Allan has time to abandon Melbourne's gargantuan folly. But it's about to run out
This means that if the government quit the SRL now, it could break the main works contracts it has already signed for a fraction of their nominal, $5.3 billion value. There are no hidden nasties like there were in the East West Link contract the former Coalition government booby-trapped for Labor on the eve of the 2014 state election.
Once the tunnel boring machine is loaded onto freight transport in Guangzhou, the costs incurred by the main works consortia – this first to get its hands dirty is the Suburban Connect consortia comprising of Acciona, CPB Contractors and Ghella – will escalate quickly.
By Christmas, the Victorian government will be standing deep in a hole at Clarinda with a choice only to keep digging.
This calculus should be front-of-mind for anyone reading revelations by my colleagues Patrick Hatch and Kieran Rooney about the North West Strategic Assessment, a wafty title given to a secret government document detailing urgent rail projects needed in parts of Melbourne far removed from the proposed route of SRL East.
In the eight years since a room full of PwC consultants started dreaming up plans for an orbital rail loop around Melbourne, the public transport needs of the city's fast-growing western and northern suburbs has gone from pressing to dire.
Loading
Former premier Daniel Andrews promised to electrify the Melton and Wyndham lines within weeks of unveiling his plans for SRL. While nothing has been done on the former, the latter is ploughing ahead despite Infrastructure Australia warning about the business case and funding model and the federal government privately urging the state to change tracks.
Premier Jacinta Allan and many of her ministers remain convinced of the electoral popularity of the SRL. Two days after the federal election wiped out the last two Liberal-held seats in Melbourne's eastern suburbs and silenced murmurings around her leadership, Allan went so far as to suggest it's the SRL wot won it.
Yet how can a Labor government, in good conscience, prioritise another rail line for a part of Melbourne already well serviced by public transport above the provision of basic transport services for communities living in neglected parts of the city?
As one Labor MP who represents a Melbourne growth area explained, access to reliable public transport isn't just about moving people around or enabling townhouse and high-rise developments. Fundamentally, it is about opportunity to study, to work and to prosper.
Loading
That opportunity should not be equal only for people living east of the Maribyrnong River or inside Melbourne's ring road.
The state and federal government's combined $4 billion investment to rebuild Sunshine station and untangle the knot of metro, regional and freight lines that run past its existing platforms is the first significant step towards modern rail transport for people living in Caroline Springs, Melton, Tarneit and Wyndham Vale.
It should be the start of a more substantial pivot away from giving Melbourne's east what it wants and providing the west and north what they need.
SRL East is a project which, in the unlikely event it is completed on time, will run its first service in 2035. Its opportunity cost is being counted now, on a daily basis, across health, mental health, education and other essential services, where jobs are being cut and agencies defunded.
Loading
In the new currency of Victoria's public sector, every metre of SRL tunnel equates to $130 million that could otherwise be spent on teachers or nurses or preventive healthcare or government schools.
Before the last state election, when then opposition leader Matthew Guy promised to axe the SRL and redirect the money into hospitals, Daniel Andrews delivered a pithy retort. 'Not rail or hospitals,' he tweeted. 'Both.'
It was a brilliant line and, as it turns out, complete bollocks.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Advertiser
an hour ago
- The Advertiser
'Battery of the nation' undersea power cable at risk
One of the nation's largest energy projects could be in doubt amid a government stoush and a cost blowout. The multi-billion-dollar Marinus Link undersea power cable project to connect Tasmania to the mainland has been touted as critical to making the island state the "battery of the nation" by increasing its capacity to export green power. The $5.5 billion project is set to be funded by the federal, Tasmanian and Victorian governments. The Tasmanian government's decision on its 17.7 per cent share of the link's Stage 1 cable, initially promised by July 31, has been delayed. Tasmania's Shadow Energy Minister Janie Finlay on Saturday accused Premier Jeremy Rockliff of blocking a briefing from Energy Minister Nick Duigan on the Marinus business case. It had been hoped the briefing would create bipartisan support to secure the project as Tasmania's Liberal government scrambles for survival following the July 19 election. "We are days away from a critical decision on one of Tasmania's largest infrastructure projects," Ms Finlay told reporters. "The business case has been sitting in the premier's office for two months, but Jeremy Rockliff won't let Tasmanians see it. "Not only have they just not briefed Tasmanian Labor, but the premier has stepped in and actively blocked that." Tasmanian Minerals, Manufacturing and Energy Council chief executive Ray Mostogl said the delay and uncertainty placed the entire project at risk. Marinus Link must "issue notice to proceed" by the end of August or lose a $1.07 billion contract with the Italy-based Prysmian Group to supply the 345km cable. Tasmania's Liberal government is in caretaker mode after the state election delivered another large crossbench, some of whom oppose the Marinus project. Ms Finlay accused the Rockliff government of hiding the Marinus Link business case for political gain because it included significant price impacts to pay for transmission infrastructure. The government has denied Mr Rockliff or his staff blocked a briefing, saying the opposition would be briefed in line with caretaker conventions. "We are carefully and methodically working through the details, with a decision expected soon," Mr Duigan said. The undersea electricity and data connector would link Tasmania's northwest with Victoria's Latrobe Valley and allow the smaller state to import surplus solar while exporting hydropower to the mainland grid, where it could help reduce the risk of brownouts. The project was scaled back in September 2023 after the cost of two cables blew out by $1.7 billion to an estimated $5.5 billion. Under the plan, Victoria has a 33.3 per cent share and Tasmania 17.7 per cent, with an option to sell its stake to the Commonwealth on completion. Marinus Link has been touted as a critical component in making Tasmania the "battery" of the nation by increasing the island's capacity to export green power and allow excess energy generated on the mainland to be stored in Tasmania's hydro storage. The first stage is not slated to be finished until 2028/29. One of the nation's largest energy projects could be in doubt amid a government stoush and a cost blowout. The multi-billion-dollar Marinus Link undersea power cable project to connect Tasmania to the mainland has been touted as critical to making the island state the "battery of the nation" by increasing its capacity to export green power. The $5.5 billion project is set to be funded by the federal, Tasmanian and Victorian governments. The Tasmanian government's decision on its 17.7 per cent share of the link's Stage 1 cable, initially promised by July 31, has been delayed. Tasmania's Shadow Energy Minister Janie Finlay on Saturday accused Premier Jeremy Rockliff of blocking a briefing from Energy Minister Nick Duigan on the Marinus business case. It had been hoped the briefing would create bipartisan support to secure the project as Tasmania's Liberal government scrambles for survival following the July 19 election. "We are days away from a critical decision on one of Tasmania's largest infrastructure projects," Ms Finlay told reporters. "The business case has been sitting in the premier's office for two months, but Jeremy Rockliff won't let Tasmanians see it. "Not only have they just not briefed Tasmanian Labor, but the premier has stepped in and actively blocked that." Tasmanian Minerals, Manufacturing and Energy Council chief executive Ray Mostogl said the delay and uncertainty placed the entire project at risk. Marinus Link must "issue notice to proceed" by the end of August or lose a $1.07 billion contract with the Italy-based Prysmian Group to supply the 345km cable. Tasmania's Liberal government is in caretaker mode after the state election delivered another large crossbench, some of whom oppose the Marinus project. Ms Finlay accused the Rockliff government of hiding the Marinus Link business case for political gain because it included significant price impacts to pay for transmission infrastructure. The government has denied Mr Rockliff or his staff blocked a briefing, saying the opposition would be briefed in line with caretaker conventions. "We are carefully and methodically working through the details, with a decision expected soon," Mr Duigan said. The undersea electricity and data connector would link Tasmania's northwest with Victoria's Latrobe Valley and allow the smaller state to import surplus solar while exporting hydropower to the mainland grid, where it could help reduce the risk of brownouts. The project was scaled back in September 2023 after the cost of two cables blew out by $1.7 billion to an estimated $5.5 billion. Under the plan, Victoria has a 33.3 per cent share and Tasmania 17.7 per cent, with an option to sell its stake to the Commonwealth on completion. Marinus Link has been touted as a critical component in making Tasmania the "battery" of the nation by increasing the island's capacity to export green power and allow excess energy generated on the mainland to be stored in Tasmania's hydro storage. The first stage is not slated to be finished until 2028/29. One of the nation's largest energy projects could be in doubt amid a government stoush and a cost blowout. The multi-billion-dollar Marinus Link undersea power cable project to connect Tasmania to the mainland has been touted as critical to making the island state the "battery of the nation" by increasing its capacity to export green power. The $5.5 billion project is set to be funded by the federal, Tasmanian and Victorian governments. The Tasmanian government's decision on its 17.7 per cent share of the link's Stage 1 cable, initially promised by July 31, has been delayed. Tasmania's Shadow Energy Minister Janie Finlay on Saturday accused Premier Jeremy Rockliff of blocking a briefing from Energy Minister Nick Duigan on the Marinus business case. It had been hoped the briefing would create bipartisan support to secure the project as Tasmania's Liberal government scrambles for survival following the July 19 election. "We are days away from a critical decision on one of Tasmania's largest infrastructure projects," Ms Finlay told reporters. "The business case has been sitting in the premier's office for two months, but Jeremy Rockliff won't let Tasmanians see it. "Not only have they just not briefed Tasmanian Labor, but the premier has stepped in and actively blocked that." Tasmanian Minerals, Manufacturing and Energy Council chief executive Ray Mostogl said the delay and uncertainty placed the entire project at risk. Marinus Link must "issue notice to proceed" by the end of August or lose a $1.07 billion contract with the Italy-based Prysmian Group to supply the 345km cable. Tasmania's Liberal government is in caretaker mode after the state election delivered another large crossbench, some of whom oppose the Marinus project. Ms Finlay accused the Rockliff government of hiding the Marinus Link business case for political gain because it included significant price impacts to pay for transmission infrastructure. The government has denied Mr Rockliff or his staff blocked a briefing, saying the opposition would be briefed in line with caretaker conventions. "We are carefully and methodically working through the details, with a decision expected soon," Mr Duigan said. The undersea electricity and data connector would link Tasmania's northwest with Victoria's Latrobe Valley and allow the smaller state to import surplus solar while exporting hydropower to the mainland grid, where it could help reduce the risk of brownouts. The project was scaled back in September 2023 after the cost of two cables blew out by $1.7 billion to an estimated $5.5 billion. Under the plan, Victoria has a 33.3 per cent share and Tasmania 17.7 per cent, with an option to sell its stake to the Commonwealth on completion. Marinus Link has been touted as a critical component in making Tasmania the "battery" of the nation by increasing the island's capacity to export green power and allow excess energy generated on the mainland to be stored in Tasmania's hydro storage. The first stage is not slated to be finished until 2028/29. One of the nation's largest energy projects could be in doubt amid a government stoush and a cost blowout. The multi-billion-dollar Marinus Link undersea power cable project to connect Tasmania to the mainland has been touted as critical to making the island state the "battery of the nation" by increasing its capacity to export green power. The $5.5 billion project is set to be funded by the federal, Tasmanian and Victorian governments. The Tasmanian government's decision on its 17.7 per cent share of the link's Stage 1 cable, initially promised by July 31, has been delayed. Tasmania's Shadow Energy Minister Janie Finlay on Saturday accused Premier Jeremy Rockliff of blocking a briefing from Energy Minister Nick Duigan on the Marinus business case. It had been hoped the briefing would create bipartisan support to secure the project as Tasmania's Liberal government scrambles for survival following the July 19 election. "We are days away from a critical decision on one of Tasmania's largest infrastructure projects," Ms Finlay told reporters. "The business case has been sitting in the premier's office for two months, but Jeremy Rockliff won't let Tasmanians see it. "Not only have they just not briefed Tasmanian Labor, but the premier has stepped in and actively blocked that." Tasmanian Minerals, Manufacturing and Energy Council chief executive Ray Mostogl said the delay and uncertainty placed the entire project at risk. Marinus Link must "issue notice to proceed" by the end of August or lose a $1.07 billion contract with the Italy-based Prysmian Group to supply the 345km cable. Tasmania's Liberal government is in caretaker mode after the state election delivered another large crossbench, some of whom oppose the Marinus project. Ms Finlay accused the Rockliff government of hiding the Marinus Link business case for political gain because it included significant price impacts to pay for transmission infrastructure. The government has denied Mr Rockliff or his staff blocked a briefing, saying the opposition would be briefed in line with caretaker conventions. "We are carefully and methodically working through the details, with a decision expected soon," Mr Duigan said. The undersea electricity and data connector would link Tasmania's northwest with Victoria's Latrobe Valley and allow the smaller state to import surplus solar while exporting hydropower to the mainland grid, where it could help reduce the risk of brownouts. The project was scaled back in September 2023 after the cost of two cables blew out by $1.7 billion to an estimated $5.5 billion. Under the plan, Victoria has a 33.3 per cent share and Tasmania 17.7 per cent, with an option to sell its stake to the Commonwealth on completion. Marinus Link has been touted as a critical component in making Tasmania the "battery" of the nation by increasing the island's capacity to export green power and allow excess energy generated on the mainland to be stored in Tasmania's hydro storage. The first stage is not slated to be finished until 2028/29.

Sky News AU
4 hours ago
- Sky News AU
‘The opposite happened': Economic roundtable could dissuade Australians from investing
LNP Senator James McGrath discusses Labor's economic reform roundtable, urging that it will dissuade Australians from investing in the 'productive part of the economy'. 'What the Labor Party doesn't realise is that if people start to cotton on to the fact that Labor is going to come after the money they've worked so hard for, people will no longer invest in the productive part of the economy,' Mr McGrath told Sky News host Steve Price. 'You only have to look at what's happening in the UK at the moment, with the Labour Party there, taxing what's called 'non-doms'. 'They thought they were going to bring billions of pounds of revenue … the opposite happened.'

Sky News AU
4 hours ago
- Sky News AU
‘Australians should be worried': Labor's economic reform roundtable is ‘bonkers'
LNP Senator James McGrath discusses how Australians should be worried about Labor's economic reform roundtable, saying it is 'bonkers' and will only produce 'hair-brained ideas'. 'Australians should be worried,' Mr McGrath told Sky News host Steve Price. 'Those who own their own homes, are of pensionable age, should be worried about organisations, so-called think-tanks, like the Grattan Institute coming up with quite frankly hair-brained ideas like this. 'This is bonkers.'