Coal-fired plant in Gwadar planned: CPPCL cites ‘snags' and ‘challenges'
In a letter addressed to Shah Jahan Mirza, Managing Director of the Private Power and Infrastructure Board (PPIB), CPPCL Chairman Zhao Bo stated that the company submitted the required Performance Guarantee (PG) on March 21, 2025, in compliance with PPIB's requirements. This extended the validity of the Letter of Support (LoS) to March 31, 2028, fulfilling all obligations under the LoS and PPIB's directives.
Subsequently, on April 14, 2025, the company received a notice from PPIB requesting payment of the Financial Closing Date extension fee.
Gwadar coal-fired power project in limbo over tariff dispute
CPPCL emphasized that Clause 5 of the 2019 LoS clearly stipulates that 'delays caused by Government of Pakistan (GoP) entities' and 'events beyond the reasonable control of the Power Company' are valid grounds for exemption from the Financial Closing Date extension fee. Based on this clause, and after thorough evaluation, PPIB had approved the submission of the PG at the original amount — without requiring a doubled guarantee.
'In our previous communications with the Ministry of Planning, Development & Special Initiatives, and PPIB, we have detailed the reasons for the delays, including force majeure events and government-related delays, all of which are beyond the Power Company's reasonable control,' said Zhao Bo.
He further argued that Clause 6 of the 2018 Fee Regulations must be interpreted in conjunction with Clause 5 of the LoS. According to him, PPIB's unilateral enforcement of the 2018 Fee Regulations violates key legal principles such as: (i) lexspecialisderogatlegigenerali (special law overrides general law),(ii) the principle of contractual reciprocity, and(iii) Pakistani laws and regulations that prohibit holding a party liable for losses without direct causation.
Chairman Zhao warned that if PPIB enforces encashment of the PG solely due to non-payment of the extension fee, it would be a misuse of Clause 3 of the LoS, which limits PG encashment to scenarios involving 'failure to achieve the Financial Closing Date or execute agreements.'
He also pointed to Clause 3A of the 2018 Fee Regulations — titled 'Exemption from Fees and Charges' — which applies to the LoS extension fee for this project. The regulation, effective July 1, 2022, states that power companies and sponsors are exempted from such payments if the delay in milestone achievement is due to timeline adjustments under IGCEP or attributable to government entities or factors beyond the sponsor's control. However, the exemption does not apply if the delay is also attributable to the power company or sponsor.
Regarding the fee payment, CPPCL noted that the project has already incurred approximately $22 million in development costs, far exceeding NEPRA's approved cap of $10.5 million for development and owner management fees. Additionally, over $1 million has been paid in PPIB processing fees. Imposing further charges, the company argues, would severely impact the financial viability of the project.
Nevertheless, to prevent further delays and safeguard the broader interests of the China-Pakistan Economic Corridor (CPEC), the company said it will pay $150,000 as a 'payment under protest' for the extension fee. This payment is made without prejudice to its right to: (i) seek compensation for excess costs through NEPRA with PPIB's support; (ii) recover unjust charges and related losses through legal or other means, and (iii) claim refunds under Clause 5 (Refund Clause) of the PPIB Fee Rules.
The company also reiterated that despite receiving tariff approval with PPIB's support, it continues to face major challenges — including insufficient project cost approvals, exchange rate losses, currency conversion hurdles from the State Bank of Pakistan, tariff payment delays, and financing uncertainties. These challenges, it said, render the project commercially unviable in its current form.
'The true purpose of the LoS is to facilitate project advancement through PPIB's support,' the company stated, urging PPIB to act swiftly to resolve the issues that are threatening the project's commercial viability. The company affirmed its readiness to assist in finding solutions.
Copyright Business Recorder, 2025
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Express Tribune
2 minutes ago
- Express Tribune
Iqbal wants issues hindering Chinese investment resolved
Planning Minister Professor Ahsan Iqbal on Thursday chaired a special meeting of the Cabinet Committee on Chinese Investment Projects to review the progress of various projects under the China-Pakistan Economic Corridor (CPEC). The meeting, attended by senior officers from relevant ministries, focused on implementing decisions taken in the previous meeting and addressing issues faced by Chinese investors. Iqbal said resolving problems faced by Chinese investors was a top priority for the government. "The government is committed to ensuring a safe and conducive environment for Chinese investment, which is crucial for bilateral cooperation in new sectors under CPEC Phase II," he added. The minister said CPEC has the potential to play a significant role in increasing regional cooperation, with the Gwadar Port poised to become a hub of regional trade. He highlighted the importance of protecting the interests and employment of local fishermen in Gwadar, adding that the pace of water and power projects in the area be accelerated. The meeting directed that pending issues in projects built with Chinese investment be resolved immediately. Iqbal reiterated that increasing foreign investment and employment opportunities was a key part of the government's manifesto. "We are working tirelessly to ensure that CPEC projects are completed on time and that they benefit the local population," he remarked.


Business Recorder
11 hours ago
- Business Recorder
Emirates NBD helps secure $1bn for Dubai Metro's $5.6bn Blue Line
Emirates NBD said Wednesday it has concluded AED 3.9bn ($1bn) Syndicated Bonding Facilities to a consortium that will deliver the new Dubai Metro 'Blue Line' Project. In December 2024, Dubai's Roads & Transport Authority (RTA) awarded a AED 20.5 billion contract for the 30 km Blue Line to a consortium comprising Turkey's MAPA and LIMAK, along with Chinese state-owned CRRC. Emirates NBD engaged with the consortium 'as part of a seamless, comprehensive, and collaborative process,' it said in a statement. Valued at AED 20.5 billion, the infrastructure initiative is a crucial component in Dubai's 2040 Urban Master Plan to create, develop, and expand a world-class network of public transportation services and mobility solutions that connects communities with key locations, alleviates traffic congestion, and enables easier movement of people around the emirate. Dubai moves one step closer to flying taxis with successful test flight Scheduled for completion by September 2029, the Dubai Metro Blue Line will have 14 stations - five of which will be underground - to provide 'seamless connections' with the existing Red and Green Metro lines, as well as bus and taxi routes. The project, which was officially announced by the RTA at the end of last year, is expected to serve approximately 350,000 daily passengers by 2040. As a state-of-the-art electrified railway network, the Dubai Metro Blue Line project aligns with the Emirates NBD Sustainable Finance Framework, qualifying as Green Financing under the 'Clean Transportation' category. Dubai is spending billions to fix its traffic problems Ahmed Al Qassim, Group Head of Wholesale Banking at Emirates NBD, said the project 'will strategically and significantly empower the continuous development of the emirate by providing a rising population with new, efficient, accessible, and reliable public transportation and mobility solutions.' He said the transaction highlights 'Emirates NBD's status as the go-to banking partner for diverse mega projects that are transforming Dubai's landscape, capabilities, and global appeal.' Murathan Doruk Günal, Vice President & CEO at MAPA, said: 'The successful closing of the financing with Emirates NBD marks a key milestone and reflects the trust placed in our consortium's ability to deliver complex, high-impact projects' while Serdar Bacaksız, Board Member at Limak Group of Companies was quoted as saying that the Blue Line project 'is a testament to Dubai's forward-thinking approach to urban development.'


Business Recorder
17 hours ago
- Business Recorder
Iron ore rises on strong China steel demand, production curbs
SINGAPORE: Iron ore futures prices advanced on Thursday, buoyed by robust steel demand amid production curbs in top Chinese steelmaking regions. The most-traded September iron ore contract on China's Dalian Commodity Exchange (DCE) rose 1.3% to 781.5 yuan ($108.87) a metric ton by 0337 GMT. The benchmark August iron ore on the Singapore Exchange was 0.66% higher at $100.6 a ton. Steel production has rebounded in China, driven by accelerating accumulation of building materials, robust manufacturing demand, and sustained strength in steel exports, broker Galaxy Futures said in a note. Key steel producing regions Shanxi and Tangshan have started implementing output restrictions, Galaxy said. Iron ore shipments from top suppliers Australia and Brazil have fallen after a ramp-up by the end of the past quarter, according to analysts. Rio Tinto posted its highest second-quarter iron ore output since 2018, but shipments missed analyst forecasts and reached their lowest level for the half since 2014 due to weather-related disruptions. Improving mill margins are starting to boost optimism around demand, ANZ analysts said in a note. Meanwhile, BHP said costs of establishing a 'green iron' industry in Australia remained too high, even as Australia and China reached an agreement this week to work together on steel supply chain decarbonisation. Australia, which supplies 60% of China's iron ore needs, produces lower-grade iron ore which cannot be directly processed into steel with renewable energy. Other steelmaking ingredients on the DCE fell, with coking coal and coke down 0.66% and 0.83%, respectively. Most steel benchmarks on the Shanghai Futures Exchange gained ground. Rebar increased 0.26%, hot-rolled coil climbed 0.68%, wire rod rose 0.39% and stainless steel lost 0.08%.