Centre delays green panel nod, airport expansion yet to take off
Centre's delay in approving the list of new committee members for State Environmental Impact Assessment Authority (SEIAA), forwarded by state govt, is cited as the reason. Though state govt submitted the new list two months ago, Centre hasn't taken any decision on it.
Originally scheduled to begin in April 2025, the project is now on hold after the previous SEIAA committee, responsible for reviewing and granting environmental approvals, expired on March 5.
Even after four months, a new committee is yet to be formed, stalling progress on one of Kerala's most ambitious infrastructure developments.
Airport operator Adani Airport Holdings Ltd submitted detailed plans for redeveloping terminals 1 and 2, which included a five-star hotel, underground parking, expanded passenger facilities and various commercial amenities. The revised master plan, which incorporated recommendations from ministry of environment, forest and climate change, was under review when SEIAA committee's term expired, effectively freezing all decisions.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Passa a WINDTRE, attiva a 0€
Passa a WINDTRE
Undo
Although SEIAA requested some modifications, the process couldn't continue due to the committee's dissolution. As a result, critical approvals required to commence construction remain pending.
Aviation secretary K Biju confirmed that state govt submitted a list of new SEIAA committee members to Union ministry of environment and forests for approval. He told TOI that once Centre gives the green light, the new committee will be constituted and clearing the airport terminal expansion will be treated as a top priority.
Until then, no construction activity can begin.
According to sources close to the airport, a public hearing is due before obtaining environmental clearance. The public hearing is for clearance from Kerala state pollution control board. "We are waiting for the public hearing to be called by the pollution control board. That has to be decided by the board. However, we have not been informed about the hearing so far. Besides, the initial proceedings for Project Anantha are also yet to be completed," a source said.
Project Anantha aims to transform the airport into a major international gateway capable of handling 27 million passengers annually and 0.42 million tonnes of cargo.
One major structural feature of the plan is vertical expansion of the terminal building, with two separate levels for domestic and international passengers. Demolition of the existing domestic terminal has been deferred until after 2027 and will be reconsidered in the next control period.
Meanwhile, the airport has been experiencing a significant rise in both passenger traffic and flight operations, further straining its outdated infrastructure.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Hindu
23 minutes ago
- The Hindu
Efforts on to revive effluent plant project in Edayar industrial area
The government is exploring options to revive the project to set up a common effluent treatment plant (CETP) for industrial units along the Eloor-Edayar stretch of the Periyar. The much-delayed project was expected to get a push after the government had earmarked around ₹30 crore towards a ₹250-crore assistance promised by the Small Industries Development Bank of India (SIDBI) for setting up CETPs in various industrial estates in the State. However, the Centre's borrowing restrictions on the State had delayed its implementation. Industries Minister P. Rajeeve said on Tuesday that the restrictions on taking loans had impacted the CETP project under assistance from the SIDBI. However, the government was looking at whether it could be included under the Guarantee Redemption Fund (GDR), which was meant to cover government guarantees offered for loans availed by public sector entities and cooperatives, he said. The monthly progress report on the updated status of the short- and long-term projects for the rejuvenation of the Periyar submitted before the Ministry of Jal Shakthi for May had quoted a decision taken at a meeting called by the Chief Secretary on February 9, 2023 saying that the CETP project might be dropped. All the units may be advised to have their own facilities for treatment of effluents. The fund allotted for the project may be utilised for any other liquid waste treatment project, it said. According to the detailed project report for the CETP in Edayar, the proposed plant will have the capacity to treat two million litres per day. A preliminary report prepared by the Kerala Water Authority said that the site identified for the project was close to the north-western portion of the industrial estate, which was previously occupied by the now defunct Periyar Chemical Industries. There was sufficient land with a facility to discharge to the downstream of the Pathalam regulator-cum-bridge of the Periyar, it said.


Time of India
27 minutes ago
- Time of India
Shipwreck off Kerala coast: Plea seeks arrest of ship against $134-million damage claim
Kochi: A petition has been filed in high court seeking a directive to arrest any vessel of the Mediterranean Shipping Company (MSC) currently within Indian admiralty jurisdiction, to secure a maritime claim of $134 million for the damage caused by the capsizing of the cargo vessel MSC ELSA 3 off Kerala coast. The public interest litigation (PIL) filed by Charles George, president of Kerala Fish Workers Coordination Committee and Swatantra Matsya Thozhilali Union, has been adjourned to Wednesday by the bench of Chief Justice Nitin Jamdar and Justice Basant Balaji for consideration along with related petitions. The Liberian-flagged MSC ELSA 3 sank approximately 14.6 nautical miles off Alappuzha coast on May 25. The petitioner submitted that the incident has triggered catastrophic ecological, economic and legal consequences. The continued presence of hazardous containers and bunker oil poses severe risks to Kerala's marine biodiversity, particularly during the monsoon fish spawning season protected under the trawling ban. Oil sardines, a vital source of income for Kerala's coastal fishermen, are at risk of extinction due to this maritime disaster. He also prayed for a directive to MSC to initiate and complete urgent wreck removal operations of the sunken vessel MSC ELSA 3 in a strict time-bound manner. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Giao dịch vàng CFDs với mức chênh lệch giá thấp nhất IC Markets Đăng ký Undo The petition further sought a directive to the shipping company to deposit an amount of $134 million with the high court registry as security for future compensation to be awarded to the affected stakeholders, including the local fishing community, environmental agencies and state govt, in proportion to the environmental and economic damage caused by the incident. Get the latest lifestyle updates on Times of India, along with Doctor's Day 2025 , messages and quotes!


Time of India
40 minutes ago
- Time of India
Jessica Pegula net worth: How rich is the World No.3 player?
Image credits: Getty Images Jessica Pegula, an American professional tennis player recently suffered a shocking defeat by world number 116, Italy's Elisabetta Cocciaretto in the Wimbledon first round. The 31-year-old was defeated by the player in just 58 minutes in what she described as her "worst result of the year. " She credited her defeat to humidity, the court, and her knee and neck injury. Along with being a talented sportswoman, Pegula is also considered as World's richest tennis player. Her parents Terry and Kim Pegula, are two powerful and successful personalities. While her father is an oil-and-gas billionaire and the owner of the Buffalo Sabres hockey team and Buffalo Bills NFL team, her South-Korean-born mother is a former president of the family's sports holding company and one of the only three principal NFL team owners not born in the United States. Born on February 24, 1994, she is one of five children and has been married to Taylor Gahagen since 2021. While Pegula herself earns considerable amounts from her tennis career, she still stands as one of the richest tennis players in the world. Here's all you need to know about her net worth. What is Jessica Pegula's net worth? Image credits: X As of 2025, Pegula's net worth is estimated at approximately $13 million as per Forbes. While this wealth includes her tennis earnings it also includes her sponsorships, partnerships, endorsements and investments. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Giao dịch CFD với công nghệ và tốc độ tốt hơn IC Markets Đăng ký Undo Pegula has earned over $18 million in career prize money, making her one of the top-earning women in tennis. In 2024, she earned $4.2 million from on-court achievements and an additional $6 million from off-court projects. She also won her first Grand Slam final at the US Open, earning valuable prize money. In terms of endorsements, she has worked with popular brands such as Adidas, Yonex, Ready Nutrition, Dyson, IBM and Stella Artois. Additionally, in 2017, she ventured into business with a skincare line, Ready 24, whose vice president is her husband, adding another source to her wealth. She and her husband also run a charity 'A Lending Paw' which supports the training of rescue dogs to become service animals.