Month after deadline, cement rd contractors get extension till Dec
Phase-IV of the cement road project covers the conversion of 33 major tar roads — each ranging between 9 and 24 metres in width — into cement roads. The roads have been divided into 14 packages spread across zones including Laxmi Nagar, Dharampeth, Mangalwari, Nehru Nagar, Ashi Nagar, Dhantoli, and Lakadganj. These corridors include critical routes like Central Jail Road, Chhatrapati Square to Besa, Ajni to Sita Nagar, and Manish Nagar to Laxmi Nagar.
Adding to the concerns, the contractor for Package 9 also formally requested an extension. The original deadline for all 14 packages under phase-IV was May 2025. However, with work proceeding at a sluggish pace, officials say even the remaining packages are unlikely to meet the revised targets, indicating that more extensions may be on the horizon.
The delays come at a particularly difficult time for motorists, as several of the under-construction roads are either dug up or barricaded, posing serious problems during the ongoing monsoon season.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Cervecería Nacional CFD: Calcula cuánto podrías ganar invirtiendo solo $100
Empieza a invertir
Inscríbete ahora
Undo
"Commuters are forced to negotiate muddy detours, leading to frequent traffic snarls and accidents," admitted an NMC official on condition of anonymity.
Among the defaulters, M/s Drishti Structural Engineering Pvt Ltd, assigned package 1 (covering key roads in Laxmi Nagar zone), and M/s RM Dayaramani, responsible for packages 2 and 4, received extensions till December 2025. M/s PK Nagrare Constructions, which is executing package 9 in Dhantoli zone, also sought more time citing delays.
Other contractors working on major city roads are also under scrutiny for slow execution. This includes high-traffic stretches like Ram Nagar, Dharampeth Jhenda Chowk to Adivasi Vikas Bhawan, which are also unlikely to meet their May 2025 deadlines.
The NMC previously claimed success in its cement road initiative, converting over 690km roads under phases I-III out of the city's 1,556km tar road network. But the ongoing phase-IV delays threaten to erode public trust in the project.
With costs rising and civic inconvenience mounting, questions are being raised about the NMC's contractor selection and monitoring processes. The repeated extensions raise red flags about accountability, project management, and whether penalties for delays are being enforced.
INFOBOX: NMC Phase-IV Cement Road Project — Extended Deadlines
Package No.---- Road Numbers---- Key Stretches---- Zone---- Extension Period
1---- RD-1, RD-13, RD-14, RD-15---- Somalwada Rd, Govind Nagar, Tapowan Main Road, Jaiprakash Nagar --- Laxmi Nagar--- Up to December 2025
2---- RD-3, RD-7---- Gulmohar Hall to Wardha road, Bharat Petrol Pump to Joggers Park Football Ground--- Laxmi Nagar --- Up to December 2025
4---- RD-4, RD-9, RD-12---- NEERI Road to Aath Rasta Sq., Deo Nagar Square to Swami Vivekanand Sq. to Gajanand Nagar, Roseta Club to FCI Godown stretch--- Laxmi Nagar --- Up to December 2025
9 ---- (requested) RD-23, RD-24---- Bharat Petrol pump to New Apolostical School to Parizad Beauty Parlour To Manewada School, Suyog Nagar to Railway Yard Compound--- Dhantoli --- Extension requested

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
an hour ago
- Time of India
Infopark Phase III: GCDA to pool 1,000 acres, to issue notification soon
Kochi: Greater Cochin Development Authority (GCDA) initiated procedures to publish the notification for land pooling for the much-awaited Phase III of Infopark GCDA is planning to pool nearly 1,000 acres to establish the new campus across 300 acres in Kizhakkambalam and Kunnathunadu villages of the district. The project will be the first land-pooling project in Kerala. Govt tasked GCDA with land pooling through an order last year. Following this, GCDA engaged in discussions with Infopark at various stages, conducted site inspections and began efforts to identify suitable land. However, GCDA faced technical hurdles as the identified lands were outside GCDA's jurisdiction. The authority approached govt, which subsequently issued an order last month assigning GCDA a special task for land pooling in the area. The first step for land pooling is issuing an initial notification by determining the suitable land. The area intended for pooling, along with details including survey numbers, will be published with the help of a boundary map. Subsequently, a meeting of landowners in the area will be convened to present the project details. If 75% of total landowners agree to pooling, GCDA will proceed with the project. Following this, a draft project document will be prepared for govt approval. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like American Investor Warren Buffett Recommends: 5 Books For Turning Your Life Around Blinkist: Warren Buffett's Reading List Undo After gathering public opinions and necessary changes, the final project document will be prepared before commencing work. After implementing projects on the pooled land, a specified percentage of land will be returned to landowners. If 75% of landowners do not consent, steps will be initiated to identify other suitable land, said GCDA authorities. A press note issued by GCDA on Monday said Phase III campus will feature six key components: carbon neutrality, self-sufficiency in water resources, a complete waste management system, road, rail and airport connectivity, an inclusive IT park and a maintenance system that doesn't disrupt the functioning of IT companies. Besides IT companies, there will be residential facilities, commercial establishments, sports and cultural facilities, recreational areas, hospitals and educational institutions, it said.


Time of India
an hour ago
- Time of India
20 years on, GDA may file FIR against officials for 134 extra flats in society
Ghaziabad: GDA will take action against several current and former officials who allowed a private developer to construct and sell 134 extra flats beyond the sanctioned 400 units at Express Garden society in Indirapuram's Vaibhav Khand in 2005. A GDA panel, set up on the direction of the Allahabad High Court, is set to submit its report to the Authority's additional secretary later this week. The high court is due to hear the matter in Sept. Officials, privy to the content of the committee's findings, said the panel has recommended "FIR be filed against the architect, developer and the then GDA officials under whose watch the additional units were constructed". You Can Also Check: Noida AQI | Weather in Noida | Bank Holidays in Noida | Public Holidays in Noida A residents' group of Express Garden that filed a petition in Allahabad high court in May 2022, stating that since 2015, no yearly election was held for the residential society on the pretext that the deed of declaration was defective. "During the hearing, it was learnt that the promoter had constructed 534 units in place of the sanctioned 400 in the project map," Vijay Rathi, a resident who is also one of the complainants, said. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Use an AI Writing Tool That Actually Understands Your Voice Grammarly Install Now Undo A single judge bench of Justice Rohit Ranjan Agarwal, in an order dated Dec 20, 2023, said, "The vice-chairman is to initiate/conduct an inquiry against the subordinate staff who are responsible for monitoring the project in which an additional 134 units have been carved out against the sanctioned strength of 400 units." Last Feb, TOI reported that the internal probe by the GDA had zeroed in on some officials deputed mostly at the development authority's enforcement wing between 2008 and 2012, and notices had been served to them. Developer Pankaj Goyal, meanwhile, said he was not aware of any probe by a GDA-led panel against the project. "We did not tamper with the covered area but subdivided bigger flats to carve out 134 extra units," Goyal said. "We are for regularising the extra units as per the provisions of Building Bylaws, 2016, for which we approached the state govt and got the necessary sanction. This will be presented in the court." In 2005, the GDA approved the layout of Express Garden, allowing the construction of 400 flats on plot number 6 of Vaibhav Khand. The construction was completed between 2008-12.


Time of India
an hour ago
- Time of India
Kolkata office market sees growth in Grade A assets, PBDs
Kolkata: More than half of Kolkata's burgeoning office stock has been classified as Grade A, according to a report by property consultancy Knight Frank India (KFI) in its report "A Billion Sq Ft and Counting – India Office Supply Growth Story" released on Monday. "This is a clear indication of the region's focus on quality-led development," said KFI senior director (occupier strategy & solutions) Joydeep Paul. Further, 71% of Kolkata's office stock is now concentrated in peripheral business districts (PBDs) such as Salt Lake Sector V and New Town, underlining the city's structural shift from legacy central business districts (CBDs) to well-connected, cost-efficient suburban office corridors. You Can Also Check: Kolkata AQI | Weather in Kolkata | Bank Holidays in Kolkata | Public Holidays in Kolkata Kolkata currently accounts for 3% of India's total office space. But developers say that with Kolkata steadily evolving as a business destination, the share is set to rise. In the past decade, the office market in Kolkata witnessed a compound annual growth rate (CAGR) of 3.2%, fuelled by infrastructure upgrades, increased interest from regional headquarters of national and global companies and rising occupier confidence. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Learn 57+ Languages Easily with AI [Join] Talkpal AI Undo "Kolkata may be smaller in terms of absolute office stock, but it's steadily building a strong foundation for future growth. With the majority of supply in PBDs and a growing share of Grade A assets, the city presents compelling opportunities for occupiers seeking quality spaces at attractive costs. The emergence of new corridors, and increased occupier diversification signal a positive shift in the market's trajectory," said Paul. Demand in Kolkata was largely driven by IT/ITES, BFSI, flex spaces, and regional headquarters of national conglomerates. A growing startup ecosystem and rising interest from coworking players has added to the city's absorption pipeline. While close to three-fourths of the office market stock concentrated in PBDs, traditional CBDs including Park Street, Camac Street, and Esplanade comprise 20% of the stock, while secondary business districts (SBDs) like EM Bypass, Topsia and Anandapur contribute 8%. Though Kolkata's high Grade A office stock is in line with the national average, the city also held the highest share of Grade C stock among top office markets at 11%, highlighting the opportunity for asset upgrade and retrofitting to meet modern occupier expectations. Grade B stock comprised 37% of the city's total office space. Kolkata continued to offer attractive rental economics, with CBD rents ranging from Rs 70–105/sq ft, SBDs from Rs 55–95/sq ft, and PBDs from Rs 27–65/sq ft, reinforcing its sub-dollar competitiveness in global benchmarks.