Muscat Municipality Chairman reviews progress on Al Ansab–Al Jifnain road dualisation: 58% complete
This major infrastructure project aims to ease traffic congestion and support the area's growing needs. The 15-kilometre route involves expanding the existing single-lane road from Falaj Al Sham Roundabout into a dual carriageway with three lanes in each direction. The project also includes converting four roundabouts into multi-level interchanges, constructing three flyovers connected to the Al Jifnain Bridge, and installing smart traffic signal systems at key intersections to improve traffic flow and safety.
The scope also encompasses 20 kilometres of service roads adjacent to the main carriageway, the installation of box culverts for stormwater and wadi drainage at critical points, and the relocation and protection of utility lines to prevent disruption to progress.
His Excellency commended the project team and the contractor for their dedication, noting that work has reached 58 per cent completion, which is ahead of expectations. He said this progress reflects strong on-site supervision and effective coordination between all parties, which could lead to the project finishing ahead of schedule in August 2026.
The Al Ansab to Al Jifnain Road Dualisation Project was awarded in September 2023, with an expected execution period of 36 months. It forms part of a wider programme of strategic development projects in Muscat Governorate, in line with Royal directives to improve road infrastructure and enhance connections between Muscat and other governorates.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Zawya
26 minutes ago
- Zawya
The AI revolution won't wait – and neither should we
The AI revolution is advancing at light speed around the world, impacting every industry, driving economic growth, and reshaping how we live and work. In Africa, the pace of technological adoption and innovation is inspiring—as AI-powered tools are being applied to agriculture, healthcare, finance, and much more. It's certainly no surprise, as Africa has many of the key ingredients to be a global player in data and AI: a young, tech-savvy population rich in entrepreneurial talent; established and expanding digital ecosystems (just look at mobile money, pioneered in Africa and now a global phenomenon); and ample land for building infrastructure like data centres. All this AI-related potential, however, relies on data processing —and data processing relies on energy. And, on a continent that continues to struggle with delivering reliable and affordable power, the urgency of this critical issue cannot be overstated. For example, Kenya's industrial sector alone accounts for over 50 percent of total electricity consumption, highlighting how crucial reliable power is for manufacturing and large-scale economic growth. Both the United Nations and the African Development Bank Group highlight that access to reliable, affordable, and sustainable energy are the lynchpin to ushering in an age of industrialisation, economic growth, and prosperity across the continent. AI is clearly not a short-term craze; it's a game-changer for the long-term that demands immense processing power. That's why hyperscale data centres are being built at a rapid pace in North America, Europe, and Asia. Used to train large AI models and operate cloud services, these facilities don't just use power, they devour it. Operating 24/7, data centres require stable, high-capacity baseload energy to keep servers running, data flowing, and cooling systems functioning. Globally, the International Energy Agency reported that data transmission networks consumed 260-360 TWh in 2022, or to put another way, that is 1-1.5 percent of global electricity use. While renewables like solar and wind are critical for long-term sustainability, their intermittent nature means they can't shoulder the load alone, especially in regions with limited storage or grid flexibility. If Africa is to compete globally in AI and cloud computing, energy strategies must put reliability and scale at the centre of infrastructure planning. The solution lies in pragmatism and scalability. Africa needs a diversified energy strategy that combines natural gas with renewables. Gas-fired power offers a reliable, on-demand energy source capable of delivering the baseload power data centres require. It emits 50 percent less CO2 than coal and is more scalable than renewable solutions today. At the same time, renewables must remain central to the continent's energy future. Solar and wind can be deployed 'behind the meter'—directly on or near data centre sites—to supplement gas and reduce emissions. This hybrid approach allows for energy resilience while accelerating the transition to a cleaner energy mix. Innovative models are already emerging on the continent. Project Spark, for example, is combining a liquid natural gas (LNG) multiuser port in Walvis Bay, Namibia, with vast land resources to develop LNG infrastructure and power plant that can deliver dependable power throughout the region. With an eye toward scalability and speed, it shows how targeted energy development can catalyse digital transformation across the continent. This kind of forward-looking investment is what Africa needs more of—not just more power, but the right kind of power in the right places. Data centres don't just need megawatts; they need planning, precision, and policy alignment to succeed. And that success depends on a balanced energy strategy, one that prioritises reliability and scalability alongside sustainability. By 2026, half of the world's hyperscale data centres will be in North America, while Africa still accounts for less than 1 percent. Africa must confront these issues head-on, by building energy and data infrastructure, or risk missing the window to lead. The opportunity is there but it demands urgency and coordinated action. For the energy needed to power the future—not just homes and hospitals but also the AI tools that will shape the next century—governments, investors, and the private sector must align around infrastructure that supports long-term digital competitiveness. Building world-class data centres is not only about technology, it's about creating jobs, stimulating industrial growth, and reducing electricity costs through large-scale, dependable infrastructure that serves both economic and human needs. Just as Africa revolutionised global banking through mobile money, the continent is now on the cusp of leading the next wave of digital transformation. But that future depends on energy systems that are built to scale, built to last, and built with balance in mind. What it needs now is the will and effective collaboration between the governments and the private sector to build the energy infrastructure necessary to match its ambitions, including power plants with renewables, updated transmission lines, more undersea cables to increase our connectivity to the world, and efficient storage systems. By embracing a hybrid energy approach and making strategic decisions to fund investments like Project Spark, Africa can create an energy foundation that not only powers data centers, but powers opportunity—for innovation, jobs, and inclusive economic growth. The AI revolution won't wait. And neither should we. Herta von Stiegel is the Founder & CEO of Ariya Capital Group, Chairperson of Britam Asset Managers (Kenya) and Daniel R. Weber is a Communications Consultant for Ariya Capital Group. © Copyright 2022 Nation Media Group. All Rights Reserved. Provided by SyndiGate Media Inc. (


Zawya
an hour ago
- Zawya
Egypt: Tanmeyah develops El Zaharaa Square in Maadi as part of ESG strategy
Arab Finance: Tanmeyah, a subsidiary of EFG Holding, has developed El Zaharaa Square in Maadi as part of its environmental, social, and governance (ESG) strategy focused on environmental sustainability and community development, as per an emailed press release. Located at the intersection of Al Zahraa Street and El Khamseen Street, the 8,600-square-meter square is one of the largest public spaces in Greater Cairo. Its location in Maadi, where Tanmeyah is headquartered, made it a practical choice for the company's latest urban development effort. The project was implemented in coordination with several government bodies, including the Cairo Governorate, the Office of the Deputy Governor for South Cairo, the Al Basateen and Al Maadi District Authorities, the National Organization for Urban Harmony, and the Cleaning and Landscaping Authority. It was carried out under the patronage of the Financial Regulatory Authority (FRA). The initiative follows Tanmeyah's previous collaboration with the Al Basateen District and the National Organization for Urban Harmony in December 2024 to redevelop Palestine Square and Ahmed Abd El-Azeem Street in Al Maadi. © 2025 All Rights Reserved Arab Finance For Information Technology Provided by SyndiGate Media Inc. (


Zawya
2 hours ago
- Zawya
Top firms bid for Oman's Musandam Airport construction works
Several local and international companies have submitted bids for the pre-qualification of contractors for the design and construction of enabling works to the Proposed Musandam Airport in the Wilayat Khasab in Musandam Governorate. Around 20 companies, including some prominent names in Oman's infrastructure development, submitted their bids before the deadline to do so on July 28. The final design of the proposed airport has been completed. The tender was floated by the Civil Aviation Authority (CAA). As per earlier reports, Musandam Airport is expected to be ready in 2028, and the project assumes significance due to operational challenges facing the current Khasab Airport, especially the possibility of operating services for 24 hours. The project will be divided into phases. The first stage will include a 45-metre-wide runway. A passenger building (to handle 250,000 passengers annually) will be constructed in addition to an air traffic control tower, runway (2,520 metres long and 45 metres wide), taxiways, a fire station, equipment repair shops, a marine rescue station, and parking lots for aircraft. There will be a new road 7-km leading to the airport. In the second phase, the runway will be expanded to 3,300 metres, capable of Airbus 330s, 350s, and Boeing 787s and 777s, in addition to increasing the number of taxiways and parking lots for aircraft, an aircraft isolation yard, and the terminal building (if required). It may be noted that CAA has plans for specialised companies for site selection studies, master plans, design, and supervision for the proposed development of Al Jabal Al Akhdhar, Masirah, and Suhar airports. The Civil Aviation Authority (CAA) has issued tenders for site selection studies, master plans, design, and supervision for the development of an airport in Masirah. 2025 © All right reserved for Oman Establishment for Press, Publication and Advertising (OEPPA) Provided by SyndiGate Media Inc. (