Karnataka govt tells NTPC to scout entire state for nuclear plant site, rejects initial locations
National Thermal Power Corporation
(NTPC) to submit a report after carrying out a study across the state, regarding the location for the proposed nuclear power plant, following which it said it will take a considered view.
The cabinet did not agree with three potential sites identified by NTPC to conduct preliminary studies for setting up the nuclear power plant.
"In-principle approval was sought to set up a nuclear power plant in the state, along with permission to conduct preliminary studies at potential sites identified by NTPC. They (NTPC) were requesting to study three locations, but the cabinet did not agree with that. We have decided that let them study the whole of the state for possible viable alternatives and submit a report, so that the government of Karnataka will take a considered view," Law and Parliamentary Affairs Minister H K Patil said.
Speaking to reporters after the cabinet meeting, he said, "Now we have agreed that we need to have a nuclear project, but as regards the location is concerned, they have to study all possible alternatives and submit the report and we will take the considered opinion later."
The three places suggested were in Vijayapura, Raichur and Koppal district. "They were not considered for various reasons after detailed discussion," he said.
Patil said, to promote tourism in the state, it was decided that, the North Karnataka tourist circuit including Hampi-Badami-Aihole-Pattadakallu-Vijayapura will be developed under the DBFOT (Design, Build, Finance, Operate, and Transfer) model through Karnataka Tourism Infrastructure Limited at an estimated cost of ₹166.22 crore.
Administrative approval was given by the cabinet to undertake 5 years of Operation and Maintenance (O&M) work of the Lift Irrigation Project to fill 126 lakes in Kolar district and Chintamani taluk of Chikkaballapur district with treated wastewater from Bengaluru city at an estimated cost of ₹128.00 crore.
Also approved was the purchase of the 32 Mobile Forensic Vehicles (with Fabrication + SOC kits) for the Directorates of Forensic Science Laboratories at a cost of ₹20.40 crore.
To develop a new textile park in Raichur taluk, Raichur district, under Public-Private Partnership (PPP) model at a total cost of ₹24.50 crore was approved by the cabinet.
The cabinet has also decided to merge the Ayurvedic, Siddha and Unani (ASU) Drugs Enforcement Division and Testing Laboratory of the Department of AYUSH with the Department of Food Safety and Drug Administration (FDA).
The establishment of Dr B R Ambedkar Constitution chair in the University of Mysore at an estimated cost of ₹10 crore was also approved.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
6 hours ago
- Time of India
NTPC halts FGD work at 5 plants after government exemption; 7 GW projects hit
NTPC has asked Bharat Heavy Electricals Ltd ( BHEL ) to halt installation of flue-gas desulphurisation (FGD) systems at five under-construction coal-fired power plants days after the government exempted most thermal power plants from FGD requirement. The stop work request covers Lara-II, Singrauli-III, Sipat-III, Darlipalli-II, and Telangana-II plants. This translates into desulphurisation works being stalled on projects with over 7 GW capacity that are under construction. "Considering the recent notification issued by the Ministry of Environment, Forest and Climate Change, BHEL is requested to keep all activities related to FGD for the aforementioned projects on hold until further communication," NTPC said in a communication to BHEL. The ministry in a gazette notification on July 11 exempted coal-fired power plants outside a 10-km radius of populated and polluted cities from a 2015 mandate to install FGD systems in phases. BHEL is the country's primary supplier of FGD systems, which remove sulphur dioxide from the plants' exhaust gases. "BHEL has some foreign collaborators in FGD projects and may seek compensation from NTPC for the stop work order," an official aware of the NTPC letter told ET. NTPC had floated several tenders and installed, or is in the process of installing, multiple FGD systems after a 2015 directive made them mandatory for all coal-based plants to meet revised environmental standards. Responding to queries from ET, BHEL said the matter is too premature to comment. '…Specific queries cannot be responded definitively at this stage,' the company said. As of February, 537 thermal units totalling 204 GW capacity were identified for installation of FGDs. Of them, installation was completed in 49 units, while contracts were awarded or were under implementation in 211 units. Another 180 units were under various stages of the tendering process, according to the government. CareEdge Ratings said the FGD exemption for the majority of the plants, with 145 GW capacity, is positive for private companies or independent power producers, as it is a costly pollution control system.


Hans India
9 hours ago
- Hans India
CM asks Sri City team to actively support ‘P4'
Sri City: Sri City Chairman Srini Raju, and MD Dr Ravindra Sannareddy took part in a dinner hosted by Chief Minister N Chandrababu Naidu at his camp office in Undavalli on Friday. The gathering brought together distinguished leaders from industry and business sectors to discuss the P4 (Public-Private-People Partnership) initiative, which is designed to uplift underprivileged communities across the state. Following the meeting, Srini Raju, Sannareddy, Taizo Iwami (MD, IMOP), and Yuichi Tomita (Plant Head, Aisan Auto Parts) met the Chief Minister on behalf of the Sri City industrial community. The Chief Minister urged them to actively support the initiative and help uplift the underprivileged across the State. The delegation pledged Sri City's full backing for the P-4 programme, expressing confidence in its potential to drive inclusive and transformative development in Andhra Pradesh.


Time of India
21 hours ago
- Time of India
NTPC halts FGD work at 5 plants after government exemption; 7 GW projects hit
NTPC has asked Bharat Heavy Electricals Ltd ( BHEL ) to halt installation of flue-gas desulphurisation (FGD) systems at five under-construction coal-fired power plants days after the government exempted most thermal power plants from FGD requirement. The stop work request covers Lara-II, Singrauli-III, Sipat-III, Darlipalli-II, and Telangana-II plants. This translates into desulphurisation works being stalled on projects with over 7 GW capacity that are under construction. "Considering the recent notification issued by the Ministry of Environment, Forest and Climate Change, BHEL is requested to keep all activities related to FGD for the aforementioned projects on hold until further communication," NTPC said in a communication to BHEL. Explore courses from Top Institutes in Select a Course Category Digital Marketing Cybersecurity Project Management PGDM Design Thinking Management Product Management healthcare CXO Data Science Healthcare Data Science Technology Degree others MCA Public Policy Artificial Intelligence Operations Management Data Analytics Others Finance MBA Leadership Skills you'll gain: Digital Marketing Strategies Customer Journey Mapping Paid Advertising Campaign Management Emerging Technologies in Digital Marketing Duration: 12 Weeks Indian School of Business Digital Marketing and Analytics Starts on May 14, 2024 Get Details Skills you'll gain: Digital Marketing Strategy Search Engine Optimization (SEO) & Content Marketing Social Media Marketing & Advertising Data Analytics & Measurement Duration: 24 Weeks Indian School of Business Professional Certificate Programme in Digital Marketing Starts on Jun 26, 2024 Get Details The ministry in a gazette notification on July 11 exempted coal-fired power plants outside a 10-km radius of populated and polluted cities from a 2015 mandate to install FGD systems in phases. BHEL is the country's primary supplier of FGD systems, which remove sulphur dioxide from the plants' exhaust gases. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like These WhatsApp hacks are going viral in India google Learn More Undo "BHEL has some foreign collaborators in FGD projects and may seek compensation from NTPC for the stop work order," an official aware of the NTPC letter told ET. NTPC had floated several tenders and installed, or is in the process of installing, multiple FGD systems after a 2015 directive made them mandatory for all coal-based plants to meet revised environmental standards. Live Events Mails sent to NTPC and BHEL remained unanswered till the time of publishing. As of February, 537 thermal units totalling 204 GW capacity were identified for installation of FGDs. Of them, installation was completed in 49 units, while contracts were awarded or were under implementation in 211 units. Another 180 units were under various stages of the tendering process, according to the government. CareEdge Ratings said the FGD exemption for the majority of the plants, with 145 GW capacity, is positive for private companies or independent power producers, as it is a costly pollution control system.