Coal mine stalled in 'groundbreaking' climate decision
A community environment group from the NSW Hunter region successfully challenged an Independent Planning Commission decision to allow the expansion of the Mount Pleasant open-cut mine, near Muswellbrook.
Operator MACH Energy applied to deepen the mine and double its output, extending its life for 22 years to enable the extraction of an additional 406 megatonnes of coal.
The commission consented to the expansion in September 2022 and a judicial review brought by the community group was dismissed by the Land and Environment Court two years later.
Denman Aberdeen Muswellbrook Scone Healthy Environment Group took its fight to the Court of Appeal, arguing the environment court had erred and the commission failed to consider the likely climate effects in the region.
The Court of Appeal on Thursday found the commission had accepted the project's emissions would contribute to global climate change, but there was nothing in its reasons to indicate it had considered the local impacts.
The commission's consent referred to Australia's obligations under the Paris Agreement, noting that the mine's emissions would be "accounted for" in the countries where the coal was burnt.
"The commission's obligation to consider the likely impacts of the development on the natural and built environment in the locality of the mine ... required it to address the potentially adverse effects of climate change in the locality," the judgment said.
"This obligation could not be discharged by general references to the effects of global warming on the planet generally."
Environmental lawyer Elaine Johnson, the director of the firm that represented the community group, said the court's decision was groundbreaking.
"The NSW Court of Appeal has just confirmed that the local impacts of climate change on communities are a direct consequence of continued fossil fuel production in NSW," Ms Johnson said in a statement.
"From today, climate harm must be specifically considered when deciding proposals for fossil fuel expansions."
NSW Greens MP Sue Higginson also said it was a significant legal breakthrough.
"With this decision, the government must now reckon with the fact that they have a responsibility to the whole planet when it comes to allowing more coal to be dug up and burnt," Ms Higginson said.
"The status quo of setting emissions reduction targets domestically and then exporting the climate crisis is now broken with this decision."
The case will be returned to the Land and Environment Court to consider and MACH Energy was ordered to pay the costs of the appeal.
The company was contacted for comment.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Advertiser
a day ago
- The Advertiser
Trinity Point expansion approved after five-year wait
The largest development project outside of Sydney is one step closer to being built after a protected development application - five years in consideration - was approved on Friday. The $665-million expansion of the Trinity Point precinct at Lake Macquarie has been sold as "Australia's leading waterfront destination" and Lake Macquarie's answer to the Sydney Opera House, but has been mired in planning red tape for the past five years. Johnson Property Group founder Kieth Johnson, who has held the site for 25 years, said it was a relief to see approvals finally secured after a years-long wait that left investors in uncertainty. "We have had investors and potential joint venture partners wanting to talk to us, but we couldn't do a thing," Mr Johnson said. "We had nothing to guarantee until (Friday, August 1)." "Unfortunately NSW is the slowest state in Australia to get approvals." The luxury waterfront project will bring a resort experience to the shores of Lake Macquarie, complete with a cutting-edge wellness centre and two world-class restaurants, as well as 160 waterfront apartments, conference facilities, and commercial and public space in a sprawling precinct designed by boundary-pushing architect firm Koichi Takada. Mr Johnson, who is the same developer behind Lake Macquarie's Watagan Park project, said the project was aimed at city-siders looking to escape to the regions in the post-COVID era, adding that designs had reduced the number of apartments but increased their size to cater to changing market tastes. "People want to move to the country. They want to move, but they want bigger units," he said. "It's a really luxurious lifestyle." He now hopes that, with development approvals secured, the project will move to detail designs and ultimately to tender within the next year. He estimated it would be a three-year build after that. "This project is about putting Lake Macquarie on the global stage," Mr Johnson said. "We're not just building something beautiful we're creating a destination that will showcase the best of this region to the world and leave a lasting legacy for generations to come." An earlier planning document indicated the project would create 398 jobs and some $15.8 million in salaries. The largest development project outside of Sydney is one step closer to being built after a protected development application - five years in consideration - was approved on Friday. The $665-million expansion of the Trinity Point precinct at Lake Macquarie has been sold as "Australia's leading waterfront destination" and Lake Macquarie's answer to the Sydney Opera House, but has been mired in planning red tape for the past five years. Johnson Property Group founder Kieth Johnson, who has held the site for 25 years, said it was a relief to see approvals finally secured after a years-long wait that left investors in uncertainty. "We have had investors and potential joint venture partners wanting to talk to us, but we couldn't do a thing," Mr Johnson said. "We had nothing to guarantee until (Friday, August 1)." "Unfortunately NSW is the slowest state in Australia to get approvals." The luxury waterfront project will bring a resort experience to the shores of Lake Macquarie, complete with a cutting-edge wellness centre and two world-class restaurants, as well as 160 waterfront apartments, conference facilities, and commercial and public space in a sprawling precinct designed by boundary-pushing architect firm Koichi Takada. Mr Johnson, who is the same developer behind Lake Macquarie's Watagan Park project, said the project was aimed at city-siders looking to escape to the regions in the post-COVID era, adding that designs had reduced the number of apartments but increased their size to cater to changing market tastes. "People want to move to the country. They want to move, but they want bigger units," he said. "It's a really luxurious lifestyle." He now hopes that, with development approvals secured, the project will move to detail designs and ultimately to tender within the next year. He estimated it would be a three-year build after that. "This project is about putting Lake Macquarie on the global stage," Mr Johnson said. "We're not just building something beautiful we're creating a destination that will showcase the best of this region to the world and leave a lasting legacy for generations to come." An earlier planning document indicated the project would create 398 jobs and some $15.8 million in salaries. The largest development project outside of Sydney is one step closer to being built after a protected development application - five years in consideration - was approved on Friday. The $665-million expansion of the Trinity Point precinct at Lake Macquarie has been sold as "Australia's leading waterfront destination" and Lake Macquarie's answer to the Sydney Opera House, but has been mired in planning red tape for the past five years. Johnson Property Group founder Kieth Johnson, who has held the site for 25 years, said it was a relief to see approvals finally secured after a years-long wait that left investors in uncertainty. "We have had investors and potential joint venture partners wanting to talk to us, but we couldn't do a thing," Mr Johnson said. "We had nothing to guarantee until (Friday, August 1)." "Unfortunately NSW is the slowest state in Australia to get approvals." The luxury waterfront project will bring a resort experience to the shores of Lake Macquarie, complete with a cutting-edge wellness centre and two world-class restaurants, as well as 160 waterfront apartments, conference facilities, and commercial and public space in a sprawling precinct designed by boundary-pushing architect firm Koichi Takada. Mr Johnson, who is the same developer behind Lake Macquarie's Watagan Park project, said the project was aimed at city-siders looking to escape to the regions in the post-COVID era, adding that designs had reduced the number of apartments but increased their size to cater to changing market tastes. "People want to move to the country. They want to move, but they want bigger units," he said. "It's a really luxurious lifestyle." He now hopes that, with development approvals secured, the project will move to detail designs and ultimately to tender within the next year. He estimated it would be a three-year build after that. "This project is about putting Lake Macquarie on the global stage," Mr Johnson said. "We're not just building something beautiful we're creating a destination that will showcase the best of this region to the world and leave a lasting legacy for generations to come." An earlier planning document indicated the project would create 398 jobs and some $15.8 million in salaries. The largest development project outside of Sydney is one step closer to being built after a protected development application - five years in consideration - was approved on Friday. The $665-million expansion of the Trinity Point precinct at Lake Macquarie has been sold as "Australia's leading waterfront destination" and Lake Macquarie's answer to the Sydney Opera House, but has been mired in planning red tape for the past five years. Johnson Property Group founder Kieth Johnson, who has held the site for 25 years, said it was a relief to see approvals finally secured after a years-long wait that left investors in uncertainty. "We have had investors and potential joint venture partners wanting to talk to us, but we couldn't do a thing," Mr Johnson said. "We had nothing to guarantee until (Friday, August 1)." "Unfortunately NSW is the slowest state in Australia to get approvals." The luxury waterfront project will bring a resort experience to the shores of Lake Macquarie, complete with a cutting-edge wellness centre and two world-class restaurants, as well as 160 waterfront apartments, conference facilities, and commercial and public space in a sprawling precinct designed by boundary-pushing architect firm Koichi Takada. Mr Johnson, who is the same developer behind Lake Macquarie's Watagan Park project, said the project was aimed at city-siders looking to escape to the regions in the post-COVID era, adding that designs had reduced the number of apartments but increased their size to cater to changing market tastes. "People want to move to the country. They want to move, but they want bigger units," he said. "It's a really luxurious lifestyle." He now hopes that, with development approvals secured, the project will move to detail designs and ultimately to tender within the next year. He estimated it would be a three-year build after that. "This project is about putting Lake Macquarie on the global stage," Mr Johnson said. "We're not just building something beautiful we're creating a destination that will showcase the best of this region to the world and leave a lasting legacy for generations to come." An earlier planning document indicated the project would create 398 jobs and some $15.8 million in salaries.

Sydney Morning Herald
3 days ago
- Sydney Morning Herald
What's in a number? New carbon target sparks new climate warfare
Our free Environment newsletter is sent every second Wednesday. Below is an excerpt. Sign up to get the whole newsletter delivered to your inbox. Casual observers of federal parliament might this week have been startled by a sudden resumption of conflict over climate, but the timing was no accident. Australia, like the rest of the world, is due to set its 2035 carbon-emission reduction target under the Paris Agreement. As a result, Canberra is crawling with those who have an interest in influencing that target (or Nationally Determined Contribution, more on which shortly). Setting the scene for many turning their attention to parliament as it resumed for the Albanese government's second term, were Nationals MPs Barnaby Joyce and Michael McCormack, who introduced a private members' bill to have Australia abandon entirely the effort to cut emissions in line with the Paris Agreement. Also in Canberra this week was Simon Stiell, the UN's chief climate diplomat or, more properly, executive secretary of the United Nations Framework Convention on Climate Change. He has been travelling the world urging nations to submit ambitious targets that will keep Paris Agreement goals within reach. Far too careful a diplomat to recommend an Australian target, he has been making the case that, on economic and security grounds, Australia should be ambitious. 'Bog standard is beneath you … Go for what will build lasting wealth and national security,' he said in a speech in Sydney before travelling to Canberra. 'Go for what will change the game and stand the test of time.' So, what's a Nationally Determined Contribution? When world governments signed the Paris Accord almost a decade ago they agreed that to halt climate change before catastrophic tipping points kicked in, warming needed to be arrested below 2 degrees and as close as possible to 1.5 degrees.

The Age
3 days ago
- The Age
What's in a number? New carbon target sparks new climate warfare
Our free Environment newsletter is sent every second Wednesday. Below is an excerpt. Sign up to get the whole newsletter delivered to your inbox. Casual observers of federal parliament might this week have been startled by a sudden resumption of conflict over climate, but the timing was no accident. Australia, like the rest of the world, is due to set its 2035 carbon-emission reduction target under the Paris Agreement. As a result, Canberra is crawling with those who have an interest in influencing that target (or Nationally Determined Contribution, more on which shortly). Setting the scene for many turning their attention to parliament as it resumed for the Albanese government's second term, were Nationals MPs Barnaby Joyce and Michael McCormack, who introduced a private members' bill to have Australia abandon entirely the effort to cut emissions in line with the Paris Agreement. Also in Canberra this week was Simon Stiell, the UN's chief climate diplomat or, more properly, executive secretary of the United Nations Framework Convention on Climate Change. He has been travelling the world urging nations to submit ambitious targets that will keep Paris Agreement goals within reach. Far too careful a diplomat to recommend an Australian target, he has been making the case that, on economic and security grounds, Australia should be ambitious. 'Bog standard is beneath you … Go for what will build lasting wealth and national security,' he said in a speech in Sydney before travelling to Canberra. 'Go for what will change the game and stand the test of time.' So, what's a Nationally Determined Contribution? When world governments signed the Paris Accord almost a decade ago they agreed that to halt climate change before catastrophic tipping points kicked in, warming needed to be arrested below 2 degrees and as close as possible to 1.5 degrees.