New Papar sub-station, meters for Inanam: SE

New Papar sub-station, meters for Inanam: SE

Daily Express3 days ago

Published on: Wednesday, June 25, 2025
Published on: Wed, Jun 25, 2025
By: Sidney Skinner Text Size: A new substation is coming up along this section of the access road to Kg Kawakahan. SABAH Electricity (SE) has begun building a new substation near a Papar village and is in the midst of processing applications for meters at some low-cost flats in Inanam. This action was prompted by feedback about the power irregularities in Kg Kawakahan, as well as the delay which some occupants of the 'Projek Perumahan Rakyat (PPR, People's Housing Project)' Kionsom had experienced in having a supply extended to their units. A Papar consumer was under the impression that her village might not be receiving enough electricity as her household appliances had not been operating at their maximum capacity for some time. An Inanam senior citizen, on the other hand, was dismayed to find that there was still no electricity in her flat, more than 10 days after she had applied for a supply. Both individuals provided Hotline with the pertinent details regarding their grievances, which were forwarded to the company. A SE spokesman said about 20 per cent of the substation had been completed so far, since construction got underway on May 19.
Advertisement 'Barring any unforeseen circumstances, we tentatively hope to finish the remaining 80 per cent of the work by October 16,' he said. 'The nominal level of the voltage to our customers in Kg Kawakahan should increase to around 230volts, once the substation becomes operational.' He explained that a voltage drop was to blame for the electricity woes in this part of the district. 'The existing substation is located about 2.5 kilometres away from the village. It generates between 210V and 215V during the peak period of electricity usage He said the problems in Kg Kawakahan stemmed from the increasing development taking place around Papar. The spokesman said SE had been aware about the irregularities in the village since last year. 'We refurbished the existing transformer and, for a time, the situation seemed to stabilise. 'Later, we carried out a load-shedding exercise and even tried having new overhead lines put in place to service the village.' 'In January, our technicians changed the tapping points for some of these premises to a different phase.' He said each of these strategies did not provide its consumers with lasting improvements. Meanwhile, SE's effort to provide PPR Kionsom occupants with power was partly held up due to the management company's (MC's) failure to complete the 'tagging' at the cabinets prepared for the meters. A SE spokeswoman said the MC was informed that the 'tagging' was still outstanding a whole fortnight before the keys were handed out to the first group of tenants in the middle of June. 'Tagging involves applying labels, tags or seals to the cabinets for identification, security and proper management of the meters,' she said. 'The tags help prevent tampering, ensure accurate billing and facilitate meter maintenance.' She said the oversight involving the tagging was only addressed after some of those who received their keys began grousing about their failure to receive an electricity supply, let alone have meters installed for their units. 'Once the tagging was done, our technicians immediately went in to have meters put in place for those whose applications had been approved. 'In some cases, the processing of these applications was delayed because of incomplete documentation, including the failure to provide signed copies of the tenancy agreements.' A spokesman for DBKK Holdings Sdn Bhd, the MC for the flats, said a miscommunication between the firm and its appointed contractor was to blame for the hold up with the tagging. 'A check of our records shows that, as of June 18, keys had been given out for 43 units whose tenants had paid their deposits,' he said. 'To date, occupational certificates have been issued for about 400 units.' He said PPR Kionsom comprised 1000 units overall, with DBKK Holdings tentatively targeting completion of the remaining flats by August. DBKK Holdings Sdn Bhd is the corporate arm of City Hall. * Follow us on our official WhatsApp channel and Telegram for breaking news alerts and key updates! * Do you have access to the Daily Express e-paper and online exclusive news? Check out subscription plans available.
Stay up-to-date by following Daily Express's Telegram channel. Daily Express Malaysia

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Telco woes in Ulu Kimanis village
Telco woes in Ulu Kimanis village

Daily Express

timea day ago

  • Daily Express

Telco woes in Ulu Kimanis village

Published on: Friday, June 27, 2025 Published on: Fri, Jun 27, 2025 By: Sidney Skinner Text Size: Subscribers in this Ulu Kimanis village were unable to use their service almost two weeks recently. A Papar handphone user has expressed her displeasure about poor coverage in one part of the district, while a Penampang employee is hoping that more care will be taken to look after the telecommunications installations near her office. The former shared her frustrations about the service outage at her village in the Ulu Kimanis area. The office-worker, on the other hand, was perturbed by a phone pole which was leaning over at a 45 degree angle off a section of Jalan Penampang. Both individuals provided Hotline with the pertinent details regarding their grievances. This information was forwarded to CelcomDigi and Telekom Malaysia (TM) Bhd. A CelcomDigi spokesperson said a preliminary check was made of the installation in the vicinity of the subscriber's village shortly after the company was contacted by the media. 'Our technical team was immediately deployed to assess the network signal in the customer's area,' the spokesperson said. 'The issue was resolved on the spot and the signal coverage was subsequently restored.' She said its personnel later confirmed that subscriber's handphone service was functioning as it should. 'Nevertheless, we will continue to monitor the network quality in the area to ensure consistent coverage.' GANESH of Papar said he was unable to use his handphone to make calls or access the Internet in Kg Toboon Minansar for days at a time. He said this had been going on for 'the past fortnight'. 'I can receive messages via whatsapp. However, I have noticed that there is a substantial delay between when they are first sent to me and when they appear on my phone,' he said. 'A friend who lives in Penampang sent me a request around 8.10pm on a recent Friday night. Her message only registered in my whatsapp about 45 minutes later.' He said his telecommunications services only functioned like normal when he reached the nearest main road. 'I have to make a two to three-minute drive from my house just to be able to use my handphone, which I feel is a ridiculous inconvenience.' Ganesh said he shared his handphone woes with several of his neighbours. Those among them, who also used CelcomDigi, expressed similar frustrations about the poor coverage, according to him. 'It is especially disappointing that the company's lines should malfunction like this. I fear that I will not be able to call for help if there is an emergency at home.' Meanwhile, TM staff have been asked to make periodic checks of the condition of its assets in Penampang, including those on the vegre along the main road leading to Donggongon. The firm recently dealt with a problem involving a pole which was bending towards the compound for a commercial premises dealing in hardware, plumbing and heating equipment at Mile 6 Jalan Penampang. A TM spokesman said the relevant section was alerted to what was happening in this part of the district. 'Our technicians confirmed that the pole was no longer upright a few days later,' he said. 'They set about repositioning the structure on the spot. A stay-wire was put in place to provide the pole with additional support.' He said the team also attended to any low-hanging cables in the area. 'We wanted to ensure that these lines did not droop down over the road shoulder or parking area for the commercial building in question.' EVAN, who works at the Penampang company, said his employers were worried about the potential property damage which they could incur if the pole were to fall. 'Several of our customers have already remarked that the pole seems to be edging closer and closer towards our compound,' he said. 'When the pole topples, there will be less space for the staff and shoppers to park their vehicles, let alone for us to store our bigger items.' * Follow us on our official WhatsApp channel and Telegram for breaking news alerts and key updates! * Do you have access to the Daily Express e-paper and online exclusive news? Check out subscription plans available. Stay up-to-date by following Daily Express's Telegram channel. Daily Express Malaysia

New Papar sub-station, meters for Inanam: SE
New Papar sub-station, meters for Inanam: SE

Daily Express

time3 days ago

  • Daily Express

New Papar sub-station, meters for Inanam: SE

Published on: Wednesday, June 25, 2025 Published on: Wed, Jun 25, 2025 By: Sidney Skinner Text Size: A new substation is coming up along this section of the access road to Kg Kawakahan. SABAH Electricity (SE) has begun building a new substation near a Papar village and is in the midst of processing applications for meters at some low-cost flats in Inanam. This action was prompted by feedback about the power irregularities in Kg Kawakahan, as well as the delay which some occupants of the 'Projek Perumahan Rakyat (PPR, People's Housing Project)' Kionsom had experienced in having a supply extended to their units. A Papar consumer was under the impression that her village might not be receiving enough electricity as her household appliances had not been operating at their maximum capacity for some time. An Inanam senior citizen, on the other hand, was dismayed to find that there was still no electricity in her flat, more than 10 days after she had applied for a supply. Both individuals provided Hotline with the pertinent details regarding their grievances, which were forwarded to the company. A SE spokesman said about 20 per cent of the substation had been completed so far, since construction got underway on May 19. Advertisement 'Barring any unforeseen circumstances, we tentatively hope to finish the remaining 80 per cent of the work by October 16,' he said. 'The nominal level of the voltage to our customers in Kg Kawakahan should increase to around 230volts, once the substation becomes operational.' He explained that a voltage drop was to blame for the electricity woes in this part of the district. 'The existing substation is located about 2.5 kilometres away from the village. It generates between 210V and 215V during the peak period of electricity usage He said the problems in Kg Kawakahan stemmed from the increasing development taking place around Papar. The spokesman said SE had been aware about the irregularities in the village since last year. 'We refurbished the existing transformer and, for a time, the situation seemed to stabilise. 'Later, we carried out a load-shedding exercise and even tried having new overhead lines put in place to service the village.' 'In January, our technicians changed the tapping points for some of these premises to a different phase.' He said each of these strategies did not provide its consumers with lasting improvements. Meanwhile, SE's effort to provide PPR Kionsom occupants with power was partly held up due to the management company's (MC's) failure to complete the 'tagging' at the cabinets prepared for the meters. A SE spokeswoman said the MC was informed that the 'tagging' was still outstanding a whole fortnight before the keys were handed out to the first group of tenants in the middle of June. 'Tagging involves applying labels, tags or seals to the cabinets for identification, security and proper management of the meters,' she said. 'The tags help prevent tampering, ensure accurate billing and facilitate meter maintenance.' She said the oversight involving the tagging was only addressed after some of those who received their keys began grousing about their failure to receive an electricity supply, let alone have meters installed for their units. 'Once the tagging was done, our technicians immediately went in to have meters put in place for those whose applications had been approved. 'In some cases, the processing of these applications was delayed because of incomplete documentation, including the failure to provide signed copies of the tenancy agreements.' A spokesman for DBKK Holdings Sdn Bhd, the MC for the flats, said a miscommunication between the firm and its appointed contractor was to blame for the hold up with the tagging. 'A check of our records shows that, as of June 18, keys had been given out for 43 units whose tenants had paid their deposits,' he said. 'To date, occupational certificates have been issued for about 400 units.' He said PPR Kionsom comprised 1000 units overall, with DBKK Holdings tentatively targeting completion of the remaining flats by August. DBKK Holdings Sdn Bhd is the corporate arm of City Hall. * Follow us on our official WhatsApp channel and Telegram for breaking news alerts and key updates! * Do you have access to the Daily Express e-paper and online exclusive news? Check out subscription plans available. Stay up-to-date by following Daily Express's Telegram channel. Daily Express Malaysia

No hidden increases of power tariff in Sabah - ECoS
No hidden increases of power tariff in Sabah - ECoS

Borneo Post

time4 days ago

  • Borneo Post

No hidden increases of power tariff in Sabah - ECoS

KOTA KINABALU (June 24): The Energy Commission of Sabah (ECoS) refers to a recent statement made by Warisan Kota Kinabalu Division Information Chief, Samuel Wong, regarding alleged hidden increases in electricity tariffs through the tiered rate structure. ECoS wishes to state that the tariff structure and rates have not been revised since the last tariff revision in 2014. The schedule of tariff structure and rates for Sabah and Labuan (effective 1 January 2014) can be obtained from Sabah Electricity Sdn Bhd's website. Consumers are reassured that they will only be charged the rate of 47 sen/kWh for units above 1,000 units, i.e. monthly bill above RM383, and this has been in effect since 1 January 2014. Samuel, or any concerned member of the public, are urged to present abnormal bills not in accordance with the gazetted tariff blocks and rates to ECoS for investigation. If there is any error or negligence on the part of Sabah Electricity Sdn Bhd (SE), ECoS will investigate and rectify accordingly. In the interest of transparency and accountability, ECoS strongly encourages the public to use its official complaints and clarification platform, Talk2ECoS, especially in cases where consumers are unable to receive adequate responses from licensees such as SE. ECoS reiterates its commitment to safeguard consumer rights and ensure fair electricity pricing, while continuing to support efforts that strengthen the reliability and sustainability of Sabah's power supply.