Mawson Finland Limited Announces Significant Progress in Permitting Process for the Rajapalot Gold-Cobalt Project, Finland
Ms. Noora Ahola, Mawson Finland CEO, states: "We are very happy to announce that we have advanced in our Environmental Impact Assessment procedure, and have now selected a suitable consultant after a rigorous selection process. Ramboll is a highly respected and very experienced international consultancy office with a wide global network of experts, including experience in developing EIAs and related studies with Finnish mining operators. We are all very pleased to start working together and further develop the Rajapalot asset on its path to production. We would like to thank our shareholders, local stakeholders and communities for all the support and encouragement to continue developing and de-risking the Rajapalot project."
Highlights:
Responsible consultant selected for preparing the EIA Report ("second phase of the EIA procedure); RambollPart of international Ramboll Group A/SWidely experienced global network of expertsDedicated team of Finnish expertsRecent clients from the Nordic mining industry includes for example Agnico Eagle (Kittilä Gold Mine), Finnish Minerals Group (Terrafame Mine), Yara Suomi (Siilinjärvi Mine), Boliden (Kylylahti Mine) and Anglo American (Sakatti Mine project)Strong local support for the progress and development of the project
EIA - Environmental Impact Assessment Procedure
In Finland and the European Union, regulatory environmental planning processes form the foundation for a structured permitting path required for sustainable mine development. The EIA procedure lays the groundwork for moving the Rajapalot project through all future mine permitting requirements (i.e., industrial zoning, extraction and operational permits etc). Throughout this procedure the Rajapalot project and future mine permitting can be further de-risked while the company continues the on-going resource expansion work.
This EIA procedure ensures not only the project's environmental responsibility but also facilitates meaningful stakeholder engagement in the development process. The EIA procedure includes two major phases: the Program phase (ie., "first phase") and the Report phase (ie., "second phase"). The "first phase", or the EIA Program, was finalized in late 2024 (see MFL news release dated December 10, 2024). This "second phase" or the EIA Report, will document and address any significant environmental impacts from mine development and continued operations. As such, Mawson has now achieved a significant milestone in this development journey by initiating the final "second phase" of the EIA procedure.
It is important to note that while this EIA procedure is not a permit, it provides the vital and underlying foundations on which any further mine permitting processes will require. It provides both the environmental baselines of the area, and any possible effects of the project which will be continuously referred to by the governing authorities during subsequent mine permitting. The EIA Report can be finalized after the Pre-Feasibility has been completed.
This same EIA procedure has been or is being presently undertaken by all the other mineral development projects in Finland, including the Ikkari project of Rupert Resources, Suhanko ("Arctic Platinum") project of CD Capital Natural Resources Fund III L.P., the Sokli project of The Finnish Minerals Group, and the Sakatti project of Anglo American.
Ramboll
Ramboll is a global engineering, architecture, and consultancy company with over 18,000 experts worldwide and 2,500 in Finland. In the mining sector, Ramboll combines international expertise with local insight to deliver responsible, technically sound solutions across the full mine life cycle. Core services include ESIAs, permitting, closure planning, and stakeholder engagement, all aligned with IFC, EBRD, and Equator Principles to ensure compliance and financing readiness. Ramboll's recent assignments include for example acting as GISTM Designer of Record for Boliden Kylylahti mine and leading the EIA for Yara Suomi's Siilinjärvi mine expansion. Ramboll has also delivered zoning and impact assessments for Anglo American Sakatti Mining, an IFC-compliant ESIA for Sydvaranger AS in Norway, and environmental permitting and risk assessments for Terrafame mine. Ramboll have provided land-use and permitting services also for Agnico Eagle's Kittilä gold Mine.
About Mawson Finland Limited
Mawson Finland Limited is an exploration stage mining development company engaged in the acquisition and exploration of precious and base metal properties in Finland. The Company is primarily focused on gold and cobalt. The Corporation currently holds a 100% interest in the Rajapalot Gold-Cobalt Project located in Finland. The Rajapalot Project represents approximately 5% of the 100-square kilometre Rompas-Rajapalot Property, which is wholly owned by Mawson and consists of 12 granted exploration permits and one extension permit application for a total of 11,262 hectares. In Finland, all operations are carried out through the Company's fully owned subsidiary, Mawson Oy. Mawson maintains an active local presence of Finnish staff with close ties to the communities of Rajapalot.
Additional disclosure including the Company's financial statements, technical reports, news releases and other information can be obtained at mawsonfinland.com or on SEDAR+ at www.sedarplus.ca.
Media and Investor Relations Inquiries
Please contact: Neil MacRae Executive Chairman at neil@mawsonfinland.com or +1 (778) 999-4653, or Noora Ahola Chief Executive Officer at nahola@mawson.fi or +358 (505) 213-515.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release. No securities regulatory authority has reviewed or approved of the contents of this news release.
Forward-looking Information
This news release includes certain "forward-looking information" and "forward-looking statements" within the meaning of applicable securities laws (collectively, "forward-looking information") which are not comprised of historical facts. Forward-looking information includes, without limitation, estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking information may be identified by such terms as "believes", "anticipates", "expects", "estimates", "aims", "may", "could", "would", "will", "must" or "plan". Since forward-looking information is based on assumptions and address future events and conditions, by their very nature they involve inherent risks and uncertainties. Although these statements are based on information currently available to the Company, and management of the Company believes them to be reasonable based upon, among other information, the contents of the PEA and the exploration information disclosed in this news release, the Company provides no assurance that actual results will meet management's expectations. Risks, uncertainties and other factors involved with forward-looking information could cause actual events, results, performance, prospects and opportunities to differ materially from those expressed or implied by such forward-looking information. Forward-looking information in this news release includes, but is not limited to, the Company's objectives, goals or future plans, any expected receipt of additional assay results or other exploration results and the impact upon the Company thereof, any expected milestone independent data verification, the continuance of the Company's quality assurance and quality control program, potential mineralization whether peripheral to the existing Rajapalot resource or elsewhere, any anticipated disclosure of assay or other exploration results and the timing thereof, the estimation of mineral resources, exploration and mine development plans, including drilling, soil sampling, geophysical and geochemical work, any expected search for additional exploration targets and any results of such searches, potential acquisition by the Company of any property, the growth potential of the Rajapalot resource, all values, estimates and expectations drawn from or based upon the PEA, and estimates of market conditions. Factors that could cause actual results to differ materially from such forward-looking information include, but are not limited to: any change in industry or wider economic conditions which could cause the Company to adjust or cancel entirely its exploration plans, failure to identify mineral resources or any additional exploration targets, failure to convert estimated mineral resources to reserves, any failure to receive the results of completed assays or other exploration work, poor exploration results, the inability to complete a feasibility study which recommends a production decision, the preliminary and uncertain nature of the PEA, the preliminary nature of metallurgical test results, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, political risks, uncertainties relating to the availability and costs of financing needed in the future, changes in equity markets, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects, capital and operating costs varying significantly from estimates and the other risks involved in the mineral exploration and development industry, and those risks set out in the Company's public documents filed on SEDAR+. Although the Company believes that the assumptions and factors used in preparing the forward-looking information in this news release are reasonable, undue reliance should not be placed on such information, which only applies as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by law.
SOURCE: Mawson Finland Limited
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Miami Herald
6 hours ago
- Miami Herald
GameSquare Regains Compliance with Nasdaq's Minimum Bid Price Requirement
FRISCO, TX / ACCESS Newswire / July 25, 2025 / GameSquare Holdings, Inc. (NASDAQ:GAME) today announced that it received formal written confirmation from The Nasdaq Stock Market, LLC ("Nasdaq") confirming that the Company has regained compliance with Nasdaq's minimum bid price requirement. To regain compliance with the Minimum Bid Price Requirement, the Company's common shares were required to maintain a minimum closing bid price of $1.00 or more for at least 10 consecutive business days. The closing bid price of the shares has been at $1.00 per share or greater for 10 consecutive business days from July 8 to July 21, 2025. Accordingly, Nasdaq Listing Qualifications Staff has notified the Company that it has determined that the Company has regained compliance with Nasdaq Listing Rule 5550(a)(2), and the matter is now closed. About GameSquare Holdings, Inc. GameSquare (NASDAQ: GAME) is a cutting-edge media, entertainment, and technology company transforming how brands and publishers connect with Gen Z, Gen Alpha, and Millennial audiences. With a platform that spans award-winning creative services, advanced analytics, and FaZe Clan, one of the most iconic gaming organizations, we operate one of the largest gaming media networks in North America. Complementing our operating strategy, GameSquare operates a blockchain-native Ethereum treasury management program designed to generate onchain yield and enhance capital efficiency, reinforcing our commitment to building a dynamic, high-performing media company at the intersection of culture, technology, and next-generation financial innovation. To learn more, visit Forward-Looking Statements: This news release contains "forward-looking information" and "forward-looking statements" (collectively, "forward-looking statements") within the meaning of the applicable securities legislation. All statements, other than statements of historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this news release. Any statement that involves discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, future events or performance (often but not always using phrases such as "expects", or "does not expect", "is expected", "anticipates" or "does not anticipate", "plans", "budget", "scheduled", "forecasts", "estimates", "believes" or "intends" or variations of such words and phrases or stating that certain actions, events or results "may" or "could", "would", "might" or "will" be taken to occur or be achieved) are not statements of historical fact and may be forward-looking statements. In this news release, forward-looking statements relate, among other things, to: the Company's future performance, revenue, growth and profitability; and the Company's ability to execute on its current and future business plans. These forward-looking statements are provided only to provide information currently available to us and are not intended to serve as and must not be relied on by any investor as, a guarantee, assurance or definitive statement of fact or probability. Forward-looking statements are necessarily based upon a number of estimates and assumptions which include, but are not limited to: the Company's ability to grow its business and being able to execute on its business plans, the success of Company's vendors and partners in their provision of services to the Company, the Company being able to recognize and capitalize on opportunities and the Company continuing to attract qualified personnel to supports its development requirements. These assumptions, while considered reasonable, are subject to known and unknown risks, uncertainties, and other factors which may cause the actual results and future events to differ materially from those expressed or implied by such forward-looking statements. Such factors include, but are not limited to: the Company's ability to achieve its objectives, the Company successfully executing its growth strategy, the ability of the Company to obtain future financings or complete offerings on acceptable terms, failure to leverage the Company's portfolio across entertainment and media platforms, dependence on the Company's key personnel and general business, economic, competitive, political and social uncertainties. These risk factors are not intended to represent a complete list of the factors that could affect the Company which are discussed in the Company's most recent MD&A. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on the forward-looking statements and information contained in this news release. GameSquare assumes no obligation to update the forward-looking statements of beliefs, opinions, projections, or other factors, should they change, except as required by law. GameSquare Corporate Contact Lou Schwartz, PresidentPhone: (216) 464-6400Email: ir@ GameSquare Investor Relations Andrew BergerPhone: (216) 464-6400Email: ir@ GameSquare Media Relations Chelsey Northern / The UntoldPhone: (254) 855-4028Email: pr@ SOURCE: GameSquare Holdings, Inc.


Time Business News
12 hours ago
- Time Business News
Tech Cables & Power Solutions in Pakistan
IT professionals, Network Engineers, Business Owners, Industrial Buyers, ISPs, Retailers, Importers, Solar Installers, and Home Users across all cities of Pakistan. As Pakistan's IT infrastructure grows, Cat6 Ethernet LAN cables are becoming essential for reliable and high-speed networking across homes, offices, and industrial zones. Bandwidth up to 250 MHz Transmission speed: up to 10 Gbps Suitable for: Gigabit Ethernet, CCTV, smart homes, routers, switches, and access points Category Speed Frequency Max Distance Shielding Cat5e 1 Gbps 100 MHz 100 meters UTP only Cat6 10 Gbps 250 MHz 55 meters UTP/STP Cat6a 10 Gbps 500 MHz 100 meters STP Cat6 Cable Price in Pakistan can vary depending on brand, copper content (pure copper vs. CCA), shielding type (UTP/STP), and packaging (box or roll). Fiber optic technology is rapidly transforming the digital backbone of Pakistan, enabling ISPs, data centers, and enterprises to deliver fast, secure connectivity. 2-Core & 4-Core: Ideal for short-range FTTH and CCTV setups Ideal for short-range FTTH and CCTV setups 6-Core & 12-Core: Popular in mid-sized offices, corporate buildings, and educational institutions Popular in mid-sized offices, corporate buildings, and educational institutions 24-Core & 48-Core: Best for ISP backbones, metro networks, and large-scale data centers Internet Service Providers (ISPs) FTTH (Fiber to the Home) solutions Educational and government networks Industrial automation Fiber Optic Cable Pakistan is available in both Single-mode and Multi-mode, with brands such as Furukawa, ZTT, Litech, and Corning dominating the market. Beyond homes, Ethernet LAN cables are critical for structured cabling in: Corporate Offices Call Centers Educational Campuses Banks and Hospitals Shopping Malls and IT Parks High-performance Ethernet cables help eliminate downtime, reduce latency, and improve internal communication and data security. When selecting an Ethernet LAN cable for office, ensure: Copper content is 99.99% (for signal integrity) Lengths are according to TIA/EIA standards Category (Cat6 or higher) matches your bandwidth needs Patch cords are short-length networking cables used to connect endpoints to structured cabling systems, switches, or patch panels. Ethernet Patch Cords (RJ45) UTP or STP Cat5e, Cat6, Cat6a standards Used for LAN interconnections Fiber Patch Cords LC-LC, LC-SC, SC-SC connectors Available in OM1, OM2, OM3, OM4 grades Ideal for high-speed data centers Jacket Material: PVC or LSZH Lengths: 0.5m to 30m Compliance: ISO/IEC, RoHS Patch cord types and uses are vital for efficient cabling layouts in server rooms, industrial racks, and telco setups. For fiber optic installations, fusion splicers are essential tools. These machines ensure accurate and permanent joins between fiber ends with minimal loss. Core alignment vs. Cladding alignment splicing Fast splice time (typically 7–15 seconds) Touchscreen interface and auto-calibration Built-in heater for splice protection sleeves Fusion Splicer Machine Price in Pakistan depends on brand (e.g., Fujikura, INNO, Sumitomo, Goda), number of splicing cores, portability, and features. Professional ISPs, FTTH contractors, and industrial installers rely on splicers for rapid and low-loss fiber deployments. With frequent load-shedding and increased solar adoption, reliable energy storage has become a top priority in Pakistan. Advantages: Longer life cycle (2000–5000+ cycles) Lightweight and compact Faster charging and deep discharge capability Requires no maintenance Advantages: Lower upfront cost Readily available Proven over decades Disadvantages: Shorter lifespan Heavy and maintenance-prone Ideal for solar panel systems , UPS , and hybrid inverters , , and Efficient in hot climates Safe with built-in Battery Management Systems (BMS) Solar battery price Pakistan is now competitive due to growing local demand and increased imports. If you're looking for core fiber optic cable suppliers in Pakistan, Cat6 cables, or solar batteries, consider reputable vendors that offer: ✅ Product warranty & technical support✅ OEM and branded options✅ Delivery across all major cities (Karachi, Lahore, Islamabad, Multan, Peshawar, Quetta) ✅ B2B pricing for bulk orders One such trusted source is: Products: Cat6 cables, patch cords, fiber cables, lithium batteries, solar batteries, and splicing tools Clients: ISPs, data centers, solar companies, schools, hospitals, and retailers Nationwide delivery and custom solutions Website: Cat6 supports up to 10 Gbps at 55m, while Cat6a supports 10 Gbps at 100m and offers better shielding. 2-core or 4-core fiber optic cables are usually sufficient for basic FTTH use. Yes, lithium batteries with built-in BMS are safe, efficient, and long-lasting for home use. Single-mode is best for long distances (ISPs), while multi-mode is suitable for short distances (data centers, campuses). Depending on quality, lithium-ion batteries can last 5–10 years or more with proper use. Fusion splicers are available through industrial IT suppliers like Litech, Al-Razzaq, and authorized distributors in major cities. Pakistan's digital and energy infrastructure is evolving fast. Whether you're setting up a high-speed office LAN, deploying an FTTH solution, or installing solar systems for power backup, choosing the right tech cables and power solutions is crucial for performance, longevity, and cost-efficiency. From Cat6 Ethernet LAN cables and core fiber optic cables to patch cords, fusion splicer machines, and lithium solar batteries, understanding your options will help you make smarter investments. For trusted, high-quality tech and energy solutions in Pakistan, always go with verified suppliers and brands that meet local standards. TIME BUSINESS NEWS

Associated Press
14 hours ago
- Associated Press
4 Steps to Budget When Living on Your Own in Lafayette, LA
NEW YORK CITY, NY / ACCESS Newswire / July 26, 2025 / Living on your own in Lafayette, LA, is a big step - and an exciting one. You get to make your own choices, create your own space and enjoy your independence. But living on your own also means being in charge of your own money, which may be overwhelming at first. Don't worry, you're not alone. Many people in Lafayette are learning how to manage their budgets and take control of their finances for the first time, just like you. And while it may seem challenging some days, the good news is that you could build smart money habits one step at a time. Whether you're paying rent, buying groceries or handling surprise costs, tools like budgeting, saving or looking into loans in Lafayette, LA, could help you stay on track. Keep reading for a few ways to care for your finances while living on your own. 1. Know what's coming in and going out The first step to creating a budget is understanding your income and expenses. Income is how much money you earn each month and expenses are how much you spend. Start by writing down your monthly income. If you get a regular paycheck, list how much money you earn after taxes. If you work different hours each week or have more than one job, try to estimate an average income based on what you've earned in the past few months. Next, write down your regular monthly expenses. These might include: Also, think about any bills that come up less often, like car insurance, which you may pay every six months or annually. Break those less frequent payments into monthly amounts so you don't forget to plan for them. Once you compare the money coming in and going out, you could see if you're spending more than you make or if you have funds left over to save. 2. Choose a budgeting method Choosing a budgeting method that fits your lifestyle may make managing money much easier. Consider the following well-known strategies: 3. Prepare for the unexpected Even if you have a solid plan, life doesn't always go the way you expect. Your car might break down, your pet might need to see a vet or you could lose hours at work. To deal with any unforeseen expenses, it's smart to set up an emergency fund. An emergency fund is money you set aside specifically for unexpected costs. Start small - even saving $20 a week can add up over time. If you don't have enough money saved and something urgent comes up, you might consider a personal loan to help cover car repairs, medical bills or other important expenses. A personal loan is a lump sum of money you borrow from a bank, credit union or other lender. You pay back the loan in fixed monthly installments over a pre-determined amount of time along with interest, which is the cost of borrowing money. Make sure you understand the terms of a loan before you borrow. Look at the interest rate, monthly payment amounts and the time it will take to repay. 4. Make saving a regular habit Saving money doesn't have to be hard. If you treat savings like a regular bill, it might become part of your routine. One simple method is setting up automatic transfers from your checking account to a savings account. Automatic transfers ensure that part of your paycheck gets saved without you even thinking about it. You could also make saving into a game. Set a goal to save $5 every time you skip a coffee or pack lunch instead of going out. Over time, you'll see how small choices could lead to big savings. Build your independence with smart money habits Living on your own comes with new responsibilities, but it also brings freedom and the opportunity to make your own financial choices. When you learn how to budget, save and prepare for the unexpected, you're giving yourself the tools to stay in control of your money - and your future. SPONSORED CONTENT CONTACT: Sonakshi Murze Manager [email protected] SOURCE: OneMain Financial press release