logo
Complete solar plant projects on time: SCCL CMD

Complete solar plant projects on time: SCCL CMD

The Hindu10-07-2025
The Singareni Collieries Company Ltd (SCCL) has cautioned contract agencies engaged in construction of solar power plants against delay in completion of work, and threatened either to blacklist the agencies or to cancel the contracts if works were not completed in time.
SCCL Chairman and Managing Director N. Balaram reviewed the progress of construction of solar power plants at a meeting held here on Thursday. He instructed the agencies to complete the power plants, sanctioned under Phase-I and II, by October.
He stated that 54.5 megawatt capacity plants out of 300 MW planned in the first phase and 67.5 MW out of 240 MW taken up in the second phase were yet to be completed.
He expressed dismay over the delay in the construction of the sanctioned plants and cautioned the agencies of severe action for further delay in the completion of works. He pointed out that the contract agencies were delaying the works, though there was no delay in payment of bills for completed works by SCCL.
The CMD also cautioned the officials of Singareni over not getting the work done in time by contract agencies, saying such delays would reflect as remarks in their service records. He directed them to complete the battery energy storage system (BESS), being established at 28 MW solar plant at Mandamarri, by August.
On the 32.75 MW roof-top solar power plants sanctioned under Surya Ghar Yojana on the buildings of SCCL, the CMD told the officials to complete the installation by December-end.
Director of the company D. Satyanarayana Rao (E&M), Executive Director (Coal Movement) Sd. M. Subhani, General Manager (Solar) B. Seetharamam and others participated in the meeting.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

KSEB seeks approval for grid-scale battery storage systems at four more locations to manage surplus solar power
KSEB seeks approval for grid-scale battery storage systems at four more locations to manage surplus solar power

The Hindu

time6 hours ago

  • The Hindu

KSEB seeks approval for grid-scale battery storage systems at four more locations to manage surplus solar power

The Kerala State Electricity Board (KSEB) has sought approval for grid-scale battery energy storage systems (BESS) at four more of its substations to handle the large volume of surplus solar power being generated in the State. The power utility has sought the State Electricity Regulatory Commission's approval for implementing BESS systems with a combined capacity of 125 megawatt/500 megawatt hour (MW/MWh) at its substations at Sreekantapuram in Alappuzha district, Pothencode in Thiruvananthapuram, Mulleria in Kasaragod and Areacode in Malappuram. In a BESS system, the MW rating denotes the maximum amount of power that it can deliver at any given moment. MWh indicates the total amount of energy that the system can store. The BESS projects at Sreekantapuram and Pothencode will each have a capacity of 40 megawatt/160 megawatt hour (MW/MWh), while the ones planned in Mulleria and Areacode will have a capacity of 15 MW/60 Mwh and 30 MW/120 MWh. KSEB proposes to implement these projects through NHPC Ltd, which has been nominated as a BESS Implementing Agency (BIA) by the Union Power Ministry under the Viability Gap Funding scheme for the development of BESS systems. The KSEB has also sought the commission's approval for the monthly capacity charges quoted by four project developers shortlisted by NHPC. The tariff quoted by the developers would remain fixed for a period of 12 years, with a provision for extending the project life by another five years with appropriate adjustments in the applicable tariff. The power utility had already announced plans to set up a BESS at the Mylatti substation in Kasaragod. In seeking the commission's approval for the four new proposals, the KSEB has cited a growing requirement for energy storage in the State, given the 'increasing solar power penetration, rising peak power demand, the installed capacity within the State, and the prevailing price of peak power.' BESS systems will increase the internal power handling capacity of the State and reduce the dependence on the inter-State power transmission corridor, according to KSEB.

India installs record 22 GW renewable capacity in H1 2025; solar leads with 18.4 GW: Report
India installs record 22 GW renewable capacity in H1 2025; solar leads with 18.4 GW: Report

Time of India

time10 hours ago

  • Time of India

India installs record 22 GW renewable capacity in H1 2025; solar leads with 18.4 GW: Report

India added a record 22 gigawatts (GW) of renewable energy capacity in the first half of 2025, marking a 57 per cent increase from the 14.2 GW installed in the same period last year, according to a report by Rystad Energy. Of the total, 18.4 GW came from solar installations, followed by 3.5 GW of wind and 250 megawatts (MW) of bioenergy. This is the highest-ever renewable capacity addition for any six-month period in the country. The growth was driven by developers rushing to capitalise on the Interstate Transmission System (ISTS) charge waiver, which starts at 25 per cent and increases annually until full implementation in June 2028. With this, India's total installed renewable energy capacity, including large hydropower, has reached 234 GW. However, fossil fuels continued to account for around 75 per cent of the electricity generated in the first half of 2025, the report noted. 'India installed 22 GW of renewable energy capacity in the first half of 2025, a new record. However, the country is still banking heavily on coal to meet growing power demand, with plans to install an additional 80 GW of new thermal projects. India is not yet undergoing a true energy transition; instead, it is focusing on building up installed capacity from both conventional and renewable energy sources to ensure energy security. Without urgent action to improve affordability and sustainability, particularly through grid upgrades and energy storage, coal will remain central to electrification efforts, jeopardizing progress toward India's net-zero goals,' said Sushma Jagannath, Vice President of Renewables and Power Research at Rystad Energy. Battery Energy Storage Systems (BESS) also saw a major expansion, with a total of 7.6 GW allocated to developers. This includes 5.4 GW of collocated solar and BESS projects, and 2.2 GW of standalone BESS—India's highest BESS allocation to date. Average tariffs were ₹4,000 per megawatt-hour (MWh) for standalone BESS and ₹3,208 per MWh for collocated solar-BESS projects. Jindal Group secured 990 MW of collocated solar and BESS capacity, while NTPC and ReNew each won 900 MW. In the standalone BESS segment, JSW Energy was allocated 625 MW and Reliance Power secured 525 MW of collocated capacity. Adani Green Energy secured a 510 MW collocated solar and BESS project. State-wise, Rajasthan led the renewable capacity chart with 37.4 GW, including 32 GW of solar and 5.2 GW of wind. Gujarat followed with 35.5 GW (21.5 GW solar and 13.8 GW wind), while Tamil Nadu ranked third with 11.8 GW of wind and 10.6 GW of solar. Tamil Nadu also contributed 1 GW to the national bioenergy total of 11.6 GW. Other key contributors to onshore wind capacity included Karnataka (7.7 GW), Maharashtra (5.3 GW), Andhra Pradesh (4.4 GW), and Madhya Pradesh (3.2 GW). Rystad Energy stated that the strong BESS auction participation reflects growing attention to grid stability and renewable integration. It expects continued acceleration in the sector due to policy and market signals. Nuclear power also saw some expansion, with the commissioning of the 700 MW Unit 7 of the Rajasthan Atomic Power Project. The government has also approved the country's first small modular reactor (SMR) in Bihar. Despite the growth in renewables and storage, coal remains the mainstay of India's power mix, and its phase-down remains a critical challenge in achieving the country's net-zero targets.

Tata Power Renewable Energy secures BESS project for Kerala State Electricity Board
Tata Power Renewable Energy secures BESS project for Kerala State Electricity Board

Business Standard

time2 days ago

  • Business Standard

Tata Power Renewable Energy secures BESS project for Kerala State Electricity Board

NHPC (has been nominated as a Battery Energy Storage System (BESS) Implementing Agency (BIA) by Ministry of Power), through an International Bidding process, has selected Tata Power Renewable Energy (TPREL), a subsidiary of Tata Power Company for setting up BESS of capacity 30MW/120MWhr to be utilized by Kerala State Electricity Board (KSEBL) for optimizing their excess energy by storing it in the said storage asset. The said BESS asset shall be established at the Area code Substation of KSEBL located in Mulleria, District Kasaragod, Kerala. The estimated project cost is Rs 110 crore approximately.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store