KUALA LUMPUR: Malakoff Corp Bhd, via its subsidiary Sungai Udang WTE Sdn Bhd, has signed a concession agreement under a public-private partnership framework with the government.
The deal involves the design, construction, financing, operation, maintenance, and eventual closure of a waste-to-energy (WTE) facility located in Sungai Udang, Melaka.
Sungai Udang WTE is a special-purpose joint venture for the project, with Malakoff holding a 60 per cent stake, while the remaining 40 per cent is owned by Alam Flora Environmental Solutions Sdn Bhd (AFES).
AFES is a wholly-owned subsidiary of Alam Flora Sdn Bhd, which is 97.37 per cent owned by Malakoff.
In a statement, Malakoff said the WTE facility is designed to process up to 1,056 tonnes of municipal solid waste daily and will produce around 22 megawatts of gross renewable energy.
This will be done under a power purchase agreement to be signed between Tenaga Nasional Bhd and the concession company.
Managing director and group chief executive officer Anwar Syahrin Abdul Ajib said the facility plays a crucial role in tackling Melaka's pressing waste management challenges, especially as the state's sole sanitary landfill approaches full capacity.
"By diverting over 300,000 tonnes of waste from landfills annually, the plant is expected to eliminate 75,000 tonnes of carbon dioxide emissions, which is equivalent to preserving more than 3.4 million trees and preventing 23,000 cubic metres of leachate from polluting local waterways.
"Malakoff currently manages 3,649 tonnes of waste per day. With this project expected to add another 1,056 tonnes daily, we will have the capacity to manage up to 6,206 tonnes per day based on our existing contracts, concession agreements and available assets," he said.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Over 12,000 objections to EIA report on Batu Arang plant
Over 12,000 objections to EIA report on Batu Arang plant

The Star

time14 hours ago

  • The Star

Over 12,000 objections to EIA report on Batu Arang plant

JRTI members and other NGOs submitting the 12,150 objection forms in response to the EIA report on the proposed WTE in Batu Arang to a DOE representative (wearing headscarf). — FAIHAN GHANI/The Star FOLLOWING the announcement of a proposed merger of two waste-to-energy (WTE) plants in Selangor, action group Jaringan Rawang Tolak Insinerator (JRTI) believes autho­rities intend to proceed with the Batu Arang project while merging plants at two other locations. 'There are currently three state-­­­initiated incinerator projects – in Jeram (Kuala Selangor), Tanjung Dua Belas (Kuala Langat) and Batu Arang (Rawang) – plus another by the Federal Govern­ment in Taman Pelangi (Rawang). 'The Jeram project is being built while the others are at the proposal stage,' said JRTI spokesperson Abdul Hanan Abd Mokti. He added that their interpretation of reports on the merger was that the government intended to proceed with the Batu Arang incinerator plant while merging the Jeram and Taman Pelangi projects. Selangor Mentri Besar Datuk Seri Amirudin Shari had said the state government was ready to discuss the merger of the two WTE projects to strengthen sustainable solid waste management in the state. He had said the plants were located in Rawang and Jeram, although there had been conflicting reports on the exact location of the Rawang plant. Abdul Hanan submitted 12,150 objection forms in response to the environmental impact assessment (EIA) report on the proposed WTE in Batu Arang. The forms were submitted to the Department of Environment (DOE) at Menara Petra, Pre­cinct 4, Putrajaya. The proposed RM4.5bil project in Batu Arang, also known as Sultan Idris Shah Green Energy Park (SISGEP), has received widespread objections from residents in the surrounding areas of Batu Arang, Bandar Tasik Puteri, Kota Puteri and Bandar Seri Coalfields. Abdul Hanan said JRTI, two other non-governmental organisations, Persatuan Keseda­ran and Pendidikan 3R Kuala Lumpur and Persatuan Keles­tarian Warisan dan Alam Batu Arang engaged experts to res­pond on aspects such as geology, public health and environment. 'We also received public feedback through physical and online forms.' The group, he said, was concerned about the proposed Batu Arang project for several reasons, including potential health risks, traffic hazards, environmental impact and impact on property value. 'Batu Arang sits on a former coal mine connected by a network of tunnels, while the incinerator plant will sit on a former open-cast coal mine. 'Their locations could affect the geological stability of the area.'

Malakoff signs Sungai Udang WTE concession in Melaka
Malakoff signs Sungai Udang WTE concession in Melaka

New Straits Times

time6 days ago

  • New Straits Times

Malakoff signs Sungai Udang WTE concession in Melaka

KUALA LUMPUR: Malakoff Corp Bhd, via its subsidiary Sungai Udang WTE Sdn Bhd, has signed a concession agreement under a public-private partnership framework with the government. The deal involves the design, construction, financing, operation, maintenance, and eventual closure of a waste-to-energy (WTE) facility located in Sungai Udang, Melaka. Sungai Udang WTE is a special-purpose joint venture for the project, with Malakoff holding a 60 per cent stake, while the remaining 40 per cent is owned by Alam Flora Environmental Solutions Sdn Bhd (AFES). AFES is a wholly-owned subsidiary of Alam Flora Sdn Bhd, which is 97.37 per cent owned by Malakoff. In a statement, Malakoff said the WTE facility is designed to process up to 1,056 tonnes of municipal solid waste daily and will produce around 22 megawatts of gross renewable energy. This will be done under a power purchase agreement to be signed between Tenaga Nasional Bhd and the concession company. Managing director and group chief executive officer Anwar Syahrin Abdul Ajib said the facility plays a crucial role in tackling Melaka's pressing waste management challenges, especially as the state's sole sanitary landfill approaches full capacity. "By diverting over 300,000 tonnes of waste from landfills annually, the plant is expected to eliminate 75,000 tonnes of carbon dioxide emissions, which is equivalent to preserving more than 3.4 million trees and preventing 23,000 cubic metres of leachate from polluting local waterways. "Malakoff currently manages 3,649 tonnes of waste per day. With this project expected to add another 1,056 tonnes daily, we will have the capacity to manage up to 6,206 tonnes per day based on our existing contracts, concession agreements and available assets," he said.

Melaka Thanks Federal Government For RM660 Mln WTE Project
Melaka Thanks Federal Government For RM660 Mln WTE Project

Barnama

time22-06-2025

  • Barnama

Melaka Thanks Federal Government For RM660 Mln WTE Project

MELAKA, June 22 (Bernama) -- The Melaka government has expressed its appreciation to the Federal Government for approving the RM660 million Waste-To-Energy (WTE) plant project in Sungai Udang, expected to be completed by 2029. State Housing, Local Government, Drainage, Climate Change and Disaster Management Committee chairman Datuk Rais Yasin said a groundbreaking ceremony will be held soon and officiated by Chief Minister Datuk Seri Ab Rauf Yusoh. "This project enhances the efficiency of solid waste management and supports the state's green agenda," he said during the Elected Representative for the People (WRUR) programme for the Bemban state constituency.