
BRT Line 2C delays spark conflicting claims as contractor denies payment issues
Motorists and residents continue to face frustration as the Bus Rapid Transit (BRT) Line 2C project on Lynnwood Road lags behind schedule, with delays now stretching the project's deadline to the end of June.
This comes after multiple deadline extensions, conflicting statements from Tshwane and the contractor, and growing safety concerns on the road.
The project, which began in May 2023, was initially scheduled to be completed by November 19 that year.
The deadline has since shifted several times, from March to mid-April and now to the end of June.
Previously, Tshwane spokesperson Lindela Mashigo said one of the factors behind the delays has been the contractor's failure to pay workers on site, along with rain delays and changes in scope.
However, the contractor for the project, Buhle Shabalala, has denied any issues with wage payments, saying all workers on site have been fully compensated.
Shabalala insists the real cause of the holdups lies in waiting for design drawings from the consultants and delays in approvals from the metro.
'It's not true that there were extensions due to non-payment of the workers. All of my workers on site are paid,' Shabalala said.
'The delays were due to heavy rainfall and the time it took to get design approvals from Tshwane.
'There's a large pipeline in one section that required changes to the original design, and that's added time.'
He explained that while most sections of Line 2C will be completed by June, one section still awaits approval so that a new pipe installation can proceed.
Shabalala also dismissed claims that rubble is being left on site.
'We remove rubble at the end of each workday. The only materials we stockpile are G1 and G5 construction materials.'
Responding to growing complaints from motorists about broken barriers and safety hazards, Shabalala said the barriers were damaged during heavy rains two months ago and were replaced when broken.
'We've completed several sections and are currently working on the remaining parts,' he said.
DA councillor Dikeledi Selowa confirmed that the latest deadline has been extended to June 23, as reflected in a council report.
She said that while the project is back on track, ongoing oversight is crucial.
'The issue is poor project management within the metro.
'These ongoing extensions beyond the initial contract period can potentially lead to extra, unforeseen expenses,' Selowa said.
Selowa acknowledged that the contractor has since caught up with wage payments and that progress on the ground is visible.
'We are monitoring the project closely. Once it's completed, we will call for a physical audit verification to ensure that every cent spent from the metro's grant funding delivered value for money.'
Selowa also pointed to issues of rubble not being cleared adequately, placing that responsibility on the contractor.
The contractor, however, strongly denies neglecting site cleanliness.
Mashigo confirmed that the project was 84% complete and gave non-payment of workers, slow progress, rain delays, and changes in project scope as reasons for the delay.
The city did not provide an updated comment by the time of publication.
Do you have more information about the story?
Please send us an email to bennittb@rekord.co.za or phone us on 083 625 4114.
For free breaking and community news, visit Rekord's websites: Rekord East
For more news and interesting articles, like Rekord on Facebook, follow us on Twitter or Instagram
At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!
Stay in the know. Download the Caxton Local News Network App
Stay in the know. Download the Caxton Local News Network App here

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Citizen
2 days ago
- The Citizen
Randburg braces for major water maintenance impact
Planned maintenance on Rand Water's Eikenhof and Zwartkopjes systems from 30 June to 2 July is expected to disrupt water supply across Johannesburg, including Randburg and surrounding suburbs. According to Johannesburg Water spokesperson Nombuso Shabalala, Randburg is one of the areas that will be affected by the maintenance. Also read: Water disruptions expected during Rand Water maintenance 'Residents may experience poor pressure or no water during this period,' said Shabalala. 'Arrangements will be made for alternative supply through roaming and stationary tankers, and residents are encouraged to store water in advance.' In Ward 102, Councillor Lucinda Harman confirmed that clinics, hospitals, and retirement homes will receive top priority. 'Tankers will only start roaming after 24 hours. Please store water and avoid unnecessary usage. Schools are on holiday, and shopping centres are being monitored too,' she said. Also read: JW still has no answer for burst on Nerina Street Water will be throttled to 50% capacity, not shut off completely. However, if reservoirs aren't full before the start of the work, supply may run dry in some areas. In Ward 115, Councillor Mark van der Merwe said no major shortages are expected if residents conserve water. 'Our schools and retirement village have backup systems, and medical sites are supplied by the unaffected Bryanston Reservoir,' he explained. Residents are urged to: Limit use of dishwashers, washing machines, and baths Avoid refilling pools or washing cars Help elderly neighbours collect water Those needing JoJo tank refills can contact Somayya on 083 650 0577. A call centre number for urgent needs will also be shared. For updates, follow your ward councillor or visit Follow us on our Whatsapp channel, Facebook, X, Instagram, and TikTok for the latest updates and inspiration! Have a story idea? We'd love to hear from you – join our WhatsApp group and share your thoughts! At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!


Daily Maverick
2 days ago
- Daily Maverick
Sewage pollution, vandalism to keep Nelson Mandela Bay beach closed until summer
Six months down the line, New Brighton Beach in Nelson Mandela Bay is likely to remain closed until summer as the metro works to rectify sewage pollution and vandalism at the popular seaside facility. In December 2024, the Nelson Mandela Bay metro closed New Brighton Beach due to dangerous levels of contamination after vandalism led to a sewage spill at the nearby Fishwater Flats Sewage works. On Thursday, metro spokesperson Sithembiso Soyaya said the beach would be opened 'before the upcoming summer season'. However, he said that since the closure, beach facilities had been vandalised and the damage would be repaired only in the next financial year. 'The repairs to the Fishwater Flats Water Treatment Works are envisaged to conclude by the end of this month,' he said. Soyaya said the beach would be reopened once there were 'satisfactory results regarding levels'. According to the Auditor-General's report into municipal finances for 2023/2024, Nelson Mandela Bay was the only metro that received a regional bulk infrastructure grant, which is aimed at improving bulk water and sanitation infrastructure. The metro, however, underspent the grant by 41% due to two capital projects that were not launched because of 'implementation challenges', the report said. In its budget for the 2025/2026 financial year, the metro said: 'The Regional Bulk Infrastructure Grant (RBIG) has been allocated to the municipality only for the 2025/26 financial year to the amount of R390-million. This grant was firstly allocated to the city with effect from the 2023/24 [medium term], to deal with water drought-related issues that the city has been confronted with and will, with effect from the 2026/27 financial year, be no longer made available to the City.' Cable theft Final treated effluent is released from Fishwater Flats at two points: New Brighton Beach pier and Papenkuils River canal, but the theft of electrical cables that supplied power to the plant and essential equipment interrupted the treatment process of this effluent. In turn, this led to a massive spill of raw sewage into the sea. It has been reported in municipal statements that R18.8-million has been spent to repair Fishwater Flats. In October last year, Deputy Minister of Water and Sanitation Sello Seitlholo visited the facility. He said the water treatment works had 'experienced major destruction to a cost of almost R5-million; the repair is estimated to cost four times that. This has heavily impacted the work being done, which in turn impacts the quality of water being treated and discharged. 'I am fundamentally concerned about the level of vandalism and theft that is happening here. The municipality is losing a couple of million due to theft, and to replace that, it costs them four times what is lost,' he said. 'Dysfunctionality' The DA's mayoral candidate for Nelson Mandela Bay for the upcoming local government elections, Retief Odendaal, said the problem went further than Fishwater Flats. 'Wastewater treatment facilities in Nelson Mandela Bay continue to face serious challenges, exposing the complete dysfunctionality of the current ANC-led administration. Years of neglect and failure to maintain, upgrade, and protect critical sewerage infrastructure have led to persistent pollution of our waterways and coastline. 'While the municipality claims that pollution levels are now acceptable and plans to reopen the beach at the end of June, our inspection today indicates that this is highly unlikely,' he said. The municipality did, however, indicate on Thursday that it would open the beach only 'before summer.' 'I have now written to the Minister of Water and Sanitation, Pemmy Majodina, urging her department to intervene directly in Nelson Mandela Bay and assist in bringing all wastewater treatment works up to the required standards,' Odendaal said. Among the findings made against the municipality by the Auditor-General was that none of the wastewater treatment facilities has valid licences. 'Given the municipality's track record of failing to provide transparent and reliable water quality data, we have called on the minister's department to conduct its independent water quality testing at New Brighton Beach,' Odendaal said. The municipality doesn't make water quality results public unless it receives a Promotion of Access to Information Act application. 'Dangerous contamination' In March this year, ASC Consultants published an independent report showing that between November and December last year, the sea at New Brighton Beach was dangerously contaminated. According to the report, its results showed 'high contamination levels [that] posed significant health risks to beachgoers'. This was on 2 November. Two weeks later, the numbers had come down, but were still high. In December, contamination shot up again. Analysts compiling the report for ASC warned that sewage pollution was now 'posing severe health risks to swimmers and require[s] immediate remedial action.' A test after the beach was closed showed record-high contamination levels. Analysts issued another warning: 'This beach exhibited alarmingly high levels of contamination in the third trial… These figures exceed the Blue Flag standards by 40 and 92 times, respectively. Such extreme contamination levels suggest a direct influx of untreated sewage, likely exacerbated by an ageing infrastructure and stormwater runoff. 'The health risks here are severe, rendering the beach unsafe for recreational use. Community members who use this beach for spiritual purposes, as observed during one of the visits when samples were collected, are at significant risk of exposure to waterborne pathogens,' the report concluded. Odendaal said the DA would do its own sampling. 'The problems are not limited to Fishwater Flats. Sewage spills, failing stormwater drains and dysfunctional wastewater facilities are widespread across the city. The municipality bears primary responsibility for this persistent pollution, and the people of Nelson Mandela Bay have a right to expect transparent reporting and urgent action,' he said. DM


The Citizen
20-06-2025
- The Citizen
Crèches are now ready to fight fires
Crèches are now ready to fight fires Tshwane has delivered fire safety equipment, including serviced and upgraded extinguishers, hose reels and hydrants, to nine early childhood development centres in regions 3 and 6. This comes after a routine inspection by the DA caucus's Section 79 Community and Social Development oversight committee, chaired by Phuti Kwenaite. 'Recently, we pointed out there are maintenance elements that have been neglected in Tshwane's ECDs.' She said the fire extinguisher problem was supposed to be addressed two years ago. Kwenaite highlighted the significant risk posed when fire extinguishers are neither present nor functional. 'It is a big risk for the extinguishers not to be there and functioning. 'This is why the fire department took some time for some of these ECDs to open.' MMC for Corporate and Shared Services Kholofelo Morodi confirmed that Tshwane has completed the servicing and upgrading of fire-fighting equipment, with a sharp focus on ECD centres. She said the initiative, executed by Group Property Management, ensures full compliance with national safety standards, specifically SANS 10400 Part T (fire safety) and SANS 1475 (fire extinguishers). Marodi added that these mandate the installation, maintenance and servicing of portable fire suppression equipment. 'It includes the maintenance of fire extinguishers, hose reels, and hydrants and forms part of the city's annual fire safety programme.' She said these maintenance efforts signal a broader shift in Tshwane's multiparty coalition prioritising the safety of employees, children and communities. Marodi added that maintaining a safe workplace supports an efficient municipality and reflects Tshwane's commitment to this principle. 'Reinforcing Occupational Health and Safety (OHS) standards remains pivotal to protecting employees and service users. 'This intervention forms part of an ongoing effort to strengthen internal systems, promote compliance, and safeguard infrastructure, all aimed at delivering reliable and dignified services to residents.' ALSO READ: Mamelodi youth punches back at crime through boxing Do you have more information about the story? Please send us an email to bennittb@ or phone us on 083 625 4114. For free breaking and community news, visit Rekord's websites: Rekord East For more news and interesting articles, like Rekord on Facebook, follow us on Twitter or Instagram or TikTok. At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading! Stay in the know. Download the Caxton Local News Network App Stay in the know. Download the Caxton Local News Network App here