Why flyovers in Ahmedabad cost more than planned

Why flyovers in Ahmedabad cost more than planned

Time of India6 days ago
Ahmedabad: The Ahmedabad Municipal Corporation (AMC) and Ahmedabad Urban Development Authority (AUDA) have struggled with delays and cost escalations in their infrastructure projects over the past decade.
Construction of flyovers, railway overbridges, and underpasses has been marred by design changes that have increased project costs and timelines. An analysis of 10 major infrastructure projects reveals a pattern of poor planning, lack of coordination between agencies and mid-project design changes that have collectively added crores to the public exchequer while leaving citizens waiting for completion.
1. I-T flyover: Three disputes drive up costs
Despite the Central Road Research Institute (CRRI) recommending a four-lane, 16.50-metre-wide flyover on priority, AMC constructed a five-lane bridge spanning 20.50 metres.
The project cost ballooned from the estimated Rs 59.59 crore to Rs 65.51 crore. An additional Rs 10 crore was spent on special steel structure to preserve Gandhi's statue beneath the bridge, highlighting the lack of comprehensive site surveys during the planning phase.
You Can Also Check:
Ahmedabad AQI
|
Weather in Ahmedabad
|
Bank Holidays in Ahmedabad
|
Public Holidays in Ahmedabad
2. Ranip flyover: Land dispute, two-yr-setback
What began as a 24-month project in 2013 stretched to five years due to regulatory hurdles. The Ranip GST crossing flyover construction was delayed by a year initially due to lack of approval from the railways.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Ada jeragat, terus nampak tua! Minum ni je, beli kat Guardian
URUHIME MOMOKO
Undo
The project required 5,000 sq m of railway land, which the railways withheld for two years. Eventually, AMC had to arrange a land exchange deal costing Rs 50 crore to proceed with construction.
3. Ajit Mill junction: Oversight delays project
The Ajit Mill junction flyover, initially estimated at Rs 41 crore, was tendered for Rs 50.30 crore. Despite its inauguration in Dec 2021, the project faced over a year's delay when construction workers discovered a major water trunk line beneath the site.
This necessitated design changes and halted work.4.
4. Pallav flyover: High-tension line added Rs 18cr
Approved for Rs 64 crore in 2017, the project was eventually tendered for Rs 104.16 crore. Moving high-tension power lines underground added approximately Rs 18 crore to the budget. The CSIR report did not recommend a flyover at Naroda Pallav junction, yet AMC proceeded with construction. The project was inaugurated in May 2025, two years behind schedule.
5. Dehgam Circle flyover: Two-year delay
Poor coordination between Auda and Gujarat Energy Transmission Corporation Limited (GETCO) led to a two-year delay in the SP Ring Road's Dehgam Circle flyover. Work was halted midway to shift high-tension power lines underground. Despite Auda depositing funds with GETCO, underground work did not start for two years, pushing the completion date well beyond the original Jan 1, 2021 deadline.
6. Ghuma-Shej flyover: Rs 80cr project unused
Six years ago, Auda began work on a railway overbridge connecting Ghuma and Shej, costing Rs 80 crore. Although completed six months ago, one end of the bridge remains closed due to private land and compound walls, preventing its use for traffic.
7. Panjrapol flyover: Direction changed
The Panjrapol flyover project faced directional changes that sparked public debate.
Initially, CRRI-CSIR recommended a split flyover with two lanes each at Navrangpura Panjrapol junction. However, an IITRAM report led to a decision to construct the flyover from the govt polytechnic college towards IIM-A, requiring a new tender before work began.
8. Hatkeshwar flyover: Poor quality, to be razed
The standing committee approved the demolition of the poor-quality Hatkeshwar flyover bridge in the Khokhra area, built for Rs 34 crore, which deteriorated within five years.
It will be demolished at a cost of Rs 3.90 crore. This is the first time in AMC's history that a flyover is being demolished due to poor construction quality within five years of completion.
9. Jalaram underpass: Open-shut case
The underpass in Paldi was inaugurated by the CM on March 4, 2024, only to be closed to the public within hours. The inauguration proceeded despite incomplete work, including pending tower removal.
The project cost escalated from Rs 45 crore to Rs 83 crore due to utility relocation and other works.
10. Sattadhar flyover: Defect liability dispute
The under-construction Sattadhar junction flyover, approved at Rs 81.49 crore in April 2023, has been embroiled in defect liability disputes. Initially set at three years, the defect liability period was extended to five years following the Hatkeshwar bridge controversy. But when the contractor demanded more money or tender cancellation, the standing committee reverted to the three-year liability period within a month.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Odisha approves ‘Samrudha Sahar' scheme
Odisha approves ‘Samrudha Sahar' scheme

Hans India

time21 minutes ago

  • Hans India

Odisha approves ‘Samrudha Sahar' scheme

Bhubaneswar: The Odisha government on Wednesday approved 'Samrudha Sahar', a new scheme aimed at promoting planned urbanisation and balanced regional development across the State. The State Cabinet meeting, chaired by Chief Minister Mohan Charan Majhi, approved the scheme. The Cabinet has also approved another 12 proposals during the meeting, Chief Secretary Manoj Ahuja said. With a total outlay of Rs 4,879.30 crore, the initiative marks a significant step toward realising Odisha's goal of becoming a developed State by 2036, Ahuja said. The scheme will not only improve infrastructure and urban governance but also create new avenues for employment, private sector investment and industrial expansion, he said. As part of Viksit Odisha 2036 vision, this scheme is designed to transform cities into dynamic growth hubs and engines of economic progress, he said. The scheme comprises two key components: Town Planning Scheme and Cities as Growth Hubs. With an allocation of Rs 4,114 crore, the Town Planning Scheme is expected to significantly enhance land and asset management while promoting sustainable development, Ahuja said. He said the second component, with an investment of Rs 765.30 crore, aims to position urban areas as centres of economic transformation. The Cabinet has also approved a second amendment to the Odisha Semiconductor Manufacturing and Fabless Policy-2023. This amendment introduces a more robust package of incentives and refined provisions, aimed at enhancing the viability and sustainability of semiconductor projects, especially in this capital-intensive and high-technology sector, the Chief Secretary said. He said that the government has also approved a proposal to waive off the fees of about 45,000 boarders of 455 hostels (141 Girls & 314 Boys) in Odisha Adarsha Vidyalayas. The students are paying Rs 2,000 per month for staying in the hostels. Total financial implication for the proposal is Rs 349.20 crore for 5 years (from April 2025 to March 2030), he added. The government has also decided to bifurcate the existing Mayurbhanj Police District and carve out a new police district with headquarters at Rairangpur for effective policing and efficient public service delivery in both these police districts.

Perplexity CEO Aravind Srinivas dares Google to pick a side as AI browser battle heats up
Perplexity CEO Aravind Srinivas dares Google to pick a side as AI browser battle heats up

India Today

time21 minutes ago

  • India Today

Perplexity CEO Aravind Srinivas dares Google to pick a side as AI browser battle heats up

In a fiery Reddit "Ask Me Anything" session, Perplexity AI CEO Aravind Srinivas didn't hold back in his assessment of Google's future, or lack thereof, in the evolving landscape of AI-powered web browsing. As tech giants race to redefine the internet experience with smarter browsers and agent-driven search, Srinivas suggested Google's reliance on ad-based search could soon become its Achilles' a looming shift in how users interact with the web, Srinivas painted a picture of a future where digital agents handle everything from browsing to decision-making. That, he argued, leaves little room for Google's tried-and-tested business model that revolves around showing ads and racking up clicks. In his words, Google will face 'business model constraints' when it comes to letting AI agents 'do the clicks and work for you', all while maintaining high ad Google's own moves in the AI browser space, such as the internally developed 'Project Mariner', Srinivas said their progress is hampered by an inability to let go of legacy monetisation strategies. In what could be interpreted as both advice and warning, he remarked, 'At some point, they need to embrace one path and suffer, in order to come out stronger.' Srinivas's company, Perplexity, is taking the fight straight to Big Tech with its offering, Comet, an AI-native browser launched on July 9. It's currently only available via invitation to users of Perplexity's premium plan, which costs $200 (approximately Rs 17,230) per month or $2,000 (approximately Rs 1,72,300) per year. A free version, however, is in the pipeline. And now, Airtel has also announced a new offer for its customers across India, giving them complimentary access to the Perplexity Pro subscription plan for one CEO Aravind Srinivas subtle dig at GooglePerplexity's pitch is simple: let the browser do the heavy lifting — searching, comparing, summarising — so humans can focus on decisions, not digging through a dozen tabs. This agent-first approach, Srinivas believes, is the future. But it's one he says Google is reluctant to fully embrace, because doing so would undermine the ad model that generated $198 billion in search revenue alone last contrast to Google's scale, Perplexity is a scrappy upstart with a lean team. Leonid Persiantsev, Comet's product lead, said the team is kept deliberately small to remain agile, a subtle dig at what Srinivas characterised as Google's bloated bureaucracy. 'Too many decision makers and disjoint teams,' he wrote, calling out what he sees as an organisational sluggishness holding Google Perplexity owes a debt to Chromium, the open-source browser engine maintained by Google, the company insists it is building with a different priority: users, not also revealed that the company initially underestimated how willing people would be to pay for a browser experience free of intrusive ads and distractions. The early demand for Comet's premium tier, he said, proved that 'people are ready to pay for utility and independence.'The Perplexity chief also touched on the inevitability of being copied by larger players. At a Y Combinator event in June, he noted, 'If your company is something that can make revenue on the scale of hundreds of millions of dollars or potentially billions, you should always assume a model company will copy it.'Indeed, Srinivas expects Google to pay close attention to Comet and eventually replicate its features. He pointed to Project Mariner as 'similar but quite limited,' suggesting that innovation at Google tends to be reactive rather than head of communications, Jesse Dwyer, echoed that sentiment in a statement to Business Insider, saying bigger firms not only borrow ideas but 'do everything they can to drown your voice.' He added that the so-called 'Browser War III' could end poorly for users if monopolistic tactics from 'everything companies' prevail the shots fired, Srinivas was magnanimous in at least one regard. He acknowledged that without Chromium, Comet wouldn't exist. But even so, he said Perplexity is betting on a different vision, one where AI agents serve people, not profit models.'Enough of the monopoly of Google,' he said. - Ends

PM Modi To Launch Rs 12,000 Crore Projects In Bihar, Bengal Today
PM Modi To Launch Rs 12,000 Crore Projects In Bihar, Bengal Today

NDTV

time21 minutes ago

  • NDTV

PM Modi To Launch Rs 12,000 Crore Projects In Bihar, Bengal Today

New Delhi: Prime Minister Narendra Modi is set to visit Bihar and West Bengal on Friday, where he will launch a range of developmental projects worth over Rs 12,000 crore. After giving a major thrust to infrastructure development in both states, PM Modi will also address public gatherings in Motihari (Bihar) and Durgapur (West Bengal), respectively. The projects, amounting to over Rs 7,200 crore for Bihar and over Rs 5,000 crore for Bengal, aim to elevate the region's connectivity and overall infrastructural growth, while boosting employment, rural livelihoods, and digital innovation. In Motihari, PM Modi will inaugurate and lay foundation stones for projects across rail, road, IT, fisheries, and rural development sectors. He will flag off four Amrit Bharat Express trains connecting Patna, Motihari, Darbhanga, and Malda Town to major northern cities, including Delhi and Lucknow. Key railway projects in Bihar include the inauguration of automatic signalling on the Samastipur-Bachhwara line and the doubling of Darbhanga-Thalwara and Samastipur-Rambhadrapur sections worth Rs 580 crore. The Prime Minister will also lay the foundation stone for rail infrastructure projects, including a Vande Bharat maintenance facility at Patliputra and doubling of the Darbhanga-Narkatiaganj line, amounting to Rs 4,080 crore. In road infrastructure, PM Modi will launch the four-laning of the Ara bypass and Parariya-Mohania section of NH-319 with a combined investment of Rs 820 crore, improving access to the Delhi-Kolkata Golden Quadrilateral. To foster Bihar's digital economy, the Prime Minister will inaugurate a Software Technology Parks of India (STPI) facility in Darbhanga and an incubation centre in Patna, boosting start-ups and IT/ITES exports. Under the PM Matsya Sampada Yojana, he will launch new fisheries infrastructure, including hatcheries, aquaculture units, and fish feed mills. PM Modi will lay the foundation stone for Bharat Petroleum Corp. Ltd (BPCL) City Gas Distribution (CGD) project in Bankura and Purulia districts of West Bengal, worth around Rs 1,950 crore, to give a boost to Oil and Gas infrastructure in the region. It will provide PNG connections to households, commercial establishments and industrial customers and provide CNG at the retail outlets. PM Modi will also dedicate to the nation the Durgapur to Kolkata section (132 Km) of Durgapur-Haldia Natural Gas Pipeline and Bokaro-Dhamra Pipeline, also known as Pradhan Mantri Urja Ganga (PMUG) Project.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store