Tejas-Mk-1A roll out from Nashik this month, Astra firing likely in Aug: HAL CMD
BENGALURU: Hindustan Aeronautics Limited (HAL) will roll out the first LCA Tejas Mk1A from its new Nashik production line by the end of July, with integration and test firing of the Astra air-to-air missile scheduled for early August, HAL CMD DK Sunil told TOI in an interview.
The rollout from Nashik marks a key milestone in HAL's efforts to scale up Tejas production, even as the programme works through engine supply constraints and indigenous radar integration delays. 'The first aircraft from Nashik is already in final assembly and under testing. We expect the rollout in a month,' Sunil said, adding that while the current year may see three to four aircraft from Nashik, the plant has been built to support an annual output of eight.
At present, HAL is operating two production lines in Bengaluru and has initiated the third at Nashik. A parallel private-sector supply chain — comprising VEM Technologies (centre fuselage), Alpha (rear fuselage), and L&T (wings) — is expected to contribute towards an additional six aircraft a year, eventually raising the overall production capacity to 30 aircraft annually.
He said that despite engine supply delays from GE, HAL is pressing ahead with deliveries.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Забрави климатика – това е най-доброто решение срещу жегата
Coolbox
Научете повече
Undo
'We have already built six aircraft which are ready and flying,' Sunil said. HAL expects to produce 12 aircraft this year, using available GE engines in rotation to carry out critical test flights. GE has assured delivery of 12 engines this year, with the second engine expected this month after only one had arrived by April.
Integration of Astra missile, developed by DRDO, is scheduled for early August. 'We need to have some of the other issues sorted out like the firing of the missile, the Astra missile, which we plan to do in August, early August,' he said.
On radar integration, HAL faced criticism for opting to continue with the imported ELTA radar from Israel for all Tejas Mk1A fighters under the current contract, instead of switching midstream — from the 41st aircraft — to the indigenous Uttam AESA radar.
Sunil clarified that 40 ELTA radars were contracted initially, with a plan to introduce Uttam from the 41st aircraft onwards. However, delays in certification of both the Uttam radar and associated electronic warfare (EW) suite, also being developed by DRDO, forced HAL's hand.
He noted that over the last three years, HAL has held several meetings with senior officials from DRDO and IAF, but the certification timelines have repeatedly slipped. 'As a manufacturer, when we're under pressure for not delivering, the risk becomes ours. If we wait and the systems still aren't certified, we are left with no aircraft to hand over.'
'There was a clear directive from DRDO headquarters in Feb 2024 that if certification is not achieved by year-end, HAL may proceed.
That meeting and directive are on record. We waited until March this year, but when progress still hadn't been made, we moved forward.'
In response to persistent concerns from the Indian Air Force about unmet aircraft staff qualitative requirements (ASQRs), Sunil attributed the delays to legacy issues and dependency on various partners including ADA and DRDO. 'Parallel efforts are underway to close these issues across multiple aircraft. It's not that there's no effort — it's just that the closure needs to be more structured,' he said.
HAL aims to deliver all 12 Tejas Mk1As scheduled for this year, with the full production ecosystem — including public and private lines — expected to reach a steady state of 30 aircraft annually from 2026-27.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
an hour ago
- Time of India
Industries seek swift action for Nashik airport expansion ahead of Kumbh Mela
Nashik: Four months after industries repeatedly urged chief minister Devendra Fadnavis and other ministers to expand the Nashik airport in anticipation of the upcoming Simhastha Kumbh Mela, state govt has not taken concrete steps, raising concerns among the industrial sector. A delegation from the Nashik Industries and Manufacturers' Association (Nima) met NCP MP and party's state president Sunil Tatkare during his recent visit to Nashik. The delegation requested Tatkare to take up the issue with both state and central authorities ahead of the religious conglomerate scheduled between 2026 and 2028. Tatkare held a separate meeting with Nima members to discuss the expansion of the Nashik airport terminal and the inclusion of Nashik in the second phase of the Delhi Mumbai Industrial Corridor (DMIC). Attending the meeting with Tatkare were Nima president Ashish Nahar, vice-president and chairman of the aviation committee Manish Rawal, secretary Rajendra Ahire etc. The delegation also submitted a memorandum to Tatkare regarding the matter. Association members said the airport terminal expansion would take approximately two years; therefore, they stressed on the immediate need to develop proper plans and commence work, considering there are less than two years until the Kumbh Mela. Nima vice-president Rawal said Tatkare assured the delegation he would promptly raise the issue with deputy chief minister Ajit Pawar. Moreover, he committed to meeting the relevant Central cabinet ministers to facilitate the expansion of the airport. "We also requested Tatkare to pursue Centre for the inclusion of Nashik in the second phase of the DMIC. He assured us he would take up the matter with the ministers concerned in Delhi," Rawal said. In Jan 2025, Hindustan Aeronautics Ltd (HAL), which manages the Nashik airport, requested state govt to expand the airport amid a projected increase in passenger numbers during the Simhastha Kumbh Mela. HAL submitted proposals twice in the last four months seeking the expansion of the airport terminal building and an increase in aircraft parking bays from the current five to 15. However, state govt has yet to initiate any action in this direction. Conversely, an industrialist noted during the meeting that state govt is allocating Rs 1,200 crore for the development of Shirdi airport, but has not made any decision regarding the expansion of the Nashik airport. Nashik airport, located at Janori, approximately 20km from Nashik city, was developed jointly by state govt and HAL at a total cost of Rs 94 crore in 2013 and 2014. State govt invested Rs 84 crore, while HAL contributed Rs 10 crore and provided land for the airport's construction. State govt has leased the Nashik airport terminal building to HAL for 30 years at a rate of Rs 1,000 per month. The airport's seating capacity is currently 300 passengers at a time, whereas during the Kumbh Mela, passenger footfall is expected to reach 1,000 per hour. Consequently, industries urge state govt to develop the Nashik airport ahead of the Kumbh.

Business Standard
an hour ago
- Business Standard
The case for a second fighter jet maker in India isn't compelling: HAL CMD
Hindustan Aeronautics CMD D K Sunil says the aerospace major is leveraging private-sector partnerships to boost production capacity and address the IAF's concerns over depleting squadron strength premium Bhaswar Kumar New Delhi Listen to This Article Bengaluru-headquartered Hindustan Aeronautics Limited (HAL), a Maharatna public sector undertaking under the Ministry of Defence and India's largest defence company by revenue, order book size, and market capitalisation, has faced sustained criticism from the Indian Air Force (IAF) over delays in the LCA Tejas Mk1A programme. The original February 2024 deadline for the start of deliveries was missed, even as the IAF grapples with declining squadron strength amid a volatile neighbourhood that recently saw it carry out deep strikes into Pakistan during Operation Sindoor. HAL is also pursuing a follow-on order for the Mk1A, after the initial Rs 36,000 crore


Time of India
2 hours ago
- Time of India
SSLV acquisition strategic, we'll look at redesign in future: HAL
BENGALURU: Defence PSU Hindustan Aeronautics Ltd 's (HAL) winning Rs 511 crore bid for the Small Satellite Launch Vehicle (SSLV) wasn't just about cost — it was a strategic move to own design capabilities and begin charting an independent path in India's launch vehicle ecosystem. The bid, which was significantly higher than competing offers in the Rs 250–310 crore range, was deliberate, HAL CMD DK Sunil told TOI in an interview. 'Our internal estimates were close to what we quoted — slightly lower, but in that range. This is a long-term play. We didn't want to just manufacture. We wanted to understand the rocket, build a cadre, and eventually modify the design ourselves,' he added. Unlike HAL's earlier collaborations with L&T on the Polar Satellite Launch Vehicle (PSLV), the SSLV project marks a shift. It's a full transfer of technology (ToT) agreement, with HAL taking sole responsibility — not just for manufacturing, but also for absorbing the design and systems architecture. The formal agreement with Space PSU NewSpace India Ltd (Nsil) is expected to be signed by the end of July, after which HAL will begin building two SSLV prototypes. Sunil sees this as a beginning. 'The idea is to take baby steps. We want to understand avionics, structures, rocket parts, the entire stack. It's not about redesigning in two or three years. But ten years down the line, yes, I would be very happy if HAL builds a rocket from scratch.' The move comes as demand for launch vehicles catering to low-Earth orbit (LEO) small satellite constellations rises — both in the commercial and strategic sectors. HAL's interest in SSLV is not just about assembling hardware, but about developing a future-facing business vertical in rocketry. The immediate focus is on learning and integration, but the eventual goal is autonomy in design and adaptability to different mission profiles. Meanwhile, HAL-L&T work on the PSLV is expected to achieve a milestone later this year. The first rocket built entirely by industry is expected to launch around Oct-Nov 2025. The contract is purely for fabrication, using Isro's design and established supply chain. Even so, it has seen initial delays. 'There were some issues with sourcing materials, and the external environment has contributed to some slowdown,' Sunil admitted. 'But integration is under way. These are still early days, but we're now in better shape,' he added. Despite the differences in scope, HAL's engagement with both PSLV and SSLV signals a broader repositioning of the aerospace PSU — from being a supplier of structures to becoming a deeper stakeholder in space systems. The SSLV project, in particular, marks the beginning of HAL's ambition to design, adapt, and one day build rockets of its own. 'It's a journey,' said Sunil. 'Like how we built our aircraft capability over decades. We are starting that journey now for space.'