MN Holdings wins RM29.3mil TNB power project in Johor
In a filing with Bursa Malaysia, MN said the contract was awarded to its wholly owned subsidiary, MN Power Transmission Sdn Bhd (MNPTSB).
The contract involves the extension of two new 132-kilovolt (kV) transformer bays at the existing 132/33kV transmission main intake (PMU) at Tanjung Langsat Industrial Estate (2x90MVA), using air insulated switchgear (AIS).
MN said the contract is effective from July 3, 2025, with a completion period of 540 days from the commencement date.
MNPTSB is required to furnish a performance security of RM1.465mil, representing 5% of the contract value, within 56 days from July 3.
MN expects the contract to contribute positively to its future earnings and net assets per share upon commencement.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

The Star
a day ago
- The Star
MN Holdings wins RM29.3mil TNB power project in Johor
KUALA LUMPUR: MN Holdings Bhd has secured a RM29.3mil contract from Tenaga Nasional Bhd (TNB) for extension works at the Tanjung Langsat Industrial Estate transmission substation in Johor. In a filing with Bursa Malaysia, MN said the contract was awarded to its wholly owned subsidiary, MN Power Transmission Sdn Bhd (MNPTSB). The contract involves the extension of two new 132-kilovolt (kV) transformer bays at the existing 132/33kV transmission main intake (PMU) at Tanjung Langsat Industrial Estate (2x90MVA), using air insulated switchgear (AIS). MN said the contract is effective from July 3, 2025, with a completion period of 540 days from the commencement date. MNPTSB is required to furnish a performance security of RM1.465mil, representing 5% of the contract value, within 56 days from July 3. MN expects the contract to contribute positively to its future earnings and net assets per share upon commencement.


New Straits Times
a day ago
- New Straits Times
MN Holdings wins RM29mil TNB contract for Johor substation project
KUALA LUMPUR: MN Holdings Bhd's unit, MN Power Transmission Sdn Bhd, has secured a RM29.3 million contract from Tenaga Nasional Bhd (TNB) for a substation expansion project in Johor. In a filing with Bursa Malaysia, the company said it received the letter of award from TNB yesterday for the extension of two new 132-kilovolt transformer bays at the existing main intake substation in the Tanjung Langsat Industrial Estate. The project involves supplying, installing and commissioning the high-voltage transformer units using air-insulated switchgear technology, together with all associated civil works and secondary electrical systems. The contract, which excludes Sales and Service Tax, is scheduled to be completed within 540 days from the commencement date. MN Power Transmission is also required to furnish a performance security of RM1.47 million, equivalent to five per cent of the contract value, within 56 days of the award. Additionally, the company must procure all necessary insurance coverage, including construction all-risks, workmen's compensation, public liability and other relevant policies. "This project award reflects MN's ongoing capability and expertise in delivering power infrastructure solutions," the company said, adding that the contract is expected to contribute positively to the group's future earnings and net assets.


The Star
18-06-2025
- The Star
MN Holdings wins RM39.59mil data centre job
PETALING JAYA: MN Holdings Bhd has secured a contract from an information technology services provider (Company A) to design, supply, install, test and commission an electrical supply system for a cable landing station of a data centre in the Southern Region of Malaysia, worth RM39.59mil. In a filing with Bursa Malaysia, the infrastructure utilities and construction services provider said it was unable to disclose the identity of Company A as the company is not agreeable to provide consent for disclosure due to the non-disclosure agreement executed by the parties, which prohibits the disclosure of information in relation to the customer without prior written consent. MN Holdings said the job commenced on April 15, 2025, with the long lead equipment delivery scheduled for Sept 30, 2025. The 'power turn-on' is expected to be on Dec 30, 2025. MN Holdings said the contract will not have any effect on the issued share capital and the shareholding of the substantial shareholders of the company. However, it said the contract is expected to contribute positively to the future earnings and net assets per share of the company upon commencement of the project.