Samal-Davao City bridge construction progress at 38% —DPWH

Samal-Davao City bridge construction progress at 38% —DPWH

GMA Networka day ago

The Department of Public Works and Highways (DPWH) on Saturday said the progress rate of the ongoing construction of the Samal Island–Davao City Connector (SIDC) Bridge is now at 38%.
In a news release, DPWH said that the SIDC project has surpassed its target accomplishment rate of 16%, 'reflecting a positive slippage of 22%.'
The project is being funded through the Official Development Assistance (ODA) from China.
DPWH Unified Project Management Office – Bridges Management Cluster (UPMO-BMC) is the project's implementing agency, with China Road and Bridge Corporation as the contractor.
The SIDC would be a toll-free, four-lane extradosed bridge spanning 4.76 kilometers, linking Davao City at the R. Castillo–Daang Maharlika Junction to the Samal Circumferential Road.
The bridge will feature a 275-meter main span and a 47-meter vertical clearance to accommodate marine vessels.
Its marine crossing section will stretch 1.62 kilometers across the water, supported by two pylons, each standing 73 meters above sea level.
The complete bridge design also includes roundabouts, ramps, and approach roads.
The DPWH outlined the specific progress in the project's various components, such as bored piling on the Davao side of the land viaduct, with 73 out of 110 bored piles completed, representing 66.36% completion, while all bored piles on the Samal side were completed.
Also completed was the bored piling for the navigation bridge.
The seal concrete installation for the navigation portion is ongoing on the Davao side, while the Samal side has already been completed.
In terms of marine viaduct construction, the DPWH said the Davao side has completed 12 of 32 bored piles, or 37.5%, and the Samal side has completed 11 of 44, or 25%.
The ramp construction on the Davao side has also seen steady progress, with 60 out of 133 piles completed, equivalent to 45.11%.
For the pile cap installations, 11 out of 26 pile caps have been completed on the Davao side of the land viaduct, while 5 out of 16 pile caps have been finished on the Samal side.
In preparation for road widening along Daang Maharlika, the DPWH said fencing installation and removal of existing structures and obstructions have been completed.
Meanwhile, the Davao Light and Power Company (DLPC) has finalized the installation of primary and secondary distribution lines and is currently awaiting energization.
On right-of-way acquisition, the DPWH said a total of 61 out of 69 or 88% of affected lots in Davao City and Samal Island have already been acquired.
For affected structures in Davao City, 22 out of 51 or 43% have been secured, while the rest are currently undergoing acquisition procedures. — VBL, GMA Integrated News

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Samal-Davao City bridge construction progress at 38% —DPWH
Samal-Davao City bridge construction progress at 38% —DPWH

GMA Network

timea day ago

  • GMA Network

Samal-Davao City bridge construction progress at 38% —DPWH

The Department of Public Works and Highways (DPWH) on Saturday said the progress rate of the ongoing construction of the Samal Island–Davao City Connector (SIDC) Bridge is now at 38%. In a news release, DPWH said that the SIDC project has surpassed its target accomplishment rate of 16%, 'reflecting a positive slippage of 22%.' The project is being funded through the Official Development Assistance (ODA) from China. DPWH Unified Project Management Office – Bridges Management Cluster (UPMO-BMC) is the project's implementing agency, with China Road and Bridge Corporation as the contractor. The SIDC would be a toll-free, four-lane extradosed bridge spanning 4.76 kilometers, linking Davao City at the R. Castillo–Daang Maharlika Junction to the Samal Circumferential Road. The bridge will feature a 275-meter main span and a 47-meter vertical clearance to accommodate marine vessels. Its marine crossing section will stretch 1.62 kilometers across the water, supported by two pylons, each standing 73 meters above sea level. The complete bridge design also includes roundabouts, ramps, and approach roads. The DPWH outlined the specific progress in the project's various components, such as bored piling on the Davao side of the land viaduct, with 73 out of 110 bored piles completed, representing 66.36% completion, while all bored piles on the Samal side were completed. Also completed was the bored piling for the navigation bridge. The seal concrete installation for the navigation portion is ongoing on the Davao side, while the Samal side has already been completed. In terms of marine viaduct construction, the DPWH said the Davao side has completed 12 of 32 bored piles, or 37.5%, and the Samal side has completed 11 of 44, or 25%. The ramp construction on the Davao side has also seen steady progress, with 60 out of 133 piles completed, equivalent to 45.11%. For the pile cap installations, 11 out of 26 pile caps have been completed on the Davao side of the land viaduct, while 5 out of 16 pile caps have been finished on the Samal side. In preparation for road widening along Daang Maharlika, the DPWH said fencing installation and removal of existing structures and obstructions have been completed. Meanwhile, the Davao Light and Power Company (DLPC) has finalized the installation of primary and secondary distribution lines and is currently awaiting energization. On right-of-way acquisition, the DPWH said a total of 61 out of 69 or 88% of affected lots in Davao City and Samal Island have already been acquired. For affected structures in Davao City, 22 out of 51 or 43% have been secured, while the rest are currently undergoing acquisition procedures. — VBL, GMA Integrated News

Davao bypass project to help stimulate Mindanao's economy
Davao bypass project to help stimulate Mindanao's economy

GMA Network

time5 days ago

  • GMA Network

Davao bypass project to help stimulate Mindanao's economy

Japanese Ambassador to the Philippines Endo Kazuya lauded the Davao City Bypass Construction Project, saying that it will help enhance the economic activity in the southern portion of the Philippines. Kazuya branded it as a testament to Japan's commitment in enhancing connectivity in Mindanao. 'Upon completion, the project is expected to significantly reduce travel time, enhance mobility, and stimulate economic activity across Mindanao,' Kazuya said in a press release issued Tuesday. The envoy highlighted that the 2.3-kilometer tunnel stands as the longest mountain tunnel in the Philippines, marking a significant milestone in the country's road infrastructure. The tunnel connection marks a pivotal point in the overall construction phase, according to Kazuya. 'This cooperation between Manila and Tokyo's is a prime example of our nation's shared commitment to building infrastructure that meets the highest standards of quality, safety, and sustainability,' Kazuya said. Kazuya had visited the Davao City Bypass Construction Project and inspected the tunnel excavation site. The Davao City Bypass is the latest in the long line of high-impact infrastructure collaborations between Japan and the Philippines, dating back to the Philippine-Japan Friendship Highway. The Philippines and Japan, through the Japan International Cooperation Agency, had signed five loan agreements totaling over ¥171 billion to support key infrastructure and development projects. This included the Davao City Bypass Construction Project (Phase III), worth ¥46.338 billion. To recall, Japan remains the country's top Official Development Assistance (ODA) partner, with ongoing support in transport, disaster risk reduction, environmental protection, and peace-building efforts, particularly in the Mindanao region. —VAL, GMA Integrated News

P20 rice launched for minimum wage earners in Davao del Sur
P20 rice launched for minimum wage earners in Davao del Sur

GMA Network

time15-06-2025

  • GMA Network

P20 rice launched for minimum wage earners in Davao del Sur

The Department of Labor and Employment-Davao (DOLE-11), in partnership with the Department of Agriculture (DA) XI, launched the P20-per-kilo rice program in Hagonoy, Davao del Sur on Thursday, June 13, 2025. A total of 4,000 kilos of rice were repacked and sold to 400 minimum wage workers employed at a sugarcane farm under the Davao Mill District Development Council Foundation, Inc., which also serves as the partner organization for the program's launch. DOLE-11 Director, Atty. Randolf Pensoy, said the affordable rice initiative is currently available to vulnerable sectors, including senior citizens, persons with disabilities (PWDs), and beneficiaries of the Department of Social Welfare and Development's (DSWD) Pantawid Pamilyang Pilipino Program (4Ps). However, DOLE aims to extend the program's reach to include minimum wage earners. Employers, labor organizations, or workers' associations interested in availing of the program must sign a memorandum of agreement (MOA) with Food Terminal Inc. (FTI). Once the agreement is in place, FTI will purchase rice from the National Food Authority (NFA) and distribute it to the beneficiaries for P20 per kilo. —GMA Regional TV News

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store