Telangana asks Centre to direct AP to restore RLIS site to pre-DPR stage
In a letter to the ministry, the officials also requested that either the MoEF&CC or the Krishna River Management Board (KRMB) monitor daily activities at the RLIS site and submit fortnightly compliance reports to the National Green Tribunal (NGT).
They pointed out that the NGT had stayed construction work on RLIS and constituted a joint committee to assess the situation. However, the Andhra Pradesh government allegedly continued construction in violation of the NGT order.
The Telangana officials recalled that the joint committee, in its March 2024 report to the NGT, noted that the project proponent had undertaken works beyond DPR preparation.
Excavation was reportedly completed up to 14.14% for the approach channel and 87.03% for the pump house and related works, totalling 18.18% of the proposed excavation.
'Self-certification not applicable'
Since the works exceeded the scope of DPR preparation, the officials argued that self-certification by the project proponent, as discussed in the EAC's 25th meeting, was not applicable. They urged that this clause be removed from the EAC recommendations and replaced with a site inspection report by a competent authority.
Reiterating their demand, the Telangana officials called for immediate restoration of the RLIS site to its pre-DPR stage to safeguard the legitimate rights of Telangana in the Krishna basin.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
an hour ago
- Time of India
Govt to penalise consultants not making proper DPRs, says Nitin Gadkari
Union Minister Nitin Gadkari on Tuesday said the government will penalise those consultants who do not adhere to proper procedures in making detailed project reports (DPRs) for highways and tunnels . A DPR is a comprehensive blueprint for a road construction project, outlining all technical, financial and logistics details necessary for its execution. "In India, quality of DPRs prepared by consultancy firms is not good. And also, contractors are not doing good job," Gadkari said at an event here. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Científica argentina revela hallazgos sobre el magnesio Salud Esencial Leer más Undo "We have started rating consultants who are involved in DPR who are making good DPRs will be rewarded and those who are not adhering to proper procedures will be penalised," the road transport and highways minister said. Gadkari also stressed on the need of socio-economic audit of Corporate Social Responsibility (CSR) funds. Live Events He noted that CSR funds should be used to help economic and social backward people of the country. "CSR funds should be used to help people in education, agriculture and health sectors," Gadkari said.


Indian Express
2 hours ago
- Indian Express
Amid Chandigarh MC's financial woes, development activities take a backseat
Developmental activities continue to bear the brunt of the Municipal Corporation's severe financial crunch. For the past several months, meetings of the Finance and Contract Committee (F&CC) as well as the General House have been marked by a conspicuous absence of major development-related agendas. Instead of focusing on infrastructural growth, civic improvement, or urban planning, the meetings are now largely limited to routine administrative discussions and minor proposals. According to officials, the financial strain is primarily due to limited revenue generation and mounting expenditure, compounded by a delay in receiving grants from the UT administration and the Centre. This fund shortage has brought many projects to a standstill, including essential works like road repairs, new community centres, upgrading water supply systems, and the Smart City-related initiatives. Even ward-level development requests by councillors are being deferred indefinitely, further adding to the frustration among public representatives and residents. Sources in the MC indicate that repeated attempts have been made to seek special financial assistance or relaxation in fund usage guidelines from higher authorities, but to no avail so far. The situation shows no signs of improvement in the near future, as the civic body continues to struggle with liabilities and lacks a concrete recovery plan. Councillors across party lines have raised concerns over the administrative standstill, warning that the growing developmental backlog could lead to long-term civic distress. With the city's urban infrastructure already under stress, the absence of capital investment threatens to derail Chandigarh's growth trajectory. Deputy Mayor Taruna Mehta said that apart from the House, at the F&CC meetings, no new development agendas are being discussed. 'Even the agendas for development in the previous F&CC meetings have not been executed,' she added. 'The administration and the central government, which has to release the funds is of the BJP, and the mayor is also from BJP, but the funds are yet not been released to Chandigarh, though the mayor has been asking for the funds repeatedly from the Administration and Centre. As per the 4th Delhi Finance Commission, nearly Rs 1,700 crore should have been released, but the funds released for this financial year were just Rs 625 crore, which is even less than the 3rd Delhi Finance Commission, so how can the MC work for development of the city?' Mehta highlighted. Senior Deputy Mayor Jasbir Singh Bunty said that the condition of the roads, the dumping ground and parks, shows that there is no development in the city. 'Only there is a fund available to pay salaries to the employees of MC. For the past two years there has been no recarpeting of the roads in the city. Since funds are unavailable, the development has completely stopped,' Bunty added. According to Bunty, unless a financial revival package is formulated or new revenue streams are tapped, the MC may continue to 'remain paralysed, leaving residents to bear the brunt of stagnated development'. Meanwhile, FOSWAC president Baljinder Singh Bittu said that people have been hearing about the fund crisis of the MC for a long period now. 'If they cannot run the corporation, it shall be shut. How long will the city suffer, with bad roads and ill-maintained civic issues?' Bittu added. Mayor Harpreet Kaur Babla said, 'There has been no money for the last one-and- a-half years, and no development work was done. But now things have started moving, as in village areas of city, Rs 50 lakh funds have been released, and I am hopeful that things are going to become better. There is also an additional budget grant coming which will help us for development.' Mayor Babla has also been appealing for increased financial support from the Chandigarh Administration. The Mayor has already written two letters to Union Territory Administrator Gulab Chand Kataria in May, urging allocation of funds for critical infrastructure maintenance in the city and its villages.


India Today
2 hours ago
- India Today
Third airport in Mumbai? Vadhavan offshore project may begin by 2026
At an aviation conference in Mumbai on Friday, Maharashtra Chief Minister Devendra Fadnavis shared that the much-talked-about Vadhavan offshore airport project could begin work as early as 2026. This ambitious plan aims to make Vadhavan the third airport in the Mumbai Metropolitan Region (MMR) after Mumbai's existing airport and the upcoming Navi Mumbai International airport project, estimated at Rs 76,220 crore, was first announced by Prime Minister Narendra Modi in November 2023. Now, the state government has appointed an agency to prepare the Detailed Project Report (DPR). A pre-feasibility study is already underway to explore the possibilities of building an offshore runway and full-scale airport infrastructure off the Vadhavan said, 'We've appointed an agency to work on the Detailed Project Report (DPR). Vadhavan airport will be the Mumbai Metropolitan Region's (MMR) third airport. When we can reclaim land and build an offshore port at Vadhavan, why not build an offshore airport as well.'WHY VADHAVAN? Currently, all flights to and from Mumbai operate on a single runway, putting massive pressure on Chhatrapati Shivaji Maharaj International Airport. Although work is ongoing on the Navi Mumbai airport—which will be the second airport for the region—the future need for expanded aviation capacity is located in the Palghar district of Maharashtra, has already been chosen as the site for India's largest upcoming seaport, the Vadhavan Port, which was approved by the Union Cabinet in June 2024. This massive port project will be implemented by a special purpose vehicle called Vadhavan Port Project Limited (VPPL), jointly owned by Jawaharlal Nehru Port Authority (JNPA) with a 74 per cent stake and the Maharashtra Maritime Board (MMB) holding 26 per logic behind developing an offshore airport in Vadhavan lies in the area's transformation into a mega infrastructure hub. With land already being reclaimed for the seaport, the state government believes it's a logical next step to add an airport alongside it. The twin developments are likely to reduce congestion in Mumbai and help decentralise traffic in the Mumbai Metropolitan Vadhavan offshore airport is still in its early stages. After the feasibility study and DPR are finalised, further clearances and funding will be required before construction begins. But if all goes according to the plan, ground work could begin by 2026.- Ends