HC directs NHAI to submit Katol Road development proposal to Centre by July 31
The order came from a division bench comprising Justices Nitin Sambre and Mahendra Neralikar during the hearing of two public interest litigations — one filed by Dinesh Sheshrao Thakre and Sumit Ajay Babuta over the incomplete highway project, and another by lawyer Arun Patil regarding the poor condition of highways in Vidarbha.
Initially, the 48 km Nagpur-Katol Road was planned as a single-package project. But due to technical and administrative challenges, NHAI carved out two key portions — the 11.90 km Katol bypass and the 8.10 km stretch under Tiger Corridor-I — and excluded them from the main contract.
These segments are now to be executed through separate tenders, with development works in the tiger corridor alone expected to cost Rs500 crore.
"Work on critical portions like Tiger Corridor-I and Katol bypass is now expected only by 2027 and 2028, respectively," NHAI's divisional manager Chandrakant Sinha informed the court in the previous hearing. He also stated that while 28.20 km of the road will be ready by December 2025, the corridor segment needs National Board for Wildlife (NBWL) clearance due to requirement of constructing animal-friendly movement structures.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
집에서 10분 사용 후 "남성기능/지속시간" 폭발..20대처럼!?
男기능 10분 복구
Undo
As per the revised timeline, construction of Tiger Corridor-I is expected to begin in January 2026 and conclude by June 2027. Construction of the Katol bypass, still requiring 3 km of land acquisition and the construction of a railway overbridge, is scheduled to commence by March 2026 and finish by March 2028.
Petitioners' counsel Mahesh Dhatrak urged the court to ensure urgent intervention on the delayed wildlife stretch, calling it "critical to both traffic decongestion and ecological sensitivity".
In a related matter, the court also sought a reply from NHAI by the next hearing on the status of encroachments affecting development along the Nagpur-Fetri Road. Despite prior directions for removal, senior advocate Firdos Mirza, representing Patil, submitted that illegal constructions continue to obstruct progress.
The court was informed that the detailed project report for the Katol bypass will be sent for approval and land acquisition is expected to conclude by December 2025. The project was restructured due to ecological constraints, Sinha clarified during the hearing of a PIL (No. 22/2019), which highlights the poor condition of several roads in the region, including the Amravati-Akola-Jalgaon and Wardha-Sindkhed Raja roads.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
26 minutes ago
- Time of India
14-Samdani-CM-FIber-Net-Revival
Vijayawada: Chief minister Chandrababu Naidu directed officials to take swift action to restore and revitalize the AP Fiber Net project. He charged that the previous government had completely derailed the AP Fiber Net project, a visionary initiative launched between 2014 and 2019. Reviewing the progress of AP Fibernet activities here on Monday, the chief minister asked the officials to assess the challenges, financial constraints, necessary corrective steps, and new policy directions. He said that the system, designed to benefit the public, students, and government departments, was exploited for political purposes by the previous govt. He pointed out that while there were 8.70 lakh connections before 2019, was dropped to 4.50 lakh during the YSRCP regime. "We managed the organization effectively with just 130 employees and provided over 8 lakh connections. But the YSRCP government created unauthorized posts to accommodate its party workers, expanding the workforce from 130 to 1,350 and misusing public funds. This was a new form of corruption where party affiliates were placed in government roles and used for political work. The fiber network was no exception. Those responsible must be held accountable. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Providers are furious: Internet access without a subscription! Techno Mag Learn More Undo A thorough investigation should be conducted into those appointments, and full transparency must be ensured," directed chief minister. He, however, said that steps must be taken to rectify past mistakes and ensure a better future. He instructed that the current 4,53,525 connections be increased to at least 8–10 lakh. The chief minister approved the integration of AP Fiber Net with the BharatNet (Amended BharatNet Programme – ABP). Under this scheme, the Centre will allocate Rs. 1,900 crore to AP Fiber Net from 2025 to 2035. He also approved the transition of fiber networks in 1692 gram panchayats across Chittoor and Visakhapatnam districts from linear to ring architecture. Additionally, 480 new gram panchayats will be connected using the ring model. The Centre will provide Rs. 430 crore for this phase. GFX *A Special Purpose Vehicle (SPV), jointly managed by the Central and State Governments, to oversee these projects should be created: CM *The selection process for set-top box suppliers be completed immediately and that a revenue-sharing model be developed with Local Cable Operators (LCOs) using new set-top boxes: CM *Reintroduce services like virtual classrooms *Andhra Pradesh currently leads the nation in village panchayat connectivity. *Fiber net services have been extended to 12,946 panchayats so far. *The government aims to expand the network to a total of two lakh km. *Andhra Pradesh leads all Indian states in fiber optic network coverage with 78355km, followed by Maharashtra (50,481 km), Tamil Nadu (49,616 km), Gujarat (35,246 km), and Telangana (29,143 km).


Time of India
26 minutes ago
- Time of India
No official word yet, Metro likely to fix faulty Sadar flyover landing
1 2 Nagpur: A month after Union minister for road transport and highways Nitin Gadkari admitted to Sadar flyover's faulty landing design and assured rectification, no govt agency has officially been assigned the task. While sources have confirmed that MahaMetro will carry out the rectification, the agency is yet to receive an official contract to begin the work. Built at a cost of Rs219 crore by the National Highways Authority of India (NHAI), the 3.96-km Y-shaped flyover was inaugurated in January 2020 with the aim of easing traffic congestion in Sadar and adjoining areas. It connects Samvidhan Square to Katol road and Koradi road. However, the flyover's landing near Kasturchand Park on Kamptee road created a major traffic bottleneck that has led to persistent jams. To regulate traffic descending from the flyover, authorities were forced to shut the crucial Samvidhan square-LIC square stretch. As a result, motorists heading from Samvidhan square to the Kamptee flyover are now forced to take a detour via Sadar, make a U-turn towards NIT, then proceed through LIC square to reach Kamptee road. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like If you have a mouse, play this game for 1 minute Navy Quest Undo TOI has repeatedly reported on the flawed design of the flyover's landing and the resultant traffic chaos. Last month, Gadkari acknowledged the issue at a press conference and announced that Rs34 crore was proposed to fix the design and streamline traffic movement. Initial enquiries with NHAI revealed that it would not undertake the repairs. "The work will be carried out by PWD since it falls under the Central Road Fund (CRF)," an NHAI official said. However, PWD officials later confirmed that MahaMetro would execute the project. A senior MahaMetro official also confirmed the agency's involvement. "We have been informed that MahaMetro will be given the task. However, we are still awaiting the design-build contract (DBC) from the PWD. Once we receive it, we will begin the work," the official said. The lack of clarity and delay in assigning the rectification work — despite a ministerial assurance and the urgency of the issue — has raised questions over coordination among govt agencies. Meanwhile, thousands of daily commuters continue to bear the brunt of a flawed design awaiting a long-overdue fix.


Time of India
36 minutes ago
- Time of India
Cancer Daily Horoscope Today (Aaj Ka Kark Rashifal), July 15, 2025: Peace arrives when you stop forcing
Today teaches you that forcing something to happen is not always the answer. You may have been pushing too hard in one area of life, but now, when you step back, things begin to settle. Let life flow without trying to control every detail. When you stop struggling, a new solution may appear clearly in front of you. What clicks into place now will feel smooth and natural. Trust that rest and surrender can often do more than pressure ever could. Cancer Love Horoscope Today In love, stop trying to shape every moment or control the outcome. If in a relationship, your partner might respond better when you stop pushing for answers. Let the conversation flow softly and let love grow slowly. If single, step back from chasing or overthinking. When you release the need to control, the right connection will find you with ease. Emotional peace is the true sign of love. Let your heart breathe today and give space for real closeness. Cancer Career Horoscope Today Career life may feel less tense if you allow things to unfold naturally. A delay or confusion you were stressing over might start resolving itself. You don't have to fix every problem in one day. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like An engineer reveals: One simple trick to get internet without a subscription Techno Mag Learn More Undo Focus on doing your part well, then leave space for results to come. Sometimes, people work better when you stop managing them too closely. Step back, and solutions will appear more clearly. Trust your own efforts and give the rest to time and patience. Cancer Money Horoscope Today Money matters become more manageable when you stop trying to do everything perfectly. If your financial plans were feeling too heavy or strict, lighten them today. A simple, clear approach will help more than complex planning. Allow space in your budget for breathing room. Do not pressure yourself to meet every financial target immediately. Trust that your calm and consistent mindset will bring more peace. Let abundance come in its own time, not through force or stress. Cancer Health Horoscope Today Health feels better when your emotional body is relaxed. Forcing strict routines or pushing your body too much can create tension. Today, allow yourself to slow down and notice how your body feels. Gentle exercise, peaceful music, and light food will help. Avoid trying to fix every discomfort quickly. Sometimes, just resting deeply or drinking warm water is enough. Your body will guide you to what it needs when you listen calmly. Stop forcing healing, and it will begin naturally. Discover everything about astrology at the Times of India , including daily horoscopes for Aries , Taurus , Gemini , Cancer , Leo , Virgo , Libra , Scorpio , Sagittarius , Capricorn , Aquarius , and Pisces .