Big firms abandon wind energy plans in Colombia amid regulatory shifts, social issues and grid gaps
Margarita Nieves, director of the Colombian Offshore Wind Research Network, told The Associated Press that despite large targets — including 1.1 gigawatts awarded in a 2019 auction — only two wind farms are partially operating today, with a combined capacity of less than 32 megawatts.
Colombia's Mining and Energy Planning Unit estimates the country could generate up to 18 gigawatts of wind energy — nearly double the nation's current installed electricity capacity of 20 gigawatts.
Several companies brought equipment and infrastructure to Colombia around 2021 before securing permits, but parks remain unbuilt. Key obstacles include limited grid connection infrastructure in La Guajira, recent regulatory changes that reduce financial returns and complex social and leadership challenges.
Colombia, Latin America's third-most populous country, has pledged to reach net-zero emissions by 2050. President Gustavo Petro, the country's first leftist leader, presents himself as an environmentalist and advocate of a just energy transition. Yet Colombia remains deeply reliant on fossil fuels — oil is its top export and a major source of government revenue.
In 2023, Italian multinational Enel withdrew from the Windpeshi onshore wind energy project in La Guajira. By late 2024, EDP Renewables canceled two major projects, Alpha and Beta, two large-scale onshore wind farms in the same region. In May, Colombian state-owned oil company Ecopetrol acquired nine solar and wind energy projects from Norway's Statkraft, marking the European firm's exit from the country. The portfolio spans La Guajira, Sucre, Cordoba, Caldas, and Magdalena, with a combined potential capacity of 1.3 gigawatts. Only one project is currently operational, with others expected to come online between 2026 and 2027.
The move is part of Ecopetrol's broader energy transition strategy to reduce reliance on oil and gas and meet net-zero goals by 2050. However, challenges like regulatory delays, governance concerns, and potential impacts on Colombia's fiscal stability raise questions about the transition's pace and economic effects.
Nieves warned that the situation is 'very concerning,' with only two of over 20 planned projects advancing. She stressed the need to speed up regulatory processes, improve consultations with Indigenous communities — notably the Wayuu in La Guajira — and ensure sufficient electrical infrastructure.
'Colombia has more than 20 years of delay in wind energy,' Nieves said. 'Brazil, in contrast, has built over 1,300 onshore wind farms in the last two decades and is a top global turbine producer.'
The wind energy projects were part of Colombia's just energy transition, aiming to replace fossil fuels with renewables while supporting vulnerable groups like Indigenous peoples. The region is home to Cerrejon, one of the largest open-pit coal mines in the world and a major player in Latin America's mining sector, which has been in operation since 1985. The mine has just nine years left in its life span, and its closure, without alternative plans in place, will deal a significant blow to the region's economy.
For Samuel Lanao, head of La Guajira's environmental authority, the main reason several licensed renewable energy projects are being sold off is because companies struggle with deep-rooted social tensions, particularly during the prior consultation process with local Indigenous communities. Lanao said confrontations have emerged between firms and residents, derailing expectations of development.
'This has been a major blow to La Guajira,' he said, 'as there were high hopes for economic and social progress through these projects.'
The Wayuu people , a seminomadic Indigenous group in the arid La Guajira region of northern Colombia and Venezuela, remain divided over wind energy development. While some have welcomed the economic support offered by companies building turbines on their ancestral lands, many others have raised concerns over environmental and cultural impacts, and a lack of meaningful prior consultation, in what is one of Colombia's poorest regions.
Diego Patron, manager of the Jemeiwaa Ka'I wind project, a large-scale wind farm cluster in La Guajira, acknowledged the pioneering nature of Colombia's early wind efforts, which began in a regulatory vacuum without clear institutional frameworks.
'These foundational projects faced a steep institutional and territorial learning curve, resulting in the loss of key strategic projects,' Patron said. 'However, their legacy now forms the cornerstone for new initiatives.'
Patron believes that barriers around legitimate Wayuu community representation, environmental permitting, and contract resolutions have been overcome, creating more stable conditions.'
Patron said misinformation deepened tensions and unfairly damaged firms like EDP that, he says, aimed to support communities.
___
The Associated Press' climate and environmental coverage receives financial support from multiple private foundations. AP is solely responsible for all content. Find AP's standards for working with philanthropies, a list of supporters and funded coverage areas at AP.org .
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Bloomberg
a day ago
- Bloomberg
Ecuador in Spat With Colombia Over Deportation of Prisoners
Ecuador's decision to deport hundreds of Colombian prisoners has stoked the ire of its neighbor, prompting the countries to trade accusations over the weekend. Colombia's foreign ministry on Friday called Ecuador's decision to deport the inmates without prior agreement a violation of international law and an 'unfriendly gesture.'
Yahoo
a day ago
- Yahoo
Ecuador deports more than 800 Colombian inmates as Bogota cries foul
Ecuadoran authorities said Saturday they had deported more than 800 Colombian prisoners via a land border crossing, after Bogota protested that the move came without prior agreement. In 2024, Ecuadoran President Daniel Noboa announced his intention to deport Colombian inmates to ease overcrowding in the country's prisons. Small groups were transferred starting in April. But Colombian President Gustavo Petro opposed the move, saying that a joint plan was needed to safeguard the prisoners' rights. More than 800 prisoners were deported through the Rumichaca border crossing in Carchi province, Governor Diana Pozo told reporters at the site. The inmates, wearing orange uniforms, waited in line to reenter their home country under the watchful eye of Ecuadoran police and military personnel. Early in the day, some in shorts and t-shirts did exercises while waiting for their turn to cross the border in the chilly Andean air, saying "We want to cross, we want to cross." On Friday, the government in Bogota lodged a formal complaint with Quito, saying such a move without prior agreement was a violation of international law and an "unfriendly gesture." A source in the Carchi governor's office who spoke to AFP on condition of anonymity said the mass deportation began on Friday, and the 870 inmates slated for expulsion represented about 60 percent of all Colombians in Ecuador's prisons. Juan Morales, an official in the Colombian town of Ipiales, said that authorities had to scramble to handle the influx of people, because Ecuador had not informed them of the deportations. Ecuador's foreign ministry said Saturday that Bogota was told about the plan on July 8. The mayor of the border town of Ipiales, Amilcar Pantoja, told the media on Friday that prisoners without pending legal cases in Colombia would be released. Drug trafficking gangs operating in Ecuador -- some involving Colombian criminals -- have turned the country into one of the most violent in Latin America. The homicide rate has jumped from six per 100,000 people in 2018 to 38 in 2024, among the highest in the region. sp/sst/ksb


CNN
a day ago
- CNN
Venezuelan baseball team denied visas into US, Little League International says
A Venezuelan baseball team was denied visas into the United States and will miss this year's Senior Baseball World Series, Little League International confirmed Friday. The Cacique Mara team, from Maracaibo, Venezuela, was scheduled to participate in the tournament after winning the Latin American championship in Mexico. 'The Cacique Mara Little League team from Venezuela was unfortunately unable to obtain the appropriate visas to travel to the Senior League Baseball World Series,' Little League International said in a statement, adding that it is 'extremely disappointing, especially to these young athletes.' The Venezuelan team traveled to Colombia two weeks ago to apply for their visas at the U.S. embassy in Bogotá. The embassy did not immediately respond to an Associated Press request for comment. 'It is a mockery on the part of Little League to keep us here in Bogotá with the hope that our children can fulfill their dreams of participating in a world championship,' the team said in a statement. 'What do we do with so much injustice, what do we do with the pain that was caused to our children?' Venezuela is among a list of countries with restrictions for entering the U.S. or its territories. President Donald Trump has banned travel to the U.S. from 12 other countries, citing national security concerns. Earlier in the month, the Cuban women's volleyball team was denied visas to participate in a tournament in Puerto Rico. 'They told us that Venezuela is on a list because Trump says Venezuelans are a threat to the security of his state, of his country,' said Kendrick Gutiérrez, the league's president in Venezuela. 'It hasn't been easy the situation; we earned the right to represent Latin America in the World Championship.' The Senior League Baseball World Series, a tournament for players aged 13-16, is played each year in Easley, South Carolina. It begins Saturday. The tournament organizers replaced the Venezuelans with the Santa Maria de Aguayo team from Tamaulipas, Mexico, the team that was a runner-up in the Latin American championship. 'I think this is the first time this has happened, but it shouldn't end this way. They're going to replace us with another team because relations have been severed; it's not fair,' Gutiérrez added. 'I don't understand why they put Mexico in at the last minute and left Venezuela out.'