transaction before it can close, which Constellation expects will happen in the fourth quarter. Under the deal, Constellation will own almost 60 GW of nuclear, natural gas, geothermal, hydro, wind, solar, cogeneration and battery storage. Calpine currently owns 27 GW. Recommended Reading Ratepayer advocates urge FERC to reject proposed Constellation-Calpine deal Error in retrieving data Sign in to access your portfolio Error in retrieving data Error in retrieving data Error in retrieving data Error in retrieving data


CBS News
3 days ago
- CBS News
ComEd customers seeing bills double amid rising electric cost
Temperatures are soaring, and so are the bills for ComEd customers, who are feeling the impact of the sticker shock. Experts, however, said the anger directed toward the electric company is being misplaced. Triple-digit jumps in some electric bills have customers seeing red. The main culprit isn't ComEd. The real driver is a higher supply charge, which the grid operator sets, not the utility, and unfortunately, it will get worse. "Mine doubled! That's kind of garbage," customer Drew Marinelli said. His ComEd bill for his Albany Park apartment went from around $80 per month to $167 last month. "It is a little frustrating to see that it jumped up that aggressively for what felt like no reason," he said. Marinelli wasn't the only customer to gasp. "The increase went into effect on June 1 and is expected to be about 10 to 15 percent per household," Mohammad Abdullah said via TikTok. The issue is baked into the "electricity supply charge," and it's not the company's fault. "Big power generators, the companies that own the power plants. They are laughing all the way to the bank this summer as we pay these high bills," Citizens Utility Board Communications Director Jim Chilsen said. Chilsen said the cost of electricity on the wholesale market went up thanks to PJM Interconnection, the electric grid operator. He said they have been slow to adopt low-cost clean energy resources and battery projects to help bring down prices. ComEd said the spike, combined with an unseasonably warm June, raised the average bill by more than $67. "Rising energy prices have a real impact on the families and customers that we serve," ComEd's director of revenue policy, Brad Perkins, said. Perkins said they knew it was coming and launched a $10 million relief fund earlier this month to help struggling customers pay these rising bills. "Thus far, we've seen a lot of interest in this. Thousands of customers have applied for relief on this, and customers will start experiencing the credits associated with this relief fund in a few weeks," he said. CUB Executive Director Sarah Moskowitz said in a statement, in part: "While we are relieved that the negotiated price cap prevented capacity costs from soaring even higher, this record price spike is unacceptable. CUB is deeply concerned that ComEd customers will continue to bear painfully high costs for another year, largely because of policy shortcomings from PJM. The power grid operator's policy decisions too often favor outdated, expensive power plants and needlessly block low-cost clean energy resources and battery projects from connecting to the grid and bringing down prices. This extended price spike was preventable. It ramps up the urgency of implementing long-term reforms at PJM and comprehensive energy legislation in Illinois, such as the Clean and Reliable Grid Affordability Act, to protect customers from price spikes that serve only to give power generators windfall profits." ComEd also offers bill support and ways customers can manage the rise in cost on their website.