DCC lifts the lid on $15m plan for Edgar Centre roof

DCC lifts the lid on $15m plan for Edgar Centre roof

A new roof could be coming for Dunedin's leaky Edgar Centre complex at a cost of more than $15 million.
Replacement of the roof was yesterday added to the Dunedin City Council's planned capital expenditure programme for the next nine years after sports bodies and users of the facility advocated for comprehensive action to be taken.
They had warned of injury risks, reputational harm and the city continuing to miss out on hosting tournaments unless problems with leaks and condensation were fixed.
Councillors have begun deliberations on the council's 2025-34 long-term plan, and they agreed yesterday they had to find the money for replacing the Edgar Centre roof.
They included $360,000 in 2025-26 for detailed design, then $3m for the project in 2026-27 and $12m in 2027-28.
The allocation is not quite final, but no councillor voted against it.
The call was led by deputy mayor Cherry Lucas, who listed an array of sports that used the centre, as well as noting it was a venue for conferences, weddings, trade shows and Otago Polyfest.
It was a mass-use facility but could be "treacherous" at times, she said.
Fixing the centre was a priority spend for people who wanted rates rises kept in check, she said.
Cr Lucas said there had also been significant public fundraising in the past, as well as financial support from the Edgar family.
In 2023, the council decided to continue with a largely reactive approach to leaks.
A report at the time said leaks and condensation created risks for facility users because the water could pool on the courts and cause players to slip.
Condensation was particularly evident during winter.
The complex was described as "dynamic", as the centre was on shifting and sinking ground beside Otago Harbour.
The council faced strong calls this year to act.
Edgar Centre manager Blair Crawford said in his long-term plan submission the estimated $15m cost was good value for money compared with building a new facility.
The Edgar Centre submission was supported by numerous sporting organisations, including Sport Otago, Dunedin Netball, Basketball Otago, Volleyball Otago and Football South.
Cr Steve Walker said sports facilities were vital for adults and particularly important for the health of children.
Cr Lee Vandervis said the Edgar Centre was the "best-value facility we have".
He did not support other parts of the council's proposed $1.9b, nine-year capital expenditure programme.
Cr Jim O'Malley said fixing the problems there was part of building and maintaining a modern city.
Cr Christine Garey noted the high level of councillor support and said she hoped to also see that when it came to discussing what should be done regarding venues for performing arts.
grant.miller@odt.co.nz
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Cup race cancelled
Cup race cancelled

Otago Daily Times

time29-06-2025

  • Otago Daily Times

Cup race cancelled

A wet day was predicted and a downpour delivered. A rare cancellation of the Edmond Cup happened on Saturday as torrential rain hit the coastal Otago region. Seasoned observer Bruce Beath expected the course at the Ōtākou Golf Club would hold up better than previous iterations, and the multiple event placegetter was proven right as the absorbent fairways meant muddy areas were minimised, although visible surface flooding observed on Saturday afternoon would have made for an even wetter day for athletes. Athletics Otago said in a statement the decision to cancel was made in the interests of the safety of competitors, volunteers and supporters. It is believed the decision was made pragmatically based on the Dunedin City Council's recommendation to avoid all non-essential travel, alongside the early indications of potential rockfalls along Portobello Rd. Beath recalled many worse conditions, including "horizontal snow" in years gone by, but conceded the right decision was made. "I expect the golfers would not have been happy to have the course churned up by runners' spikes. "[The weather conditions] could have resulted in us all sleeping in our cars overnight if the road was to be closed." Becky de la Harpe, the women's pre-race favourite, will have to wait for another tilt at her maiden title. She said while it was a shame the race was cancelled, her attention had already turned firmly toward the Otago cross-country and New Zealand cross-country championships. The Otago cross-country is at Chisholm Links on July 13, while the national championships are at a Hagley Park circuit in Christchurch on August 2-3. With a growing southern contingent assembling, some strong teams could be in the running for national titles. By Luke Geddes

Games to operate out of Edgar Centre
Games to operate out of Edgar Centre

Otago Daily Times

time20-06-2025

  • Otago Daily Times

Games to operate out of Edgar Centre

Next year's Masters Games in Dunedin will focus operations at the Edgar Centre, as organisers look to shore up the event's viability. A games and entertainment hub featuring live music at the University Union has been dropped — a move expected to reduce costs by about $100,000. A streamlined check-in and administrative centre would be set up instead, and there would be a major shift in event operations to the Edgar Centre indoor sports complex, a report for the Dunedin City Council said. Other changes would include the Masters Games Trust asking sports partners to take on more responsibility for marketing and organising social events. The national event features more than 50 sports and games, attracting thousands of participants. Dunedin has hosted it every second year. The 2022 games were cancelled because of Covid-19 and last year's event made a $193,350.84 loss, leading to the city council writing off debt of $148,364.03, excluding GST. The council has agreed to underwrite the games until 2036. Participant registrations were budgeted at 5500 for the February 2024 games but finished well short on 3801. After the financial loss, an evaluation was carried out and the trust and council worked on an events plan. The games hub had served as a central venue for participant check-ins, social gatherings and nightly entertainment throughout the nine-day event. Feedback indicated attendance at the hub was inconsistent, particularly on weekdays, the council report said. Nightly entertainment was cut by the trust for 2026, reduced to selected nights, "ensuring a more vibrant atmosphere while reducing overhead costs associated with maintaining a dedicated entertainment space for the entire duration of the games", the council said. The Edgar Centre would host opening and closing ceremonies and costly temporary structures would not be needed there. "Additionally, this shift allows for integrated catering services, with food trucks stationed at both the Edgar Centre and key sporting venues like Logan Park and Hancock Park, providing a more cohesive experience for participants while reducing logistical costs." Sports bodies would have a bigger role in promoting their own sports ahead of the games. The trust would look to encourage teams to register well in advance. "These strategic changes are designed to reduce costs, improve financial sustainability and enhance participant engagement, ensuring the long-term success of the New Zealand Masters Games in Dunedin," the council report said. A break-even budget would be based on 2024 participant numbers, "ensuring financial viability without assuming significant growth".

Funding boost for Sunnyvale Sports Centre
Funding boost for Sunnyvale Sports Centre

Otago Daily Times

time14-06-2025

  • Otago Daily Times

Funding boost for Sunnyvale Sports Centre

A multi-year commitment will help keep the lights on at a local sporting venue. Dunedin City Council has confirmed nine years of annual funding of $45,000 to Sunnyvale Sports Centre. The facility is managed by Green Island Combined Sports Bodies Inc. Board member John Moyle said the decision could not have come at a better time, as steep insurance premiums had crippled the centre's maintenance budget. Built in the 1970s, the community-owned venue contains expanded polystyrene (EPS) panels in some areas. Once deemed state-of-the-art, they are now viewed as a fire risk. That has driven insurers to hike premiums from about $24,000 to roughly $64,000 a year. "We were all going well until the insurance killed us. "So now we really need to try to replace it, because that is just eating all of our income." The venue has been successful in establishing varied funding streams, including partnerships with sporting clubs and a lease to Village Green Cafe & Bar. Earlier, yearly support from the council had ended and rising insurance costs were draining funds set aside for maintenance. Replacing the panelling alone could cost up to $750,000, but the new long-term pledge may help the board leverage council support into a bolder project worth as much as $1.5 million that could ease Dunedin's shortage of courts. "That is why we came to the council and said, 'look, you know, is there a place for us to have six volleyball courts or two basketball courts'. "But we don't know, that is all completely to be discussed." The organisation may also look at other improvements, such as replacing showers and toilets that are nearing the end of their lifespans. A priority will be cutting insurance costs to a more manageable level. "If it was a brand new building, we would be running in the black." The yearly grant, paid throughout the council's nine-year plan, depends on a service-level agreement being finalised. The agreement may dictate exactly how the grant can be spent. "The council may put stipulations on it — they may say it is only for the project, not for running costs." A prior arrangement let the board use council funds as collateral for a loan, but new rules mean the city no longer guarantees community borrowing. However the money was ultimately used, the decision would be a turning point for the venue, he said. He thanked the council for its support. "Because it does give you the impetus to move forward," Mr Moyle said.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store