Perth Swallow Roundabout improvement delays "inexcusable"

Perth Swallow Roundabout improvement delays "inexcusable"

Daily Record04-07-2025
There have been several accidents since the new layout was introduced in March with confusing road markings and signs
Following several accidents, a Carse of Gowrie ward councillor finds it "inexcusable" recommended changes have not yet been made to make a roundabout safer.
In March 2025 a road safety audit highlighted several issues with the new road layout at the Swallow Roundabout next to Invergowrie, on the edge of Dundee and road users have raised a number too.

But many have still to be addressed and Cllr Angus Forbes fears it "may just be a matter of time" before someone is injured at the roundabout.

Approaching the roundabout from Perth, all three lanes have arrows painted on them pointing straight ahead. It is only when you are actually on the roundabout, the third lane has an arrow pointing right, resulting in some A90 northbound vehicles cutting into the middle lane at the last minute.
The traffic lights are equally confusing with "no left turn" and "no right turn" signs on them, giving the impression you can only go straight ahead - despite road signage saying otherwise.
As for the signs, they too have caused confusion. Approaching the roundabout from Perth, drivers are told there are two lanes which point straight on. It is only when the third lane appears, there is another sign saying there are three lanes and drivers can turn right towards Dundee/Invergowrie.
The signs also warn road users of "new traffic signals ahead" but not of a "new roundabout layout ahead".
Cllr Angus Forbes is "astounded that something so simple can take so long to put right".
He has asked when the safety audit recommendations will be put into place.

The Conservative councillor said: "In regard to the incorrect signage on approach to the roundabout from Perth, I am totally perplexed and pretty angry that such a simple fix which everyone agrees should be made has taken so long and is still not fixed. I am aware that accidents have already happened on this roundabout; thankfully none of them involved injury but it may just be a matter of time.
"When a safety audit throws up an issue which is simple to fix, for the changes not to have been made - months after the audit was performed - is simply inexcusable."

The Swallow Roundabout layout changes were part of the planning conditions - set by Dundee City Council - for the Western Gateway development, which housebuilder Springfield was asked to make. The developer appointed Luddon Construction Ltd to carry out the works.
According to Springfield, the findings of the March safety audit are currently "under review" but have "nearly concluded".
A Springfield spokesperson said: "The findings of the safety audit are under review by the roundabout designer and Transport Scotland to decide what measures should be taken to address the findings. We understand this part of the process has nearly concluded and look forward to learning the outcome. "

Transport Scotland is hopeful resolution works can be "agreed and implemented soon".
A spokesperson for Scotland's national transport agency said: "We are aware of the observations in the independent road safety audit carried out by the developer and any post-construction review observations, including those made by road users regarding road markings and signs. The developer is considering how to address them. The developer and their designer, along with Amey and the roads authorities, are working together to resolve these matters. This process is ongoing, and resolutions will hopefully be agreed and implemented soon. Transport Scotland will continue to work with the developer to help resolve these issues as quickly as possible.'
Amey said Western Gateway residents were "strongly supportive" of the measures taken to improve active travel provision at the busy junction. Pedestrians and cyclists can now use the traffic lights to go straight through the middle of the roundabout to cross to the other side.
The Amey spokesperson said: "The Western Gateway Community Group is strongly supportive of benefits the roundabout redesign has provided. Bill Batchelor, chair of the group has commented that: 'Prior to the construction of this junction, there was no suitable access for Western Gateway residents into Dundee, with the only route being a secluded, unlit path behind the Swallow and through the underpass. The new infrastructure has significantly improved safety and accessibility. It provides a much needed lifeline for those who walk or wheel'.
"Supported by Amey, the operating company for the North East Trunk Road network, Transport Scotland are working with all parties, including Springfield, their design consultant and Dundee City Council to ensure that any changes at Swallow Roundabout identified in the safety audit or reported by members of the public are fully considered. Any changes from the original design is a complex process involving consultation with a range of parties to identify the most effective solution, which will be progressed as quickly as possible.
"Adjustments have already been made to the traffic light sequencing and initial monitoring has shown a reduction in journey times on the A90 eastbound approach to the junction. Monitoring will continue, and further adjustments will be made as necessary to optimise the signal phasing."
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Erskine Bridge weekend closure planned as roadworks set to begin
Erskine Bridge weekend closure planned as roadworks set to begin

Daily Record

time2 days ago

  • Daily Record

Erskine Bridge weekend closure planned as roadworks set to begin

The carriageway on the northbound carriageway of the Erskine Bridge will be closed for a full weekend next month as work to resurface and replace crucial joints begins. A carriageway on the Erskine Bridge is set to shut for an entire weekend as resurfacing and crucial joint replacement work begins next month. ‌ The route will be closed northbound from 8pm on Friday, August 8, until 6am on Monday, August 11, as Amey, acting on behalf of Transport Scotland, undertakes the work. ‌ Drivers are being encouraged to plan their trips ahead of time and consider alternative routes or follow signed diversions during the work. ‌ The southbound A898 Erskine Bridge will operate with a single lane closure. Access for emergency services will be maintained. This work forms part of a £100,000 investment in the infrastructure of the A898 Erskine Bridge and will enhance the condition of the bridge joints and the road surface there. ‌ Drivers will be advised to adhere to an agreed diversion route as several key roads will be shut. Road closures will be implemented at the M8 Junction 30 westbound off-slip to M898 northbound; A898/M898 northbound; A898 northbound slips to Great Western Road (both northbound and southbound); and the A898 northbound on-slip to Erskine Bridge. A single lane closure will also be necessary on the A898 southbound carriageway, and there will be a closure of the A82 southbound off-slips to Erskine Bridge. ‌ A signed diversion for northbound traffic will reroute vehicles. Eastbound M8 traffic from Greenock/Port Glasgow will continue on the eastbound M8 to the Kingston Bridge and then take the M8 Junction 17 off-slip (Charing Cross, Glasgow) to join the westbound A82 (Great Western Road). Westbound traffic aiming to reach the A898 Erskine Bridge will be directed to turn at the M8 Junction 31 off-slip (West Ferry Interchange) to join the same eastbound diversion. ‌ Westbound M8 traffic (from Glasgow towards M898) planning to cross the A898 Erskine Bridge should follow the M8 to Kingston Bridge and then take the M8 Junction 17 off-slip (Charing Cross, Glasgow) to join the westbound A82 (Great Western Road). Westbound M74 traffic (towards M898) intending to cross the A898 Erskine Bridge should exit at M74 Junction 1 (towards Kinning Park) and follow local signs to the westbound A82 (Great Western Road). ‌ Northbound M77 traffic (towards M898) planning to cross the A898 Erskine Bridge should continue on the eastbound M8 and follow local signs to join the westbound A82 (Great Western Road). For those travelling on the southbound carriageway, the Erskine Bridge southbound on-slip from A82 westbound will be closed from 6am on Saturday, August 9, until 8pm on Sunday, August 10. Westbound A82 traffic aiming to head south on the A898 Erskine Bridge will be rerouted to continue west to Dunglass Roundabout, before returning eastbound to join the southbound A898 Erskine Bridge traffic. ‌ The Erskine Bridge southbound slip road from A82 eastbound will be shut from 8pm until 6am on both nights of Friday, August 8, and Sunday, August 10. Eastbound A82 traffic planning to head south on the Erskine Bridge will be diverted via Kilbowie Roundabout and access Erskine Bridge from A82 westbound. Local access to Erskine will be maintained via the B815 and the A726. Eastbound traffic from Greenock/Port Glasgow will carry on the eastbound M8 to Junction 30 to reach Erskine via the A726. ‌ Westbound M8 traffic (from Glasgow to M898) wishing to get to Erskine from the M8 will be redirected at the M8 Junction 31 off-slip road (West Ferry Interchange) to follow the eastbound diversion to the A726. Local Erskine traffic intending to reach the A82 Great Western Road, will be rerouted at the A726 Spectacles Roundabout and join the southbound M8 off-slip road to the eastbound M8 and continue to the M8 Kingston Bridge Junction 17 off-slip road to join the westbound A82 (Great Western Road). Local access to Erskine, north of the A898 Erskine Bridge, will be facilitated via the A726 leading to the A8 Greenock Road. From there, drivers should follow Inchinnan Road/Gleve Street/Glasgow Road/Renfrew Road/Shieldhall Road and proceed through the Clyde Tunnel, continuing on Crow Road to join the westbound A82 (Great Western Road). Motorists are encouraged to explore alternative routes where feasible to bypass the M898/A898 during the period of these works.

Blue Badge renewal tip means parking permit is always valid and never at risk of fine
Blue Badge renewal tip means parking permit is always valid and never at risk of fine

Daily Record

time2 days ago

  • Daily Record

Blue Badge renewal tip means parking permit is always valid and never at risk of fine

Local councils across Great Britain issue Blue Badges to people for up to three years. The latest statistics from the Department for Work and Transport and Transport Scotland show that there are currently more than 2.8 million Blue Badge holders in England (2.57m) and Scotland (235,779). The Scottish figure may be much higher as the most recent data was published in November 2021. ‌ The UK Government recently confirmed that 90 per cent of all Blue Badge applications are being made through the online service. For users of the scheme due to renew this year they may not be aware of a nifty way to ensure a seamless transition from the old badge to the new one which ensures the permit is always valid. ‌ Badge holders are advised to renew 12 weeks before the expiry date, however, doing it earlier has no impact on your existing Blue Badge as the start date will be the day after the current one expires. ‌ Blue Badge holders could face a hefty £1,000 fine if they continue to display it after it has expired. This is because displaying an out of date Blue Badge is classed as 'misuse'. Transport Scotland guidance states: 'Misuse of a badge is a crime. You may be prosecuted if you misuse a badge.' It's also worth noting that once you have completed the renewal process online, which involves providing details of your existing Blue Badge, personal details and eligibility criteria, you will receive an email confirming whether or not you have been successful. If you have, the email will also include instructions on making the Blue Badge payment to your local council - in Scotland this is £20. It costs up to £10 in England and is free in Wales. ‌ Once the payment has been made, you will then receive an email from the Department for Work and Transport confirming that your Blue Badge has been ordered and will arrive within 10 working days. The email also include: Name of your local authority issuing the Badge Badge number Badge start date Badge expiry date ‌ If your Blue Badge is due to expire in September or October, you can renew it now and have peace of mind that you won't forget - or run the risk of a fine. Eligibility for a Blue Badge is also reviewed every time a renewal application is submitted. Guidance on explains: 'Your Blue Badge is not renewed automatically. You need to reapply for it every 3 years. ‌ 'Your eligibility will be checked every time you reapply. This is to make sure you can still get a Blue Badge. Your local council processes your application and decides if you can get a Blue Badge. 'You should reapply 12 weeks before your badge expires.' The eligibility criteria for a Blue Badge was extended in 2019 to include individuals with non-visible disabilities such as Parkinson's, dementia and epilepsy to help more people park closer to the places they want to go when they travel as a driver, or a passenger. ‌ How to renew a Blue Badge online You will need a recent digital photo showing your head and shoulders. You will also need a photo or scan of your: ‌ proof of identity (such as a birth certificate, passport or driving licence) proof of address (such as a Council Tax bill or government letter) proof of benefits (if you get any) You will also need to know: your National Insurance number (if you have one) the details of your current Blue Badge ‌ You can start the application online and save the information you enter if you need to look for the required documents. You can easily return to it later and complete the process. Change of details You should contact your local council if there's a change to your: name address council area contact details ‌ Top 10 things to remember when using your Blue Badge You must follow the rules when using your Blue Badge, if you don't you are committing a crime You can only use your Blue Badge as a driver or passenger No-one else should use your badge if you are not in the vehicle with them If you are not getting out of the vehicle, you should not use your Blue Badge to get a parking space You must not let other people use your badge You must display your Blue Badge the right way up so the number can be seen clearly and your photo is face down You must apply for a new badge before your old badge runs out If your badge gets damaged you must apply for a new one Keep your badge safe. If it is lost or stolen, you must tell the police and the Local Council Check signs to make sure that Blue Badge holders are allowed to park there

Ayrshire motorists warned of A77 lane closures for two and a half weeks
Ayrshire motorists warned of A77 lane closures for two and a half weeks

Daily Record

time4 days ago

  • Daily Record

Ayrshire motorists warned of A77 lane closures for two and a half weeks

Ayrshire motorists warned of A77 lane closures for two and a half weeks Lanes will be closed on the A77 between Kilmarnock and Ayr to allow for footpath resurfacing next month. (Image: Google Maps) Motorists in Ayrshire are being warned to expect disruption on the A77 for two and a half weeks next month. ‌ Resurfacing work is being carried out on the footpath at Ladykirk, around 2.5 miles north of the Dutchhouse Roundabout between Kilmarnock and Ayr, from Monday, August 11. ‌ As a result, nearside lane closures will be in place between the Kilmarnock Road footbridge and Monkton Road for the duration of the works which are scheduled to end on Friday, August 29. ‌ The works were originally due to start on Monday, July 28 but trunk road operator Amey confirmed they had been delayed "due to operational issues". Download the Ayrshire Live app today The Ayrshire Live app is available to download now. Get all the local news in your area – plus features, football news and the latest on the coronavirus crisis – at your fingertips 24/7. The free download features the latest breaking news and exclusive stories while you can customise your page with the sections that matter to you. The Ayrshire Live app is available to download now on iOS and Android. A spokesperson for Amey said: "Amey, on behalf of Transport Scotland, is undertaking essential footway renewals on the A77 southbound at Ladykirk, 2.5 miles north of Dutchhouse Roundabout from Monday, August 11 until Friday, August 29. ‌ "This work will require a 24 hour nearside lane closure for the duration between Kilmarnock Road footbridge and Monkton Road. "Access for emergency service vehicles will be maintained throughout these works. "Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable. ‌ "This scheme will benefit pedestrians using this route each day, by improving the safety and condition of the footways in this area. "Road users are thanked for their patience and understanding while this work is being undertaken." Originally due to take place between Monday, July 28 and Friday, August 8, the works have been delayed and extended to take place over 18 days and not 11 days. Article continues below Amey have not confirmed if lane closures will affect both carriageways or only one. Don't miss the latest Ayrshire headlines – sign up to our free daily newsletter

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store